State v. Kemp Stone, Inc.

418 P.3d 708
CourtCourt of Civil Appeals of Oklahoma
DecidedNovember 1, 2017
DocketCase Number: 115380
StatusPublished
Cited by1 cases

This text of 418 P.3d 708 (State v. Kemp Stone, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Kemp Stone, Inc., 418 P.3d 708 (Okla. Ct. App. 2017).

Opinion

KEITH RAPP, JUDGE:

¶ 1 The defendant, Kemp Stone, Inc. ("Kemp Stone") appeals an Order denying its request that attorney fees and costs be assessed against the plaintiffs, The State of Oklahoma ex rel. Jaycee Calan, Lucille Calan, Kace Calan, John E. Kendall, Jr., Jacquelyne Kendall, David F. Hiebert, Jr., Edwina C. Hiebert, Kathryn Weatherby, Jaime Mills, and Travis Mills (collectively "Taxpayers").

BACKGROUND

¶ 2 This appeal arises from a qui tam action brought by Taxpayers and their inclusion of Kemp Stone in their lawsuit.1 Kemp Stone claimed that the lawsuit was frivolous as to Kemp Stone, thereby entitling it to attorney fees and costs.2

*710¶ 3 On September 26, 2011, the City of Miami, Oklahoma ("City") received a qui tam notice signed by ten persons (a sufficient number then) including Taxpayers. The notice complained that a City street project ("Project") funded by a sales tax was being unlawfully carried out. The basis of the claim was that the City took bids, used the bids as contracts, and paid out more than $50,000.00 to contractors. All of this was claimed to be in violation of the law concerning municipal contracts and competitive bidding statutes.

¶ 4 On November 23, 2011, the City filed a declaratory judgment action. Taxpayers intervened and added the qui tam action against City and named entities including Kemp Stone. The intervention petition contained detailed allegations regarding City's actions pertaining to the Project and the claimed unlawful acts by City's officials. The intervention petition alleged that the named entities received unspecified amounts of money from City for the Project and that such money should be repaid to City. The entities were not immediately served because City and Taxpayers engaged in mediation. The mediation was unsuccessful and City dismissed its declaratory judgment action before intervention was granted. Subsequent proceedings not relevant here culminated with Taxpayers filing this qui tam action.3

¶ 5 The qui tam petition recited the history of the intervention petition and alleged City's violations regarding the Project.4 The petition named the entities, including Kemp Stone, and alleged:

In furtherance of the Street Project it [Kemp Stone] submitted and was awarded a construction bid in excess of $50,000. However, it failed to enter into [a] public construction contract with the City prior to performing working and/or providing materials. Despite this Kemp Stone, Inc. received at least $50,000 for performing work and/or providing materials

City filed its Answer.5 The Answer admitted that Kemp Stone submitted a bid and performed work. City's Answer denied the remainder of the allegations about Kemp Stone.

¶ 6 Kemp Stone's Amended Answer6 denied all allegations against it. Kemp Stone alleged that it did have a contract for all of its work and materials. However, Kemp Stone denied submitting a bid or being paid any money on the Project.

¶ 7 Kemp Stone submitted request for admission to City. In response, City admitted that Kemp Stone neither submitted a bid nor had a bid approved regarding the Project and that Kemp Stone did not have a contract pertaining to the Project.7 Counsel for Kemp Stone wrote to counsel for Taxpayers a letter dated May 8, 2015, in which he advised of the receipt of City's discovery request submitted by Kemp Stone and enclosed a copy.8 Counsel described the discovery response as establishing that Kemp Stone had nothing to do with the Project. He also advised that City's attorney stated that City would amend its Answer to conform to its discovery response about Kemp Stone. City did not file the amendment.

¶ 8 Kemp Stone filed a motion for summary judgment based upon its position that it was not a bidder/contractor on the Project.

¶ 9 Prior to the hearing on Kemp Stone's summary judgment motion, Taxpayers dismissed the action as to Kemp Stone. Kemp Stone then sought attorney fees and costs on the ground that Taxpayers brought a frivolous lawsuit against Kemp Stone because Kemp Stone never had anything to do with *711the Project that could be considered actionable.

¶ 10 Taxpayers defended on the basis that a reasonable investigation preceded the filing and that the investigation revealed the existence of a claim against Kemp Stone. The investigation included an interview with City's chief financial officer ("CFO"). Taxpayers' claims about City's acts were confirmed in an audit performed by the State of Oklahoma State Auditor and Inspector. Taxpayers further argued that events following the filing served to confirm the existence of a claim, citing such as the City's Answer and its failure to amend the Answer.

¶ 11 In summary, the trial court had the following sequence of events to consider when making its ruling regarding whether the action against Kemp Stone was frivolous.

Taxpayers' Demand, Record p. 1123. Dated September 26, 2011. Set out specific unlawful acts and demands recovery of funds expended by City, but does not name parties receiving funds.
Issues referred to State Auditor and Inspector who issued an audit report dated June 19, 2013, Record p. 1139. Auditor's findings were addressed to Taxpayers and to City. The Auditor found several improper actions relating to the Project consistent with Taxpayers' demands served on City, including "multiple examples of noncompliance with the Public Competitive Bid Act."9
Prior to filing the petition, counsel for Taxpayers interviewed CFO. Affidavit, Record, p. 1186.10 According to counsel, CFO informed him that Kemp Stone was one of the Project contractors and was paid in excess of $50,000.00.
Taxpayers filed their petition on November 1, 2013, naming Kemp Stone as one contractor for the Project.
On January 6, 2016, Kemp Stone filed its answer generally alleging that it had nothing to do with Project or Taxpayers' claims.
On March 3, 2016, City filed its Answer where it admits that Kemp Store submitted a bid and performed work or provided materials for the Project.
On March 6, 2015, counsel for Kemp Stone transmitted a letter to counsel for Taxpayers that included recently received discovery responses from City where City admitted that Kemp Stone did not bid and was not an approved bidder on the Project.
City never amended its formal Answer, notwithstanding the statement from Kemp Stone's counsel that City would amend its Answer.
Taxpayers dismissed Kemp Stone on April 26, 2016.

¶ 12 The trial court ruled that taxpayers did not file a frivolous action and denied the attorney fees and costs request. Kemp Stone appeals.

STANDARD OF REVIEW

¶ 13 A trial court's denial of attorney fees that are requested based upon the opponent bringing a frivolous action is reviewed for abuse of discretion. Broadwater v. Courtney

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STATE ex rel. CALAN v. KEMP STONE, INC.
418 P.3d 708 (Court of Civil Appeals of Oklahoma, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
418 P.3d 708, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-kemp-stone-inc-oklacivapp-2017.