State v. Edwards

751 N.E.2d 510, 141 Ohio App. 3d 388
CourtOhio Court of Appeals
DecidedFebruary 12, 2001
DocketNo. 77382.
StatusPublished
Cited by10 cases

This text of 751 N.E.2d 510 (State v. Edwards) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Edwards, 751 N.E.2d 510, 141 Ohio App. 3d 388 (Ohio Ct. App. 2001).

Opinion

*390 Anne L. Kilbane, Judge.

This is an appeal from a judgment of conviction and sentence following a jury-trial before Judge Patricia Cleary. Appellant Alfred Edwards, found guilty on three felony counts of passing bad checks (R.C. 2913.11), claims that his Crim.R. 29(A) motion for acquittal should have been granted because (1) the payee knew at the time he presented the checks for payment that the checks would be dishonored, and (2) a dishonored check written for a pre-existing debt cannot constitute a violation of R.C. 2913.11. He also contends that the verdict is against the manifest weight of the evidence and that the sentence imposed is contrary to law. We reverse the judgment denying the Crim.R. 29(A) motion for acquittal and vacate the conviction and sentence.

The record reveals the following. In May 1998, Jeffrey Kolman, a construction manager and general contractor with over thirty years of experience, was hired by Edwards, Chairman and CEO of Triangle Development, Inc. (“Triangle”), to finish construction of two homes on East 81st Street in the Hough neighborhood of Cleveland. Edwards was to pay him $2,000 per month for each house, not to exceed a total of $6,000 per house, and Kolman was to bring in construction crews at a rate of $40 per man hour.

Kolman did not receive his May salary of $2,000 until early July and was told he would receive the rest of the June payment soon but he “didn’t press it for a couple of weeks” because he “knew that there were problems.”

At the same time Kolman was hired to act as construction manager, Kolman’s company, JefKol Construction Services, Inc., in conjunction with Kolman’s business associate, John DiMarco, lent Triangle $25,000 for operating expenses, secured by a mortgage on the two properties. The mortgage referenced an accompanying note, and an unsigned copy of a “note contract agreement.” Kolman explained that they had agreed upon a twenty-five percent per year interest rate on the loan, but the note was supposed to be only a “two-month note” that was to be paid on August 1, 1998 and was intended “to get [Triangle] over the hump so they could continue on with business.” When August arrived and Kolman had not been paid for his June or July work, he began to question what was happening with the funds.

Around October 15, 1998, Edwards gave Kolman three post-dated Triangle checks drawn on a BankOne checking account payable to JefKol and signed by Edwards. According to Kolman, a check dated October 23, 1998, written for $1,650, represented the amount of interest due on the loan at that time; a check dated October 28, 1998, written for $5,800, represented the amount due for his “management and carpentry” services; and a check dated October 28, 1998, written for $25,000 represented the repayment of the loan. In the letter *391 accompanying the checks, Edwards indicated that they would be made good no later than three to five working days after the dates on the checks. Kolman knew that Edwards did not have the money to cover the checks at the time they were written, and he agreed to hold the checks as requested.

About the same time as this transaction, Edwards wrote the following letter dated October 14,1998 and issued to both Kolman and Beverly Harris, the owner of Heights Title:

“This is a legal binding document, an instrument to be used by Heights Title that follows a verbal communication that transpired between Triangle Development, Inc. and Heights Title on the closing Escrow issues for 1836 East 81st Street, Bishop and Mrs. Hilton’s Home.
“This document serves as protection for JefKol & Associates Construction Co., Inc. that will assure that JefKol & Associates Construction Co., Inc. will be paid in full of the $25,000 loan made to Triangle Development, Inc. for purposes of a liquid line of credit toward construction and overhead.
“In addition to $5,800 due to Jeff Kolman for Management and Carpentry work performed at the 1836 81st Street Site, this will bring the total to be paid in the sum of $30,800. Two (2) checks have been issued to Mr. Kolman, by way of Mr. John DiMarco, Check No. 1147 ($5,800) and Check No. 1148 ($25,000) both dated October 28,1998.
“We only request that Mr. Kolman check with Mrs. Beverly Harris, Owner of Heights Title[,] to assure her deposit on closing of Heights Title.
“There is nothing that could be said verbally or performed physically that could stop this transaction. The only thing that may change might be a date, plus or minus three to five (3-5) working business days in case of additional due diligence from National City Bank.”

Kolman admitted that he knew, within a few days after receiving the checks, that he was supposed to receive payment of the money due him from funds resulting from the closing escrow of the Hiltons’ home rather than the checks: ‘We were to be paid on the 28th and then he [Edwards] changed the rules three days later.”

On October 21, 1998, Edwards penned yet another letter, this time to JefKol’s attorney:

“I spoke to Beverly Harris, President of Heights Title[,] and it has been confirmed to pay your client out of Escrow and[,] as you are aware, they have been given checks totaling over $32,000. Those checks were put into the hands of John DiMarco.
«* Hí *
*392 “PS: As your client, John DiMarco, was told before cashing the checks given to him, he must wait until Escrow with Heights Title and the money transfer.” (Underlining original.)

Kolman did not deposit the checks on the 28th because, upon speaking with Harris, he learned there were some “continuing problems” with the bank so he waited until November 4, 1998, to deposit them. He admitted that he had doubts about whether the property would close as scheduled but said, “It was difficult to get a straight answer from Triangle Development, so I went and deposited them at that point to see if they were good. I assumed he would make good on his word and the paperwork that he had given me.”

He admitted that he had “doubts” that the checks would clear and, therefore, before depositing the checks into a business checking account, Kolman asked for advice on what “recourse” he had when “somebody is stonewalling” him on paying checks. The bank representative told him that he had to deposit them, otherwise he would be unable to pursue a civil claim against Triangle. His bank contacted him a week later, informing him that the three Triangle checks were returned for nonsufficient funds. Kolman said he did not write any checks on JefKol’s business account because he “just wanted to make sure that the checks cleared before [he] did anything like that.” The bank returned the dishonored checks to him, and he began questioning Edwards about his payment.

Sometime in early December, Kolman claimed that Edwards had told him that Triangle could get some money if Kolman released his mechanic’s liens on the Hiltons’ property:

“Again, I knew Mr. Edwards and Triangle Development had financial difficulties down there and I, when I did get a chance to talk to Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Neiss-Parsons
2021 Ohio 897 (Ohio Court of Appeals, 2021)
State v. Gipson
2019 Ohio 1165 (Ohio Court of Appeals, 2019)
State v. Kerr, Wd-08-008 (3-20-2009)
2009 Ohio 1470 (Ohio Court of Appeals, 2009)
State v. Fletcher, 22235 (12-12-2008)
2008 Ohio 6546 (Ohio Court of Appeals, 2008)
State v. Jones, Ca2006-11-298 (3-3-2008)
2008 Ohio 865 (Ohio Court of Appeals, 2008)
State v. Widener, Unpublished Decision (2-2-2007)
2007 Ohio 429 (Ohio Court of Appeals, 2007)
Dailey v. First Bank of Oh, Unpublished Decision (6-23-2005)
2005 Ohio 3152 (Ohio Court of Appeals, 2005)
State v. Suber
798 N.E.2d 684 (Ohio Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
751 N.E.2d 510, 141 Ohio App. 3d 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-edwards-ohioctapp-2001.