State v. City of Seattle

132 P. 45, 73 Wash. 396, 1913 Wash. LEXIS 1612
CourtWashington Supreme Court
DecidedMay 6, 1913
DocketNo. 10713
StatusPublished
Cited by7 cases

This text of 132 P. 45 (State v. City of Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. City of Seattle, 132 P. 45, 73 Wash. 396, 1913 Wash. LEXIS 1612 (Wash. 1913).

Opinion

Fullerton, J.

This action arises under the workmen’s compensation act. It was brought by the state of Washington against the city of Seattle to recover the premiums due the accident fund provided for in the act, upon the pay rolls of the various contractors performing public work for the city of Seattle between October 1, 1911, and December 20, 1911. The city had retained from the payments due the contractors sums sufficient to satisfy these premiums, and on the institution of the action the contractors were allowed to intervene therein and defend against their liability to make the payments. The trial resulted in a recovery on behalf of the state for the amount of the premiums claimed, but it was found that the city had retained from the sums due the interveners a larger sum than was necessary to satisfy the premiums, and the interveners were allowed judgment against the city for the excess. The interveners have appealed.

[398]*398The facts involved in the controversy are not in dispute. The workmen’s compensation act was enacted at the twelfth biennial session of the legislature, which began on January 9, 1911, and ended on March 9, 1911. As the act had no emergency clause, it went into effect, in virtue of art. £, § 31 of the state constitution, ninety days after the adjournment. By § 4 of the act itself, it was made to take effect between employers and workmen on October 1, 1911. The act abolishes the common law remedies for awarding compensation to injured workmen engaged in hazardous employments, and provides that compensation shall be made for accidents occurring therein according to a fixed ratio from a fund collected and administered by the state. Extra hazardous employments are enumerated, and employers of labor engaged therein are required to pay a fixed percentage of their pay rolls into the fund. Extra hazardous work performed for the different municipalities of the state is provided for in § 17 of the act, and reads as follows:

“Whenever the state, county or any municipal corporation shall engage in any extra hazardous work in which workmen are employed for wages, this act shall be applicable thereto. The employer’s payments into the accident fund shall be made from the treasury of the state, county or municipality. If said work is being done by contract, the pay roll of the contractor and the sub-contractor shall be the basis of computation and in the case of contract work consuming less than one year in performance the required payment into the accident fund shall be based upon the total pay roll. The contractor and any sub-contractor shall be subject to the provisions of the act, and the state for its general fund, the county or municipal corporation shall be entitled to collect from the contractor the full amount payable to the accident fund, and the contractor, in turn shall be entitled to collect from the sub-contractor his proportionate amount of the payment.” Laws 1911, p. 366, § 17.

The contracts between the city of Seattle and the interveners here involved were all entered into after the passage of the act, but prior to the time it went into effect. The per[399]*399formance of the contracts were also entered upon prior to the time the act went into effect, but were completed in December, 1911, and the work accepted by the city in January, 1912. The sums retained by the city were a percentage on the pay rolls of the contractors for work performed between October 1, 1911, and the completion of the work by the contractors. The contracts between the city and the contractors were in writing. They contained no reference to the workmen’s compensation act, nor did they make any provision for paying the premiums that might become due thereunder in case the work provided for therein should be prolonged until after the act should become operative.

The assignment of error first to be noticed is the claim that an erroneous method for computing the amount due as premiums was adopted by the state and given effect in the judgment of the court. ' This claim has its foundation in the provisions of § 4 of the act. It is there provided that the initial payment to the accident fund for the year 1911 shall be made prior to October !, 1911, and shall be “preliminarily collected upon the pay roll” of the employer from whom collected “of the last preceding three months of operation.” It is also provided in the same section that at the end of each year an adjustment of accounts shall be made upon the basis of the actual pay roll, and “any shortage shall be made good on or before February 1, following.” The amount claimed to be due from these contractors was taken from their actual pay rolls, and not from the pay rolls of the last three months of operation prior to October 1, 1911. But no preliminary payment was exacted of these employers on October 1, 1911; on the contrary, the state waited before attempting to collect until their contracts were completed, and calculated the percentages upon the actual pay rolls during the period for which the contractors were liable. This is not in violation of the statute.' There was no waiver of the right to collect by failing to collect in advance of the actual work. If the collection had been made in advance upon an estimate taken from [400]*400pay rolls preceding. October 1 and too much had been collected, the contractors would have been entitled to the excess on the final adjustment at the end of the year 1911; if too little had been collected, they would have been hable for the shortage, which they must have made good on or before the 1st of the following February. The state, instead of collecting from the contractors in advance of the period for which the collections were due, as it might have done, is seeking to collect at the end of such period. This surely can work no hardship upon contractors, since the sums are now due and definitely ascertainable, and the amount sought to be collected is the same as it would have been had the other and perhaps more regular method been pursued. We therefore find no cause for reversal for the reason here suggested.

It is next contended that the trial court erred in holding that the provisions of § 17 of the act, above quoted, authorized the city to withhold from the contractors the amount it is obligated to pay into the accident fund. It is argued that the state, and the state only, is authorized to make such collections. In the brief it is said:

“They [meaning the court and industrial insurance commission] read the language as follows: ‘And the state for its general fund shall be entitled to collect from the contractor, and the county shall be entitled to collect from the contractor, and the municipal corporation shall be entitled to collect from the contractor.’
“We read it as follows: ‘The state (for its general fund and (or) for the county or municipal corporation) shall be entitled to collect from the contractor.’
“Namely, the power to collect is vested in but one agency, the state. This is entirely consistent with Sec. 8, which says ‘If the employer default the state shall collect by action at law.’ It is likewise consistent with the other provisions, and with section 16, which provides action shall be in name of state, while we contend that the construction now placed upon it is wholly inconsistent with the whole spirit and tenor of the remainder of the act.”

[401]*401But it seems to us manifest that the construction put upon the language of the statute by the court is the correct construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Adams
732 P.2d 149 (Washington Supreme Court, 1987)
McDaniel v. City & County of San Francisco
259 Cal. App. 2d 356 (California Court of Appeal, 1968)
City of Tacoma v. Peterson
5 P.2d 1022 (Washington Supreme Court, 1931)
State v. Postal Telegraph-Cable Co.
172 P. 902 (Washington Supreme Court, 1918)
State v. Collins
162 P. 556 (Washington Supreme Court, 1917)
Raymond v. Chicago, M. & St. P. Ry. Co.
233 F. 239 (Ninth Circuit, 1916)
Hunter v. Colfax Consolidated Coal Co.
175 Iowa 245 (Supreme Court of Iowa, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
132 P. 45, 73 Wash. 396, 1913 Wash. LEXIS 1612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-city-of-seattle-wash-1913.