State v. Citizens Trust & Guaranty Co.

15 Ohio N.P. (n.s.) 149
CourtClermont County Court of Common Pleas
DecidedOctober 15, 1913
StatusPublished

This text of 15 Ohio N.P. (n.s.) 149 (State v. Citizens Trust & Guaranty Co.) is published on Counsel Stack Legal Research, covering Clermont County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Citizens Trust & Guaranty Co., 15 Ohio N.P. (n.s.) 149 (Ohio Super. Ct. 1913).

Opinion

Davis, J.

The armory board of state of Ohio, under Sections 5257, et seq., contracted with J. H. L. Barr to build an armory at Batavia. Barr executed a bond in the sum of $9;000 conditioned for the faithful performance of the contract, the Citizens [150]*150Trust & Guaranty Company of West Virginia being the surety 'on the bond. On November 12th, 1912, Barr died, leaving the armory uncompleted. Barr’s administrator declined to complete the contract, the state notified the bonding company and thereupon the company took charge and completed the armory. The contract price for the entire work was $17,860; there had been paid Barr $10,288, leaving in the hands of the armory board $7,572. The bonding company expended in completing the building $3,983.31, and at Barr’s death there was due corporations, firms and individuals, for material, labor, etc., $6,677.08, this sum being due the defendants who have filed answers and cross-petitions in this case, and due for material, etc., furnished Barr and used in constructing the armory. There is no dispute as to the correctness, justice and amount of any claim. The contract provides for payment of 80% as’the work progresses. A number of claimants filed proof of claim with armory board and filed mechanic’s liens after Barr’s death. When the building was completed, there being many claimants of the fund in the hands of the armory board, the Attorney-General commenced this action and bringing the fund into court makes all claimants parties, and asks the court to decide as to conflicting claims and distribute the fund. An examination of pleadings discloses the fact that in addition to the material and labor furnished by the bonding company, some of the other 'defendants also furnished material, which was furnished and used after Barr’s death, as will appear by examination of account of Geo. A. Keen & Brother and Chas. Ferris.

It was insisted in argument by counsel for the bonding company that the state can not be sued, nor can any lien be acquired on the armory building, or on funds in hands of armory board.

It is so well settled by numerous decisions of the Supreme Court of the United States and of this state, that the state is sovereign and can not without its consent be sued, that it is unnecessary to cite cases on this point. Were this question in issue in this case, it would be disastrous to the bonding company and defeat not only all other creditors but the bonding company [151]*151as well. It would be a boomerang used by the company for it, as well as all other defendants, by cross-petition sue the state by laying claim to the fund. The bonding company can not urge a defense for the state, which the state does not claim. The right to plead immunity from suit, is a personal right, to be asserted, if at all, when the state is sued, by the state. ‘ ‘ The state is not bound b'y a general statute, but the exemption is a privilege of sovereignty and can be asserted only on behalf of sovereignty” (56 O. S., 175). But in this ease the state has commenced the action, has filed the petition, and it is held in State v. Executor Buttles, 3 O. S., 309, “When the state appears in her courts as a suitor to enforce her rights of property, she comes shorn of her attributes of sovereignty as a body politic, capable of contracting, suing and holding property subject to those rules of justice and right which in her sovereign capacity she has prescribed for the government of her people.” The 3d O. S., 309, has been approved in several cases, the last being Railroad Co. v. State, 85 O. S., 295. It is true that in this case the state is not trying “to enforce her rights of property,” but she is asking protection, and subjects herself to this suit, and voluntarily waives the immunity of a sovereign.” The holding of court in Ohio v. Morrow, 10 N.P.(N.S.), 279, that the state can not be sued is true, but only in cases where a suit is brought against the state, and the state interposes the defense of sovereignty. Does it follow that, as the state can not without its consent be sued, no mechanic’s lien can be taken on buildings erected by the state, or on the fund ? This point is decided in State, ex rel, v. Morrow et al, 10 N.P. (N.S.), 279. That case was an action of mandamus, and counsel claim that was the only question necessary to be decided, and in fact the only point on which the case is any authority, but Judge Kyle after disposing of question of mandamus, says: “There is a second question, more difficult of solution, and that is by the steps taken by the relator did it acquire any lien on the fund, or in other words, does the lien law apply in a case where the state of Ohio is party”? The opinion of Judge Kyle is a very clear one, and has been affirmed by the circuit court. On page [152]*152284 lie says, ‘ ‘ There is no express provision or necessary implication that the state is included within the lien act, and therefore the mechanic’s lien law does not apply to the state.” The mechanic’s lien law is a general statute 'and the state is not bound by a general statute (56 O. S., 175). The circuit court in affirming Judge Kyle, in 10 N.P.(N.S.), in a note on p. 279— cites a ease in 38 Law Bulletin, 212, Regg v. Mann, a case affirmed by Supreme Court without report. In that case the facts found and stated, are:

“Mann entered into a contract with Hill to construct a dwelling; Regg, a sub-contractor, agreed to do the brick work; Mann was aware of this sub-contract. Hill, the principal, abandoned the job when the work was about half done; Regg, having nearly completed his sub-contract for brick work, was willing and prepared to go on and complete his sub-contract. There was due Regg, on his sub-contract, when Hill abandoned the job, $122. The owner, Mann, had paid Hill $1,375 on the contract, and had he completed the work there would have been due the additional sum of $1,233. Mann advertised for bids to complete the work, but he rejected all bids and personally completed the dwelling, and the whole cost, including amount paid principal contractor, was $109.84 less than original contract price. Regg, the sub-contractor, filed with the owner an itemized statement of his claim under mechanic’s lien law. The circuit court as conclusion of the law found, (1) the contract was entire and Hill, the principal contractor, forfeited all his rights when he abandoned the contract; (2) that this abandonment worked a forfeiture against the plaintiff as sub-contractor, and that the mechanic’s lien law could not afford plaintiff any remedy.”

It is urged that Sections 8324 and 8325, General Code, part of the mechanic’s lien law, are broad enough to include either the state or the armory board, and this is true if the words “or other public buildings provided for in a contract between the owner, or the board officer, or public authority” would include an armory, and the clause authorizing sub-contractors to file with the owner, board officer or public authority, an itemized statement, would give a sub-contractor a right to a lien on the fund. The mechanic’s lien sections of General Code, are general laws, [153]*153and from such laws the state is exempt (56 O. S., 175), and in State, ex rel, v. Morrow, 10 N.P.(N.S.), the statutes are quoted and said not to apply to the state.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
15 Ohio N.P. (n.s.) 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-citizens-trust-guaranty-co-ohctcomplclermo-1913.