State Through Div. of Admin. v. Algernon Blair

445 So. 2d 133
CourtLouisiana Court of Appeal
DecidedFebruary 1, 1984
Docket83-348
StatusPublished
Cited by6 cases

This text of 445 So. 2d 133 (State Through Div. of Admin. v. Algernon Blair) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Through Div. of Admin. v. Algernon Blair, 445 So. 2d 133 (La. Ct. App. 1984).

Opinion

445 So.2d 133 (1984)

STATE of Louisiana, Through the DIVISION OF ADMINISTRATION, Plaintiff-Appellant,
v.
ALGERNON BLAIR, INC., Defendant-Appellee.

No. 83-348.

Court of Appeal of Louisiana, Third Circuit.

February 1, 1984.

*134 Hawley & Schexnayder, W. Paul Hawley, Lafayette, for plaintiff-appellant.

Breazealle, Sachse & Wilson, Michael D. Hunt, Baton Rouge, Smith, Currie & Hancock, Bert R. Oastler, Atlanta, Ga., for defendant-appellee.

Before GUIDRY, CUTRER and STOKER, JJ.

GUIDRY, Judge.

This contract dispute arises out of the construction of the University Medical Center in Lafayette, Louisiana. The State of Louisiana, through the Division of Administration, as owner, contracted with Algernon Blair, Inc. to construct the Medical Center. The construction contract was entered into on July 7, 1977. Disputes arose between the parties during the construction. Pursuant to the terms of the contract, Blair filed certain claims with the American Arbitration Association. The State subsequently filed suit seeking damages for breach of contract. The district court stayed the proceedings pending arbitration of the dispute, as provided for by the contract. This court affirmed that judgment. State, through the Division of Administration v. Algernon Blair, Inc., 415 So.2d 612 (La.App. 3rd Cir.1982).

The claims of both parties were heard by a panel of arbitrators representing the American Arbitration Association. The proceedings included approximately thirty-five days of hearings, during which a voluminous record was compiled. On November 4, 1982, the arbitrators rendered their award. Blair was awarded the sum of $5,367,988.00. Of this total, $985,414.00 was found by the arbitrators to be due certain subcontractors of Blair. The names of the subcontractors and the amount owed to each were listed in the award. The arbitrators awarded the State the sum of $141,250.00 on its counterclaim against Blair. Costs were assessed against the State. In addition, the arbitrators ordered that interest would accrue on the award at the rate of 12% beginning forty-five days after the date of the award.

On November 30, 1982, Blair filed a petition in the district court to have the award of the arbitrators confirmed pursuant to LSA-R.S. 9:4209. The State filed a motion to vacate the award pursuant to LSA-R.S. 9:4210, or alternatively, to modify or correct the award pursuant to LSA-R.S. 9:4211. The trial court denied the State's motions and confirmed the award of the arbitrators. The State appeals this judgment.

On appeal, the State urges that the trial court erred in refusing to vacate or modify the award of the arbitrators. The alleged error centers around the inclusion of interest in the award. The State claims that, in addition to the future interest awarded by the arbitrators, the amounts awarded Blair and its subcontractors included accrued interest on the amounts owed by the State. The State asserts that the award of interest in any form is prohibited by the contract, and further, that the award of interest against the State is prohibited by the law of Louisiana.

The ground relied upon for vacating the award appears in LSA-R.S. 9:4210, which provides in pertinent part:

"In any of the following cases the court in and for the parish wherein the award was made shall issue an order vacating the award upon the application of any party to the arbitration.
*135 . . . .
D. Where the arbitrators exceeded their powers or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made."

The State asserts that the arbitrators exceeded their authority in awarding interest, and that the trial court erred in refusing to vacate the award on that ground.

The grounds for modification or correction of an arbitration award are found in LSA-R.S. 9:4211:

"In any of the following cases the court in and for the parish wherein the award was made shall issue an order modifying or correcting the award upon the application of any party to the arbitration.
A. Where there was an evident material miscalculation of figures or an evident material mistake in the description of any person, thing, or property referred to in the award.
B. Where the arbitrators have awarded upon a matter not submitted to them unless it is a matter not affecting the merits of the decision upon the matters submitted.
C. Where the award is imperfect in matter of form not affecting the merits of the controversy.
The order shall modify and correct the award so as to effect the intent thereof and promote justice between the parties."

The State bases its motion to modify or correct the award on the alleged inclusion in the award of accrued interest on the amounts owed Blair by the State. Because the contract in question provided that no payments for interest on amounts owed either party would be due under the contract, the State urges that the inclusion of such interest in the award resulted from either an evident miscalculation or an award upon a matter not submitted to the arbitrators.

ACCRUED INTEREST

A factual dispute exists as to whether the award of the arbitrators included accrued interest on the money owed to Blair and the subcontractors. Blair was awarded the sum of $5,367,988.00. The award designated $985,414.00 of this total as being due to subcontractors of Blair. The amount owed each subcontractor was set out in the award. However, none of the amounts awarded Blair or the subcontractors were itemized. It is thus impossible to determine which elements of each claim were allowed or disallowed. More importantly, it is impossible to determine whether any of the amounts awarded included accrued interest. Nevertheless, the State contends that certain awards necessarily include accrued interest.

In support of this contention, the State points to a post-hearing brief submitted by Blair to the arbitrators prior to the rendition of the award. The brief contains a summary of Blair's claims against the State, and delineates the amounts claimed for labor, materials, insurance and other costs, as well as the amounts claimed on behalf of the various subcontractors. The summary of claims also included a claim for accrued interest. This summary reflects a total claim by Blair and its sub-contractors, excluding interest, of $5,992,251.00, which amount exceeds that ultimately awarded by the arbitrators. The thrust of the State's argument is that the amount awarded to Blair alone (the total award less amounts actually awarded to subcontractors) must have included interest, because the amount awarded exceeds the sum of the other elements of Blair's claim as summarized in brief. We reject this argument.

The State would have us rely on figures appearing in the brief submitted by Blair to the arbitrators, to the exclusion of the testimony taken in thirty five days of hearings before the panel. We do not have the benefit of a transcript of the arbitration proceedings. Thus, we do not know what claims were submitted to the panel, the manner in which they were presented, which of the claims were meritorious, nor the equities which may have existed in the position of any party to the controversy.

*136 In Transcontinental Drilling Co., Inc. v. Davis Oil Company, 354 So.2d 235 (La. App. 4th Cir.1978), a party aggrieved by an arbitration award sought to have the award modified, alleging an evident miscalculation of figures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leon Angel Constructors v. Kirk Knott Elec.
837 So. 2d 743 (Louisiana Court of Appeal, 2003)
Haase Construction Co. v. Strohmeyer
738 So. 2d 152 (Louisiana Court of Appeal, 1999)
Sharbono v. Steve Lang & Son Loggers
696 So. 2d 1382 (Supreme Court of Louisiana, 1997)
St. Tammany Manor v. Spartan Bldg. Corp.
509 So. 2d 424 (Supreme Court of Louisiana, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
445 So. 2d 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-through-div-of-admin-v-algernon-blair-lactapp-1984.