State Public Utilities Commission ex rel. Wabash Railroad v. Illinois Central Railroad

274 Ill. 36
CourtIllinois Supreme Court
DecidedJune 22, 1916
StatusPublished
Cited by5 cases

This text of 274 Ill. 36 (State Public Utilities Commission ex rel. Wabash Railroad v. Illinois Central Railroad) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Public Utilities Commission ex rel. Wabash Railroad v. Illinois Central Railroad, 274 Ill. 36 (Ill. 1916).

Opinion

Mr. Justice Cartwright

delivered the opinion of the court:

In 1891 the tracks of the Chicago and Alton Railroad Company, the Illinois Central Railroad Company and the Wabash Railroad Company crossed each other adjoining Pontiac, at a place then known as Paducah Junction. The Chicago and Alton "Railroad Company petitioned the Railroad and Warehouse Commission to compel the other companies to join in an interlocking device at the crossing. The commission on December 10, 1891, after a hearing of the different companies, ordered an interlocking plant constructed consisting of thirty-six working levers operated by manual power, and ordered that each of the three com-panics should pay one-third of the original cost of construction and of the expense of future maintenance and operation. The interlocking plant was constructed in compliance with the order and was completed and put in operation in the early part of 1892, and continued in operation and protecting the crossings of the three roads more than twenty-three years. In 1905- the Bloomington, Pontiac and Joliet Electric Railway Company desired to cross the tracks of the Wabash and Central companies with its interurban railway, and proceedings were had before the commission which terminated in an order on April 11, 1905, providing that the Central and Wabash companies should raise their tracks a few feet and the electric railway should go under them by means of a subway. It was ordered, however, that for a period of ninety days the electric company should, without expense to or liability on the part of the other companies, have a right to install temporary crossings over their tracks at grade but the temporary crossings should be removed within ninety days, and if not so removed the Central company and Wabash company might, upon twenty-four hours’ notice to the electric company, tear up and remove the same, unless in the meantime the commission should make an order to the contrary. The electric company was required to furnish, install and maintain the temporary crossings, and crossing frogs, switches and appurtenances, with proper derailing devices. It turned out that the order for the subway could not be carried out on account of the lack of drainage, as the subway track would frequently be covered with water, but no order was made by the commission respecting the temporary crossings and the electric company continued to use them by sufferance of the Wabash and Central companies.. In 1909 the electric company applied to the commission for a modification of the order of 1905 and for a permanent grade crossing, and that the commission should prescribe the place where and the manner in which the track of the electric company should cross the other tracks and the conditions upon which the electric company should enter into .the interlocking plant. The Chicago and Alton Railroad Company, which maintained and operated the interlocking device, then became a party to the proceeding. On October 20, 1909, the commission set aside the order of April 11, 1905, and made an order that the electric company should have a right to cross at grade the main track and side-track of the Central company and the main track and Y-track of the Wabash company after having secured the necessary right of way, as provided by law. The order specified the point of crossing as indicated on a plan in the office of the commission and provided, that the crossing should be interlocked in connection with the other tracks; that the electric company should make, at its sole expense, such changes and additions to' the interlocking system as should be satisfactory to the commission and install and maintain a proper trolley-guard, and that it should be charged thereafter with one-fourth of the cost of operation and maintenance. The electric company was required to complete the entire work by February 1, 1910, and again the electric company did nothing to comply with the order. The commission finally notified the Alton company that the interlocking plant was so worn out that the commission would not allow further substantial repairs to be made, and ordered it- taken out of service and not to be used again until a new interlocking plant should be installed. In 1914 the Alton company presented to the State Public Utilities Commission, successor to the Railroad and Warehouse Commission, for approval, plans for constructing an electric interlocking plant to take the place of the old mechanical plant. The plans so presented did not include the electric company, and the utilities commission on July 24, 1914, gave notice to all the companies to appear and show cause why the order of 1909 had not been complied with. On October 6, 1914, the electric company filed its petition that it should not be required to enter into the interlocking system. On October 19, 1914, the Alton company filed its answer, alleging that an entirely new interlocking plant was necessary, and that the cost of construction, operation and maintenance, should be divided among the companies on the unit basis of division. On October 26, 1914, the Central company answered, admitting the necessity of a new interlocking plant but denying that it was necessary to set aside the previous orders. Hearings were had, and on December 12, 1914, the commission vacated and set aside the orders of 1891 and 1909. An order was then entered that a new modern electric interlocking device, consisting of an eighty-lever frame, with sixty-eight working levers, should be installed; that the electric company should change the location of its crossings, pay the cost of constructing the crossing frogs necessary to cross the tracks of the Central and Wabash roads, and also bear the expense of such track changes as might be necessary in the tracks of the Central and Wabash; that the new interlocking plant should embrace all the crossings formed by the tracks; that the four companies should each be required to bear such proportion of the total cost of construction and maintenance of the new plant as the number of interlocking units required for the tracks of the respective roads bore to the total number of interlocking units, and that the-cost of the subsequent operation of the new interlocking plant should be borne equally by the four companies. The Central company appealed to the circuit court of Sangamon county, where the order was affirmed, and a further appeal to this court was allowed and perfected.

One objection to the order appealed from is based on the ground that the order of 1891 for the construction of a mechanical interlocking system, by which each of the three companies was required to pay one-third of the cost of construction, maintenance and operation, having taken effect and been accepted and acted upon for over twenty-three years, had the force and effect of a contract and fixed the relative share of the cost of the new plant to be paid 'by each company. The order not having been entered by consent or agreement of the parties but by the judgment of the Railroad and Warehouse Commission did not contain any element of a contract between the companies or between the commission and either company and the compliance with the order did not establish it as a contract. There was no binding obligation upon the utilities commission, under new and changed conditions after the plant was worn out and a 'new and different plant was required, to make the same order respecting the share to be paid by each company. The judgment of the utilities commission cannot be set aside because its conclusion was different from that of its predecessor, reached twenty-three years before.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
274 Ill. 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-public-utilities-commission-ex-rel-wabash-railroad-v-illinois-ill-1916.