STATE PROP. & BLDG. COM'N v. HW Miller Const. Co.
This text of 385 S.W.2d 211 (STATE PROP. & BLDG. COM'N v. HW Miller Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE PROPERTY & BUILDINGS COMMISSION OF the DEPARTMENT OF FINANCE, etc., Appellants,
v.
H. W. MILLER CONSTRUCTION COMPANY, Inc., Appellee.
Court of Appeals of Kentucky.
*212 Paul E. Tierney, Melbourne Mills, Jr., Frankfort, for appellants.
William H. Bixler, Hughes, Clark & Burke, Covington, for appellee.
PALMORE, Judge.
The State Property and Buildings Commission (KRS 56.450) sued appellee, H. W. Miller Construction Company, for damages in the amount of $4,447 resulting from an alleged breach of contract. At the close of plaintiff's evidence the trial court sustained defendant's motion for a directed verdict and entered judgment accordingly. The commission appeals.
The briefs present two issues, (1) interpretation of the contract and (2) sufficiency of the proof of damages.
The contract, awarded to Miller in June of 1955, covered the construction of a state office building in accordance with detailed specifications, drawings, and other incorporated documents for a total price of $156,900. The work was completed, payment was made and the state proceeded to occupy and use the building. In 1960 certain water pipes laid under concrete slab in an unexcavated portion of the structure began to leak, causing water to flow into an adjacent basement area. Investigation disclosed that the pipes had not been enclosed in a sonotube duct as required by the contract drawings and had rusted out.
The contract specifications called for foam glass insulation on the pipes but made no mention of any further type of casing. The detailed drawings, on the other hand, called for the sonotube casing but made no reference to the foam glass insulation. The contractor did install the foam glass insulation around the pipes but did not provide any further encasement. He (it) now contends in substance that there was an ambiguity as between the written specifications and the detailed drawings, which must be resolved against the state as the author of the contractual instruments, and that he reasonably construed them to mean that he was to provide either the foam glass or the sonotube duct but not both.
As explained in the testimony, foam glass is an insulating material only. It is not waterproof and will not protect against *213 moisture. The piping was steel and, as it was to be laid in the ground, had to be protected against water. That was the purpose of the sonotube duct, which is impervious to moisture. The drawings show clearly that one 16-inch sonotube duct was to house three small steel pipes and one copper tube. As illustrated, each of the three steel pipes is surrounded by a concentric hatch-marked area indicating some type of wrapping or cover. When the drawings and specifications are considered together (and it is not disputed that both are part of the contract), especially in the light of the testimony explaining the separate functions of the insulation and the sonotube duct, there is no ambiguity. Moreover, Article 52 of the "General Conditions" of the contract provides in part as follows:
"Anything called for in the specifications and not shown on the drawings or shown on the drawings and not called for in the specifications, shall be included in the Contractor's work, the same as if included in both."
It is our conclusion that the agreement required foam glass insulation on each of the underground steel pipes and a waterproof sonotube duct encasing the whole. Breach of the contract in this respect was proved.
It was further proved that upon discovery of the defect Miller was requested to remedy it and failed to do so, whereupon the state designed the necessary repair work, awarded a contract in the amount of $4,447 for its performance, and paid out that sum on completion of the job. There was no proof of market value of the building with the defective condition as against what its market value would have been without it.
The parties are not so much in disagreement with respect to the proper measure of damages as they are with regard to the way in which that measure applies to the facts of this case. However, for the sake of clarity it is well that we review the law before more closely considering the particular facts.
"When the building is completed but the construction is in some respect defective, the principle upon which damages are to be estimated will depend on whether the defect can be remedied by the expenditure of a reasonable amount of money. If in view of the expense it is reasonable to remedy the defect, then the measure of damages is the cost of remedying it. If, on the other hand, the value of the building with the defect is greater than its value without the defect less the cost of applying the remedy, then the measure of damages is the diminution in the value of the building by reason of the defect." Sedgwick on Damages, § 644 (Vol. 2, p. 1293). See also on this general subject 13 Am.Jur. 2d 79 (Building and Construction Contracts, § 79); Restatement, Contracts § 346(1) (a); and annotation, Cost of correction or completion, or difference in value, as measure of damages for breach of construction contract, 76 A.L.R.2d 805.
From an examination of the numerous decisions of this court in which the question was discussed it is apparent that time and again it has been argued in vain that a "difference in value" instruction was unauthorized because the evidence showed only the cost of remedying the defect. Cf. Mikkelsen v. Fischer, Ky., 347 S.W.2d 525, 528 (1961); Alvey v. Kern, Ky., 354 S.W. 2d 516, 518 (1962). Probably this is because, that being the only form of instruction on the point set forth in Stanley's Instructions (§ 216), the courts have been reluctant to give one that is more appropriate. The form in question was taken from Taulbee v. Moore, 106 Ky. 749, 51 S.W. 564, 21 K.L.R. 378 (1899), but as pointed out in footnote (1) to § 216 of Stanley, the court later commented in Forbes v. Hunter, 31 K.L.R. 285, 102 S.W. 246 (1907), that perhaps it would be better to tell the jury that the measure of damages is the sum required in order to make the building conform to the contract. And indeed it would *214 be. Confusion and misunderstanding have arisen from our persistence in approving an instruction based on the one measure when the evidence is devoted entirely to another.
There is no question that in this state the real measure of damages for defective performance of a construction contract is the cost of remedying the defect, so long as it is reasonable. Mikkelsen v. Fischer, Ky., 347 S.W.2d 527, 528 (1961); Ward v. Qualls, 229 Ky. 662, 17 S.W.2d 739, 740 (1929); Young v. Cumberland County Educational Soc., 183 Ky. 625, 210 S.W. 494, 496, 6 A.L.R. 135 (1919). As we construe the relationship between market value and cost of remedying the defect, the latter becomes unreasonable only (a) if it exceeds the difference between the market value of the building as it should have been constructed and its market value as actually constructed (assuming the defective condition to be known), or (b) if it amounts to more than is reasonably necessary in order to bring the building into substantial conformity with the contract.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
385 S.W.2d 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-prop-bldg-comn-v-hw-miller-const-co-kyctapphigh-1964.