State of Tennessee v. Christopher C. White

CourtCourt of Criminal Appeals of Tennessee
DecidedJune 5, 2024
DocketM2023-00964-CCA-R3-CD
StatusPublished

This text of State of Tennessee v. Christopher C. White (State of Tennessee v. Christopher C. White) is published on Counsel Stack Legal Research, covering Court of Criminal Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Tennessee v. Christopher C. White, (Tenn. Ct. App. 2024).

Opinion

06/05/2024 IN THE COURT OF CRIMINAL APPEALS OF TENNESSEE AT NASHVILLE April 9, 2024 Session

STATE OF TENNESSEE v. CHRISTOPHER C. WHITE

Appeal from the Circuit Court for Dickson County No. 22CC-2016-CR-371 David D. Wolfe, Judge ___________________________________

No. M2023-00964-CCA-R3-CD ___________________________________

After a bench trial, Defendant, Christopher C. White, was found guilty of one count of theft valued at $10,000 or more but less than $60,000. The trial court imposed a four-year sentence, suspended to probation, and ordered Defendant to pay $10,228 in restitution. On appeal, Defendant argues (1) the evidence was insufficient to support his conviction; (2) this court lacks subject matter jurisdiction to consider Defendant’s appeal; and (3) collateral estoppel required the trial court to dismiss the case. After review, we conclude the evidence is insufficient to support Defendant’s conviction for theft. Accordingly, we reverse the judgment of the trial court, vacate Defendant’s conviction, and dismiss the case.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Reversed; Conviction Vacated; Case Dismissed

MATTHEW J. WILSON, J., delivered the opinion of the court, in which CAMILLE R. MCMULLEN, P.J., and TIMOTHY L. EASTER, J., joined.

Mark C. Scruggs, Nashville, Tennessee, for the appellant, Christopher C. White

Jonathan Skrmetti, Attorney General and Reporter; Benjamin A. Ball, Senior Assistant Attorney General; W. Ray Crouch, Jr., District Attorney General; and Talmadge Woodall, Assistant District Attorney General, for the appellee, State of Tennessee.

OPINION

I. Background A. Factual Summary Many of the material facts of this case, as set forth by the testimony and exhibits introduced during the bench trial in this matter, are not in dispute. On December 15, 2014, Rebecca Munk1 contracted with Defendant’s company, CountryWide Barns and Buildings (“CountryWide”), to build a house in Dickson County. Per the terms of the contract, Ms. Munk was to pay CountryWide a series of “draws” or installments as follows:

Payment No.2 Description/Stage of Construction Payment Amount 1 At signing of [initial] P.O. for official plan and $57,837.81 material list development 2 Upon first material delivery $57,837.81 3 Upon completion of framing $57,837.80 4 Upon building enclosed from weather $57,837.80 5 Interior complete $43,378.35 6 Final payment $14,459.45

At trial, Ms. Munk testified she understood that per the contract, she was not responsible for paying subcontractors. Rather, Defendant would pay subcontracting companies to perform work on the house using the funds provided by Ms. Munk.

Among other provisions, the contract provided, “All changes to the Services by Customer, including but not limited to changes to the style, design, color, pattern or trim of the Improvement, shall not be undertaken by [CountryWide] without a written change order.” Furthermore, the contract provided, “Customer acknowledges and agrees that [CountryWide]’s worksite personnel do not have the authority to bind [CountryWide] to any agreement, oral or written.”

Ms. Munk paid the first installment the day the contract was signed, and work began on the house. Plans for the house initially called for a garage to be built, but on January 12, 2015, CountryWide drafted a change order reflecting the parties’ new agreement to build a basement instead of a garage. Ms. Munk signed the agreement the following day. Both Defendant and Ms. Munk testified at trial that the change in building plans developed before the change order was signed, but they differed on how it happened. Ms. Munk testified that CountryWide employees informed her that the change from a garage to a basement was needed because of grading issues at her property, while Defendant testified that Ms. Munk and the subcontractor handling the excavation changed the building plans without notifying Defendant or anyone with CountryWide. Defendant testified that he

1 At the time the contract was executed, Ms. Munk was known as Rebecca Bear. The contract references her accordingly. However, we will reference Ms. Munk as she was referenced at trial—Rebecca Munk. 2 There are no payment numbers 3 or 6 in the contract. We have renumbered the payment list accordingly to avoid confusion. -2- learned about the change in building plans only after visiting the worksite and discovering that the subcontracted excavating company had begun to build the basement.

Ms. Munk paid the first three installments on December 15, 2014, February 5, 2015, and April 13, 2015, although she testified that for the second installment, CountryWide “tried to get me to pay before the material had been delivered.” She also paid the full $31,380 cost of the basement, and the planned cost of the garage, $20,339.28, was credited to her account.

On July 2, 2015, the parties agreed to a second change order, with Ms. Munk paying an additional $13,787.89 for a retaining wall eleven days later. However, at some point before this second change order was executed, the relationship between CountryWide and Ms. Munk had begun to deteriorate. Emails between Ms. Munk and Defendant were introduced at trial that reflect their dispute. On May 22, 2015, Ms. Munk sent an email to Defendant and other persons involved with the build in which she aired certain grievances. She began her message by writing that “Communication and the lack [there]of has become a large issue.” As particularly relevant to this appeal, Ms. Munk stated, “I am hearing YET AGAIN how contractors on the site are NOT GETTING PAID. There is a pattern developing here and it isn’t looking good for [CountryWide].” (emphasis in original). However, Ms. Munk did not identify the specific contractors who claimed they were unpaid or the amounts they were owed. She also emailed about “the porch/deck situation”; at trial, Ms. Munk testified that CountryWide was contracted to build a concrete wraparound porch, but they built a wooden porch instead. She also claimed to have paid an installment for a “completed” framing job (listed as Payment No. 3 in the table above), although she did not, in fact, have a complete framing job.

On May 26, 2015, Defendant sent Ms. Munk a reply email that included the following:

Contractors getting paid. I am so tired of guys saying this. Again Keith and his guys were to be paid 8000 for repair all framing, finish the porches, and put on all the metal and soffit on the outside. To date they have been paid 5900. And look at where it is. On Thursday kieth requested 2600 for pay for the week. I told him noway and paid him 1400. This way the day after I met with him and recorded the meeting where he understood we had to be 10% ahead to insure completion. I am having sashia send you today, their CPA’s, this is the contract we get them to sign per job, and the payments to them out of the quick books. There is something not right when they go out to this job. They never say they have not been paid. We have three on this one that have said that. We are not recooping money I can guarantee you. We know the Gaines thing and the other two have killed me. Do me a favor, -3- look at your contract on framing, roofing, and siding. The money next to each item is what we should pay out. Then compare it to what I have paid out. You will see who is lying.

(Spelling in original). Ms. Munk and Defendant sent emails back-and-forth regarding the progress and timing of the build, but none of these subsequent emails addressed Ms. Munk’s claims about payment issues. Ms. Munk testified at trial that she paid certain subcontractors who complained about not being paid. Other than All Tech Insulation as explained later in this opinion, Ms. Munk did not specify who these subcontractors were or how much she paid them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Louisiana
406 U.S. 356 (Supreme Court, 1972)
Jackson v. Virginia
443 U.S. 307 (Supreme Court, 1979)
State of Tennessee v. Christopher Lee Davis
354 S.W.3d 718 (Tennessee Supreme Court, 2011)
State v. Sisk
343 S.W.3d 60 (Tennessee Supreme Court, 2011)
State v. Dorantes
331 S.W.3d 370 (Tennessee Supreme Court, 2011)
State v. Majors
318 S.W.3d 850 (Tennessee Supreme Court, 2010)
State v. Cawood
134 S.W.3d 159 (Tennessee Supreme Court, 2004)
State v. Holder
15 S.W.3d 905 (Court of Criminal Appeals of Tennessee, 1999)
State v. Gene Ivan Amanns
2 S.W.3d 241 (Court of Criminal Appeals of Tennessee, 1999)
Northland Insurance Co. v. State
33 S.W.3d 727 (Tennessee Supreme Court, 2000)
State v. Tuttle
914 S.W.2d 926 (Court of Criminal Appeals of Tennessee, 1995)
State v. Roberts
943 S.W.2d 403 (Court of Criminal Appeals of Tennessee, 1996)
State v. Hatchett
560 S.W.2d 627 (Tennessee Supreme Court, 1978)
State v. Cabbage
571 S.W.2d 832 (Tennessee Supreme Court, 1978)
State of Tennessee v. Rodney Stephens
521 S.W.3d 718 (Tennessee Supreme Court, 2017)
State of Tennessee v. Jimmy Williams
558 S.W.3d 633 (Tennessee Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
State of Tennessee v. Christopher C. White, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-tennessee-v-christopher-c-white-tenncrimapp-2024.