State of Ohio v. Nuclear Regulatory Commission

868 F.2d 810
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 10, 1989
Docket86-4085
StatusPublished
Cited by3 cases

This text of 868 F.2d 810 (State of Ohio v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Ohio v. Nuclear Regulatory Commission, 868 F.2d 810 (6th Cir. 1989).

Opinion

868 F.2d 810

57 USLW 2459, 98 P.U.R.4th 529

STATE OF OHIO, ex rel. Anthony J. CELEBREZZE, Jr.,
(86-4107); Toledo Coalition for Safe Energy, an
association; Susan A. Carter,
(86-4085), Petitioners,
v.
NUCLEAR REGULATORY COMMISSION and the United States of
America, Respondents,
The Toledo Edison Company and Cleveland Electric
Illuminating Company, Intervenors.

Nos. 86-4085, 86-4107.

United States Court of Appeals,
Sixth Circuit.

Argued Jan. 23, 1987.
Decided Jan. 27, 1989.
As Amended March 10, 1989.

Terry J. Lodge (argued), Toledo, Ohio, David Northrop and Sharon Sigler, Asst. Attys. Gen., Columbus, Ohio, for petitioners.

Carole F. Kagan (argued), L. Slaggie, James M. Taylor, Director, Office of Inspection & Enforcement, U.S. Nuclear Regulatory Comm., William Briggs, Dick Thornburgh, U.S. Atty. Gen., U.S. Dept. of Justice, Washington, D.C., for respondents.

Jay Silberg (argued), Shaw, Pittman, Potts & Trowbridge, Washington, D.C., for intervenor utilities.

Carole F. Kagan (argued), William Briggs, E. Leo Slaggie, Office of Gen. Counsel, Nuclear Reg. Comm., Washington, D.C., for Nuclear Regulatory Com'n.

Dirk D. Snel, U.S. Dept. of Justice, Washington, D.C., for U.S.

Jay Silberg (argued), Shaw, Pittman, Potts & Trowbridge, Washington, D.C., for Cleveland Elec. Illuminating Co.

Douglas O. Meyer, Ottawa County Pros. Atty., Port Clinton, Ohio, for amicus curiae Ottawa County in support of respondents.

Gary M. Orlow, Toledo, Ohio, for Lucas County in support of respondents.

Before ENGEL, Chief Judge*; BOGGS, Circuit Judge; and HILLMAN,** Chief District Judge.

ENGEL, Chief Judge.

In October 1986, the Toledo Coalition for Safe Energy and the State of Ohio each petitioned the Nuclear Regulatory Commission [NRC] for a hearing to suspend operation of Davis-Besse Nuclear Power Station [Davis-Besse] due to the alleged inadequacies of that facility's emergency preparedness plan. In November 1986, the Director of the NRC Office of Inspection and Enforcement [Director] denied both petitions. Petitioners now seek our review of the Director's decision to deny a hearing. Since both petitioners raise similar issues, their cases have been consolidated on appeal.

Whether the Director's decision is reviewable at all is a matter of initial uncertainty. The Director asserts that his decision to deny the requested hearing is a determination committed to his sole discretion in enforcing the Administrative Procedure Act, 5 U.S.C. Sec. 706(2)(A) (1982). Since this issue has not yet been resolved by the Supreme Court, we follow the path taken by the D.C. Circuit in Lorion v. United States Nuclear Regulatory Commission, 785 F.2d 1038 (D.C.Cir.1986), and adopted by our court in Dickinson v. Zech, 846 F.2d 369 (6th Cir.1988), and avoid deciding whether the Director's decision is reviewable by addressing first the easier question of whether the Director's decision was a proper exercise of his discretion. We conclude that petitioners have failed to demonstrate that the Director acted arbitrarily or capriciously in denying their request for further proceedings and affirm the Director's decision.

I. THE FACTS

The Davis-Besse Nuclear Power Station is a commercial nuclear power plant located approximately twenty-five miles east of Toledo, Ohio. In 1971, the Atomic Energy Commission issued a permit authorizing the construction of the facility. Construction was completed and an operating license was issued by the NRC in 1977. Although the facility began commercial operation producing electricity in 1978, the plant was temporarily shut down following a loss of feedwater on June 9, 1985. After reviewing the facility's design, the NRC Commissioners authorized the restart of Davis-Besse on November 21, 1986. In October 1986, both petitioners in this case, The Toledo Coalition for Safe Energy and the State of Ohio, filed petitions with the NRC pursuant to 10 C.F.R. Sec. 2.206 to suspend or terminate the Davis-Besse license and to issue an order prohibiting restart of Davis-Besse.

In their petitions, both parties cited several deficiencies in the emergency plan for Davis-Besse. The most notable of these flaws were that the Federal Emergency Management Agency [FEMA] had not formally approved the emergency plan; that the governor, an original drafter of the plan, had withdrawn his support; that the plan failed to include a portion of Lucas County within the Emergency Planning Zone (EPZ), even though it was within a ten mile radius of the plant; and finally that the NRC had failed to address the problems posed by a resolution of school union members, particularly bus drivers, not to participate in the planning or evacuation in the event of a nuclear disaster. Petitioners also requested that NRC keep Davis-Besse from operating pending resolution of the alleged deficiencies.

On November 19, 1986, the Director of the NRC Office of Inspection and Enforcement denied both petitions based on interim agreements reached with regard to all alleged deficiencies, and based also on FEMA's informal indication that the plan was adequate. The Director's decision became final twenty-five days later when the Commission chose not to review it. See 10 C.F.R. Sec. 2.206(c) (1988). Davis-Besse commenced restart as scheduled. By January 1987, shortly before oral argument, Davis-Besse was in its power ascension phase and operating at 38% of full power.

In November 1986, both petitioners filed petitions for review of the NRC's denial of their petitions and emergency motions to stay restart of Davis-Besse. On December 12, 1986, our court denied petitioners' stay request, but directed the clerk to set an accelerated briefing schedule on the petitions for review. On appeal, petitioners reassert the alleged deficiencies in Davis-Besse's emergency plan and contend that the Director acted arbitrarily and capriciously in refusing to institute the requested show cause proceedings under section 2.206.

II. REVIEWABILITY

The adequacy of safety plans at nuclear power facilities is a serious matter, and the nuclear accidents at Three Mile Island and later at Chernobyl in the Soviet Union bear witness to the importance of adequate emergency preparedness plans. Nevertheless, Congress has recognized the highly technical nature of such regulations and has accordingly circumscribed the power of the courts both to review and to overturn decisions made by the NRC. As the Supreme Court has noted, "the Commission is making predictions, within its area of special expertise, at the frontiers of science. When examining this kind of scientific determination, as opposed to simple findings of fact, a reviewing court must generally be at its most deferential." Baltimore Gas & Electric Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
868 F.2d 810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-ohio-v-nuclear-regulatory-commission-ca6-1989.