STATE OF NEW JERSEY VS. MICHAEL S. HETZEL (14-05-1100, ATLANTIC COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided July 18, 2017·No. A-0347-16T4·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-0347-10T1

MICHAEL A. WALTER BUILDERS, INC., Plaintiff-Respondent, v. BARBARA BEDNAR,

Defendant-Appellant.

Telephonically argued June 3, 2011 – Decided September 23, 2011

Before Judges R. B. Coleman, Lihotz and J. N. Harris.

On appeal from the Superior Court of New Jersey, Law Division, Cape May County, Docket No. L-553-04.

Keith A. Bonchi argued the cause for appellant (Goldenberg, Mackler, Sayegh, Mintz, Pfeffer, Bonchi & Gill, attorneys;

Mr. Bonchi, of counsel and on the briefs;

Rosann Allen, on the briefs).

Stephen W. Barry argued the cause for respondent (Barry, Corrado, Grassi & Gibson, P.C., attorneys; Mr. Barry, on the brief).

PER CURIAM Defendant Barbara Bednar appeals from a final judgment granting relief to plaintiff Michael A. Walter Builders, Inc. following a bench trial, and an order dismissing her

counterclaim. On appeal, defendant argues the trial court's factual findings are not supported by the record and certain legal conclusions supporting the relief ordered in favor of plaintiff and in dismissing her counterclaim were reached in error. We affirm.

These facts are contained in the trial record. Defendant owned the Heritage Inn Motel in Cape May. Defendant had obtained architectural and mechanical drawings for the motel's proposed modifications that were prepared by architect Blane Steinman, mechanical engineer John Schade, P.E., and structural engineer Tom Shepard. After reviewing these materials, plaintiff's principal, Michael A. Walter, drafted estimates for completion of the job and submitted his "Proposal" dated November 20, 2003, which was accepted by defendant. In the contract, plaintiff, designated as "the Builder," would construct a third-floor addition to the motel and perform other renovations1 for defendant, designated as "the Customer," for the agreed sum of $1,037,300.

Certain provisions of the proposal as accepted by the parties as their contract are relevant to our review. First,

1 Plaintiff had drafted three proposals for defendant, the last of which was executed by the parties bearing the date of November 20, 2003 but actually signed sometime in late January 2004.

the proposal expressly incorporated Steinman's architectural plans that utilized Schade's mechanical specifications for thirty-three Mitsubishi "heat pump systems at 14,500 BTUs cooling."2 Also, the plans required each room to be equipped with condenser and air handling units from the same manufacturer with the same energy output of 14,500 BTUs.

Second, the agreement included a payment schedule to provide fourteen draws. Each draw was in a stated amount and was due upon completion of various stages of the project.

Third, all renovations and the addition were to be completed within six months from the date construction commenced, or by May 20, 2004. The agreement allowed a thirty- day extension for weather-related delays.

Fourth, additional general provisions: (1) mandated any changes were not effective "unless in writing, signed by both Builder and Customer"; (2) required builders' risk insurance be "provided by [the] Builder to [the] Customer for [the] new

2 A BTU, short for British Thermal Unit, is a basic measure of thermal energy. One BTU is the amount of energy needed to heat one pound of water one degree Fahrenheit, measured at its heaviest point. When speaking of cooling power, the BTU works in reverse. The air-cooling power of an air conditioning system refers to the amount of thermal energy removed from an area. The higher the BTU output, the more powerful the heating or cooling. http://www.eia.gov/emeu/consumptionbriefs/cbecs/ pbawebsite/office/office_refbtu.htm (last visited August 30, 2011).

addition" and the Customer would provide home-owner's insurance "for [the] existing hotel"; (3) provided the "Builder will guarantee all workmanship of [the B]uilder and all of [the] Builder's Subcontractors, for one year from the day of settlement."

Two additional provisions listed under "Additional Clauses"

must also be mentioned. Subsection (F) stated, in pertinent part:

Additional work may be performed on hotel.

Cost for work will be priced by Builder and accepted by Customer. A spreadsheet for additional items will be provided and updated by Builder periodically. . . .

Payments for work shall be made the beginning of each month, during construction. Ongoing cost for additional work shall not exceed 2% of the total house [sic] construction cost, as stated [i]n this [c]ontract.

Additional work performed will affect the time of [a]ddition/renovation completion.

. . .

and subsection (J) provided:

Failure to insist upon strict compliance with any of the terms, covenants or conditions hereof shall not be deemed a waiver of such term, covenant or condition, nor shall any waiver or relinquishment of any right or power hereunder at any one or more times be deemed a waiver or relinquishment of such right or power at any other time.

The construction did not proceed smoothly. We will discuss the dilemmas which bear on the parties' claims in litigation.

As the details of the agreement were ironed out, plaintiff commenced demolition on November 20, 2003. The first step was to remove the second floor ceilings, erect scaffolding, and construct the third-floor "block walls" atop the second floor. Plaintiff used subcontractors for this job. It was decided the second floor roofing would be removed and the block for the third-floor wall would be laid in a piecemeal fashion because of "weather concerns." Walter explained:

[Y]ou just can't build a wall straight up and then build the back wall and then another side wall . . . [i]t has to be done simultaneously with another room. . . . Because a block wall might be up six feet, another block wall might be up four foot, another one up two foot. So, it wasn't on a level plane where we could put boards across and tarp [the open roof] . . . .

To protect the property from water damage during this process, plaintiff placed a tarp over the block walls and laid wooden planks on the tarps to hold them in place. Also, a rope was woven through the eyelets of the tarps and tied to the sides of the building.

During November and December 2003, before the new roof was shingled, three rainstorms occurred. Notwithstanding the protective measures employed, "[w]hen the storms came through,

there [were] heavy winds that ripped the tarps off and water got into the [m]otel." After the first storm in November, plaintiff added ropes and tarps, but "still the storm[water] got in[,]" damaging the sheetrock ceilings of the first floor, the first and second-floor carpeting, and some of the furniture stored in the first-floor rooms.

Upon discovering the extent of the damage, plaintiff suggested the parties' submit claims to their respective insurance carriers. Plaintiff hired subcontractors to restore the existing structure. This work included installing new sheetrock on the ceilings and walls; removing the old and installing new carpeting; repairing bathroom tile damage and "put[ting] new trim [], new doors, and paint" on the walls. At the same time, plaintiff continued construction of the third floor, believing "the insurance companies would take care of the cost[s]" which the parties would "sort[] out later."

Because of these construction delays, the parties agreed the new third-floor guest rooms would be finished for the summer and the meeting room, exercise room, and owner's quarters could be completed in the fall. Although the third-floor rental rooms were completed on May 26, 2004, restoration of the first and second floor rooms was not completed until immediately prior to the July Fourth weekend.

Free access — add to your briefcase to read the full text and ask questions with AI

STATE OF NEW JERSEY VS. MICHAEL S. HETZEL (14-05-1100, ATLANTIC COUNTY AND STATEWIDE), (N.J. Ct. App. 2017).

STATE OF NEW JERSEY VS. MICHAEL S. HETZEL (14-05-1100, ATLANTIC COUNTY AND STATEWIDE) (STATE OF NEW JERSEY VS. MICHAEL S. HETZEL (14-05-1100, ATLANTIC COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Home Owners Construction Co. v. Borough of Glen Rock
169 A.2d 129 (Supreme Court of New Jersey, 1961)
McDonald v. Mianecki
398 A.2d 1283 (Supreme Court of New Jersey, 1979)
Balsamides v. Protameen Chemicals, Inc.
734 A.2d 721 (Supreme Court of New Jersey, 1999)
Salvatore v. Trace
262 A.2d 385 (Supreme Court of New Jersey, 1970)
Salvatore v. Trace
262 A.2d 409 (New Jersey Superior Court App Division, 1969)
Spinks v. Township of Clinton
955 A.2d 304 (New Jersey Superior Court App Division, 2008)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Ramapo Brae Condo. v. Bergen Cty.
746 A.2d 519 (New Jersey Superior Court App Division, 2000)
Nieder v. Royal Indemnity Insurance
300 A.2d 142 (Supreme Court of New Jersey, 2004)
Reynolds Offset Co., Inc. v. Summer
156 A.2d 737 (New Jersey Superior Court App Division, 1959)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Headley v. Cavileer
82 A. 908 (Supreme Court of New Jersey, 1912)
Cooper v. Hawley
38 A. 964 (Supreme Court of New Jersey, 1897)