State of Missouri, ex rel. Attorney General Chris Koster and Missouri Department of Natural Resources v. Didion Land Project Association, LLC, Thomas T. Stewart, Daniel Fetsch, Judith Fetsch and Epic Contracting, LLC

CourtMissouri Court of Appeals
DecidedSeptember 15, 2015
DocketED101149
StatusPublished

This text of State of Missouri, ex rel. Attorney General Chris Koster and Missouri Department of Natural Resources v. Didion Land Project Association, LLC, Thomas T. Stewart, Daniel Fetsch, Judith Fetsch and Epic Contracting, LLC (State of Missouri, ex rel. Attorney General Chris Koster and Missouri Department of Natural Resources v. Didion Land Project Association, LLC, Thomas T. Stewart, Daniel Fetsch, Judith Fetsch and Epic Contracting, LLC) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Missouri, ex rel. Attorney General Chris Koster and Missouri Department of Natural Resources v. Didion Land Project Association, LLC, Thomas T. Stewart, Daniel Fetsch, Judith Fetsch and Epic Contracting, LLC, (Mo. Ct. App. 2015).

Opinion

In the Missouri Court of Appeals Eastern District DIVISION ONE

STATE OF MISSOURI, ex rel. ATTORNEY ) No. ED101149 GENERAL CHRIS KOSTER AND ) MISSOURI DEPARTMENT OF NATURAL ) Appeal from the Circuit Court RESOURCES, ) of St. Charles County ) Appellants, ) Hon. Richard K. Zerr ) vs. ) ) DIDION LAND PROJECT ASSOCIATION, ) LLC, THOMAS T. STEWART, DANIEL ) FETSCH, JUDITH FETSCH and EPIC ) CONTRACTING, LLC, ) Filed: ) September 15, 2015 Respondents. )

The State of Missouri and the Department of Natural Resources (collectively “the State”)

appeal from the trial court’s dismissal of its amended petition against the Didion Land Project,

LLC. We reverse and remand.

In 2011, the State filed a petition for injunctive relief and civil penalties against Didion

and its individual owners alleging violations of various Missouri environmental laws. Didion

operated a foundry at a site in St. Charles County until 2009, at which time Didion began

demolition of the foundry facility. The petition alleged that Didion failed to perform an asbestos

inspection or notify the DNR of the demolition. It also alleged that at various times known and

unknown, Didion generated solid waste at the site without determining whether the waste was

hazardous and then unlawfully dumped that solid waste on the ground and in nearby waters. The

State also alleged that on three occasions in 2011, Didion unlawfully refused the DNR access to

the site to conduct a compliance inspection regarding the solid waste. The State asserted that each of these actions was a violation of a specific environmental statute or regulation. The State

sought preliminary and permanent injunctive relief prohibiting Didion from further violations of

these laws and civil penalties for each day Didion was in violation.

The State applied for and was granted a temporary restraining order prohibiting Didion

from taking any action at the site. The State also applied for a preliminary injunction, and in

February of 2012, the court entered the parties’ agreed order of preliminary injunction. Therein,

Didion was ordered to properly characterize, transport and dispose of various materials at the

site. Once completed, Didion would be allowed to prepare the site for construction of a storage

building. Foundry sand also was to be characterized and disposed of accordingly. Didion was

prohibited from taking any other action at the site. The tasks in the preliminary injunction were

to be completed in ninety days.

Shortly thereafter, the State filed a motion to show cause why Didion should not be held

in contempt for violating the preliminary injunction. The court held a hearing in April of 2012,

after which the parties agreed on a resolution, and the court assessed a civil penalty of $2,000

against Didion for its failure to comply and ordered Didion to obey the orders in the preliminary

injunction. In December of 2012, the State moved again to show cause why Didion should not

be held in contempt, alleging that only a portion of the hazardous waste and materials had been

dealt with, that organic peroxide remained and that new materials were being stored on the site;

moreover, Didion had not yet paid the penalty for its first violation of the preliminary injunction.

The court entered another order of contempt in which Didion was again ordered to comply with

all the court’s orders and applicable environmental laws and assessed an additional penalty of

$6,000 for failing to pay the earlier assessed penalty and failure to comply with the court’s

previous orders. In January of 2013, that order of contempt was amended to indicate some

completion of the preliminary injunction tasks and to extend the time in which to complete

others. 2 By June of 2013, the parties still disagreed as to whether the tasks in the preliminary

injunction had been fully completed. The State filed its third motion to show cause why the

court should not hold Didion in contempt, and Didion filed a motion to dissolve the preliminary

injunction. The State also filed an application for a new temporary restraining order and

preliminary injunction. In July of 2013, the court held a hearing, at the outset of which, it stated

expressly that it was taking up the State’s motion to show cause and Didion’s motion to dissolve

the preliminary injunction. The court also granted the State leave to file an amended petition,

over no objection from Didion, although it was not actually filed until much later. The parties

presented evidence and arguments over two days.

Shortly thereafter, the court issued its “findings and judgment.” Therein, the court

identified three matters being taken up by the court: the State’s motion to show cause, Didion’s

motion to dissolve the preliminary injunction and the State’s new motions for temporary

restraining order and preliminary injunction. The court found that there was no longer any

hazardous waste at the site and the concerns that necessitated the entry of a temporary restraining

order and preliminary injunction no longer existed. It also found that there was no current

irreparable harm to justify the issuance of a new temporary restraining order or preliminary

injunction. Finally, the court found that while Didion had not further violated the preliminary

injunction, it had failed to pay the penalties previously and properly entered for earlier violations.

The court denied the State’s motion to hold Didion in contempt, denied the application for

another temporary restraining order and preliminary injunction and granted Didion’s motion to

dissolve the preliminary injunction order except as to the $8,000 in civil penalties Didion still

owed and as to the foundry sand on site that Didion was still obligated to “deal with” in

compliance with all applicable laws.

In November of 2013, the State actually filed the amended petition it had been granted

leave to file months earlier. Therein—in addition to repeating the allegations and requests for 3 relief stated in the original petition—the State alleged that Didion stored hazardous waste at the

site from October of 2009 until at least December of 2012 and therefore was a hazardous waste

facility and had failed to comply with numerous requirements imposed on such facilities;

Didion’s storage of hazardous waste without proper security or a contingency plan created a

public nuisance; since September of 2010, Didion stored foundry sand, which it intermittently

discharged into the waters of the state without a permit; and that sometime during 2012 and

2013, Didion excavated without notice as required of underground facility operators. The State

again sought preliminary and permanent injunctive relief prohibiting Didion from further

violations of environmental laws and from further public nuisance and sought civil penalties for

each day Didion violated those laws. Didion filed a counterclaim for enforcement of the

Missouri sunshine law and statutory damages a couple of days later.

The trial court then issued an order directing the parties to “review orders and determine

if issues remain” before the court would “entertain trial setting and/or motions to dismiss.” The

State responded to the court’s order with a letter explaining that while the court had concluded

there was no necessity for a preliminary injunction, no decision had yet been made on any of the

alleged violations of environmental laws or other allegations and requests for relief stated in the

amended petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shores v. Express Lending Services, Inc.
998 S.W.2d 122 (Missouri Court of Appeals, 1999)
Richard Brown v. Susan Brown-Thill
437 S.W.3d 344 (Missouri Court of Appeals, 2014)
Pathway Financial v. Schade
793 S.W.2d 464 (Missouri Court of Appeals, 1990)
American Standard Insurance Co. of Wisconsin v. Stinson
404 S.W.3d 303 (Missouri Court of Appeals, 2012)
Allen v. Titan Propane, LLC
404 S.W.3d 914 (Missouri Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
State of Missouri, ex rel. Attorney General Chris Koster and Missouri Department of Natural Resources v. Didion Land Project Association, LLC, Thomas T. Stewart, Daniel Fetsch, Judith Fetsch and Epic Contracting, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-missouri-ex-rel-attorney-general-chris-koster-and-missouri-moctapp-2015.