State of Ill. v. Borg, Inc.

548 F. Supp. 972, 1982 U.S. Dist. LEXIS 15214
CourtDistrict Court, N.D. Illinois
DecidedSeptember 10, 1982
Docket79 C 5253, 79 C 3046 and 79 C 3077
StatusPublished
Cited by4 cases

This text of 548 F. Supp. 972 (State of Ill. v. Borg, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Ill. v. Borg, Inc., 548 F. Supp. 972, 1982 U.S. Dist. LEXIS 15214 (N.D. Ill. 1982).

Opinion

MEMORANDUM OPINION AND ORDER

SHADUR, District Judge.

As indicated in prior opinions in these class actions, plaintiff property owners charge 22 piping construction companies and 36 individuals with bid-rigging, price-fixing and job allocation in the Chicago area from 1956 to 1977. However the current motion deals with only four individual transactions, three involving the Board of Education of Evanston Township High School District No. 202 (“District”) and one involving Mutual Trust Life Insurance Co. (“Mutual Trust”). 1 Defendant contractors (more accurately subcontractors) in those transactions move for summary judgment, claiming the two owners are “indirect purchasers” within the meaning of Illinois Brick Co. v. Illinois, 431 U.S. 720, 97 S.Ct. 2061, 52 L.Ed.2d 707 (1977), and are thus barred from suing under the antitrust laws. For the reasons stated in this memorandum opinion and order, defendants’ motion is denied.

Facts 2

There is no question that District 202 and Mutual Trust were not literally “direct purchasers” from the piping contractors, for in each of the four transactions there was a general contractor ultimately interposed between the owner and the piping contractor. That however is the beginning not the end of the inquiry, for the facts of each relationship must be examined to see whether a cost-plus or equivalent arrangement takes the transaction out of the Illinois Brick rule (as that case itself recognized, 431 U.S. at 732 n. 12, 97 S.Ct. at 2067 n. 12).

*974 District 202 Transactions

First of the three District 202 construction projects was a building addition to Evanston Township High School in 1956. Before entering into the general contract District 202 obtained separate bids for general construction and the several mechanical trades (plumbing, heating, ventilating and electrical work). District 202’s Board accepted the low bids and awarded contracts in each category. Indeed the piping contractor’s bid to District 202 specifically stated:

We agree to perform the Mechanical work on which this proposal is offered as sub-contract under the General Construction Contract at the price quoted above.

In turn the general contractor agreed to assume “overall direction and administrative supervision and coordination of work by the mechanical trades. . . . ” As the general contract said, the mechanical trades bids:

were accepted by the Owner [District 202] March 29, 1956. The Owner then authorized the execution of said work by subcontract under a General Construction Contract with Coath & Goss, Inc. under the provisions of Paragraph 48, Section I of the Specifications and the Proposals of the respective bidders.

As Exhibit 1 to this opinion (page 2 of the general contract) shows, the “contract sum” was specifically identified as the sum of the five individual proposals of the successful bidders, including that of a defendant here (Hanley & Company).

Second of the three District 202 projects was a 1962 third floor addition to the High School’s technical building. District agreed to pay general contractor Erik A. Borg Company the actual “Cost of the Work” plus a $10,000 fixed fee for the general contractor’s services. “Cost of the Work” was defined as (emphasis added):

the actual job costs incurred in the performance of authorized work, including cost of wages of a Superintendent, all Foremen, Mechanics and Laborers at the job site, together with insurance, payroll taxes, etc., thereon; costs of materials, fabricated items, equipment and fixtures incorporated in the Work; the rental of any special equipment required to perform the Work; and all subcontractors’ work performed under this Contract.

Then the general contractor obtained subcontractors’ bids, submitted the lowest figures to District 202 for approval and let the subcontracts to the lowest approved bidders.

Finally, the 1966 alterations and additions to the High School involved an identical “cost of the work plus a fee” (in that instance the fixed fee was $300,000) to general contractor George Sollitt Construction Company. Again District 202 agreed to reimburse the general contractor for:

all costs necessarily incurred for the proper execution of the work and paid directly by the Contractor, such costs to include the following items, and to be at rates not higher than the standard paid in the locality of the work except with prior consent of the Owner; . . .
6.10 The amounts of all sub-contracts included in the scope of the work.

And again the contract reflected District 202’s approval and acceptance of the piping subcontractor and its specific bid as part of the “cost.”

Mutual Trust Transaction

Mutual Trust had its Oak Brook, Illinois headquarters building constructed in 1973. Its agreement with general contractor Turner Construction Co. (“Turner”) included a fixed base fee of $109,410 together with the classic cost-plus language:

The Owner shall pay to the Contractor, or directly, the cost of the Work, which shall include all costs reasonably or necessarily incurred in connection therewith (except those costs specified in the Agreement to be borne by the Contractor): such costs to include the following items: . . .
(h) All subcontracts let in connection with the Work.

It had two variants frequently coupled with cost-plus contracts in the construction in *975 dustry: a guaranteed maximum price 3 (in this case $3,126,110) and a provision for sharing any savings if “cost of the Work” ultimately proved less than that maximum. That sharing provision took the form of an added fee to Turner of 30% of the shortfall, so that Mutual Trust received 70% of any savings. In fact the actual “cost of the Work” came in below the $3,126,110 ceiling.

Illinois Brick and Its Cost-Plus Exception

Illinois Brick announced the general rule that only direct purchasers from antitrust defendants could sue for treble damages under Clayton Act § 4. In the Supreme Court’s view the alternative of permitting suits by indirect purchasers too — -forcing a tracing and apportionment of the illegal overcharge along the chain of distribution— “would add whole new dimensions of complexity to treble damage suits and seriously undermine their effectiveness” (431 U.S. at 737, 97 S.Ct. at 2070).

But where that tracing-apportionment problem is not present — where the indirect purchaser’s damages are plainly ascertainable without having to reconstruct the direct purchaser’s probable competitive market response to the overcharge — the reason for the Illinois Brick rule vanishes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
548 F. Supp. 972, 1982 U.S. Dist. LEXIS 15214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-ill-v-borg-inc-ilnd-1982.