State of Delaware, Department of Natural Resources & Environmental Control v. Service Transport Group, Inc.
This text of State of Delaware, Department of Natural Resources & Environmental Control v. Service Transport Group, Inc. (State of Delaware, Department of Natural Resources & Environmental Control v. Service Transport Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
COURT OF CHANCERY OF THE STATE OF DELAWARE MORGAN T. ZURN LEONARD L. WILLIAMS JUSTICE CENTER VICE CHANCELLOR 500 N. KING STREET, SUITE 11400 WILMINGTON, DELAWARE 19801-3734
October 13, 2023
Devera B. Scott, Esquire Michael W. Teichman, Esquire State of Delaware Department of Justice Parkowski, Guerke & Swayze, P.A. 102 W. Water Street 1105 North Market Street, 19th Floor Dover, DE 19904 Wilmington, DE 19801
Ryan M. Ernst, Esquire Bielli & Klauder, LLC 1204 North King Street Wilmington, DE 19801
RE: State of Delaware, Department of Natural Resources & Environmental Control v. Service Transport Group, Inc., et al., Civil Action No. 2022-0009-MTZ
Dear Counsel:
Thank you for your September 12, 2023, status update describing the parties’
efforts to agree on the timing, necessary measures, and authority for winding down
Service Transport Group, Inc’s (“STG”) asbestos transfer station after STG failed to
comply with its environmental regulatory obligations in the time afforded by this
Court’s preliminary injunction. Under that three-phase preliminary injunction, if
STG did not come into compliance within Phase Two as defined therein, “the Court
will again enjoin the accepting of new waste at the facility until such time as the
Court issues a final judgment resolving this matter (‘Phase Three’). During Phase DNREC v. Service Transport Group, Inc, et al., Civil Action No. 2022-0009-MTZ October 13, 2023 Page 2 of 6
Three, third party asbestos generators shall be allowed to remove their waste from
the facility.”1 We are in Phase Three.
At the most recent hearing in this matter, STG agreed it could no longer
operate as a transfer station and requested an opportunity to present a closure plan
to DNREC and the Court.2 I tried to make two points clear: STG had not complied
with this Court’s preliminary injunction, and STG had lost the opportunity to
negotiate with customers who wished to retake their asbestos to fulfill their
regulatory obligations.3 I also asked for a few pieces of information: STG’s plan
for operations after ending transfer station operations, DNREC’s promised
“statutory authority” authorizing DNREC to bring in a contractor to clean up the
site, and DNREC’s statutory or regulatory authority to spend funds held after calling
STG’s letter of credit.4
The terms of Phase Three set forth the consequences for not meeting the
obligations imposed in Phase Two. Based on the evidentiary record and the progress
1 Docket Item (“D.I.”) 49 at 3–4. 2 D.I. 100 at 49. 3 Id. at 27–29, 49. 4 Id. at 40–41, 43–44. DNREC v. Service Transport Group, Inc, et al., Civil Action No. 2022-0009-MTZ October 13, 2023 Page 3 of 6
the parties have made, I believe additional terms are warranted in Phase Three. It is
hereby ORDERED that STG shall:
1. Cease accepting new asbestos.
2. Cease preventing abatement contractors from picking up their waste.
3. Refrain from engaging in any asbestos handling or remediation for which STG is not currently licensed.
4. Certify in an affidavit that the Pacific Cargo lease has terminated and set forth the plan for removing its equipment.
5. Conduct soil and air sampling as the parties agreed in the September 12 letter. STG is not presently required to perform groundwater sampling.
STG shall keep the Court informed of its progress in the following ways:
1. Filing weekly reports in the form requested by DNREC in the September 12 letter. STG shall also serve such reports on DNREC at the time they are filed with the Court.
2. Providing the Court notice within three business days of entering into a purchase and sale agreement for STG’s property. STG shall also serve any such notice on DNREC at the time it is provided to the Court.
While DNREC moved for contempt, I do not believe that more coercive
sanctions are warranted at this time, for the reasons discussed at argument. That
said, STG appears reluctant to accept my previous ruling that Phase Three requires DNREC v. Service Transport Group, Inc, et al., Civil Action No. 2022-0009-MTZ October 13, 2023 Page 4 of 6
it to permit customers to reclaim their asbestos.5 If STG refuses to allow any
customer to reclaim their asbestos, the sanction will be a fine of $5,000 customer per
day of refusal, payable to the Register in Chancery.
As to the parties’ disagreement over the funds DNREC drew from STG’s
letter of credit, some background is necessary. DNREC issued STG a waste transfer
station permit pursuant to 7 Del. C. § 6003. Title 7, Regulation 1301 of the Delaware
Administrative Code obligated STG, as a permittee, to obtain and provide assurance
that “financial costs associated with closure, post-closure care, and corrective action
could be met.”6 Among other things, STG’s chosen financial assurance mechanism
“must ensure that funds will be available in a timely fashion when
needed.”7 Regulation 1301 mandates that the “mechanisms used to demonstrate
financial assurance under this section must ensure that the funds necessary to meet
the costs of closure, post-closure care, and corrective action for known releases will
5 Id. at 10 (acknowledging that STG will not let customers pick up waste without payment); id. at 16 (“[W]e still want an opportunity to work with these . . . recalcitrant customers . . . .”); D.I. 101 at 3–4 (“STG has . . . elected to treat all unclaimed [asbestos] as abandoned and remove it, and pursue such remedies as it has against abatement contractors and generators thereafter.”). 6 7 Del. Admin. C. §§ 1301-4.1.11.1 to -11.2. 7 Id. § 1301-4.1.11.2.3.2. DNREC v. Service Transport Group, Inc, et al., Civil Action No. 2022-0009-MTZ October 13, 2023 Page 5 of 6
be available whenever they are needed.”8 It also mandates that the amount of funds
assured be “sufficient to cover the costs of closure, post-closure care, and corrective
action for known releases when needed.”9 STG provided a letter of credit as
financial assurance; on July 12, 2022, the bank informed DNREC that the letter of
credit would not be renewed.10 STG failed to provide alternative financial assurance
within ninety days as required, so, as authorized by Regulation 1301, DNREC drew
on the assurance funds.11
Now that STG is in the closure process, the parties disagree as to how those
funds should be administered. Their disagreement is understandable: the
regulations appear to be silent on how the funds should be administered once
DNREC draws on them. DNREC seeks to withhold the funds until STG’s station is
closed and all asbestos has been removed. STG wishes to have the funds released
to it incrementally to cover closure costs. I fall back on the intentions behind the
financial insurance program: to set aside sufficient funds, and to make them
available in a timely fashion when needed to meet the costs of closure. To meet
8 Id. § 1301-4.1.11.2.4. 9 Id. § 1301-4.1.11.2.3.1. 10 D.I. 97, Ex. A. 11 7 Del. Admin. C. § 1301-4.1.11.2.4.3, Condition 8. DNREC v. Service Transport Group, Inc, et al., Civil Action No. 2022-0009-MTZ October 13, 2023 Page 6 of 6
these goals, DNREC must make funds available to STG to pay for STG’s costs of
closure.
STG shall submit a detailed closure plan to the Court, serving DNREC, within
twenty days. With that plan in place, STG’s proposal that DNREC release funds to
STG in the amount of $3,000 per trailer removed appears reasonable and compliant
with Regulation 1301.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
State of Delaware, Department of Natural Resources & Environmental Control v. Service Transport Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-delaware-department-of-natural-resources-environmental-control-delch-2023.