State of Colo. v. Asarco, Inc.

616 F. Supp. 822, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1985 U.S. Dist. LEXIS 16365
District Court, D. Colorado·Decided August 29, 1985·No. Civ. A. 83-C-2383·Published·Cited by 9 cases

Opinion

MEMORANDUM OPINION AND ORDER

CARRIGAN, District Judge.

In its first amended complaint, the State of Colorado (“State” or “plaintiff”) alleges that ASARCO is liable under § 107 of the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), 42 U.S.C. § 9607, for damages for injury to, destruction of, and/or loss of natural resources caused by releases of hazardous substances from ASARCO’s Globe Plant, and for response costs incurred and to be incurred by the State at the site. The State also asserts pendent state law claims for statutory nuisance, strict liability, and negligence.

ASARCO has moved to dismiss the plaintiff’s CERCLA claims pursuant to Fed.R. Civ.P. 12(b)(6), or, in the alternative, for summary judgment on these claims under Fed.R. Civ.P. 56. The parties have briefed the issues, and oral argument would not assist in resolving them.

*824 I.

ASARCO first argues that the plaintiff’s claims are barred by its failure to present a claim letter to ASARCO sixty days before commencing this action as required by CERCLA § 112(a), 42 U.S.C. § 9612(a). That section provides:

“All claims which may be asserted against the Fund pursuant to section 111 of this title [42 USC § 9611] shall be presented in the first instance to the owner, operator, or guarantor of the vessel or facility from which a hazardous substance has been released, if known to the claimant, and to any other person known to the claimant who may be liable under section 107 of this title [42 USC § 9607], In any case where the claim has not been satisfied within sixty days of presentation in accordance with this subsection, the claimant may elect to commence an action in court against such owner, operator, guarantor, or other person or to present the claim to the Fund for payment.”

A “claim” is defined as a “demand in writing for a sum certain.” 42 U.S.C. § 9601(4). Plaintiff presented to ASARCO a “Notice and Claim Against ASARCO Incorporated for Costs and Damages Pursuant to 42 U.S.C. § 9612,” dated December 2, 1983. In that claim, the plaintiff notified ASARCO that, based upon information and belief, releases of hazardous substances, including arsenic, lead, cadmium, and selenium, had occurred at the Globe Plant facility and had contaminated natural resources of the State, including surface soils, surface water, ground water, and air. The notice concluded, “The state hereby makes its claim pursuant to section 112 of the Act (42 U.S.C. § 9612) and demands that the state be compensated for costs and damages in the amount of $50,000,000 per release, subject to adjustment based on federal regulations and/or assessment of natural resource damage.” The complaint in this action was filed on December 9, 1983.

Indisputably, the State did not present its claim sixty days prior to commencing this action, nor did the claim demand a sum certain. The figure $50,000,000 per release is merely the statutory maximum for liability for damage to natural resources. 42 U.S.C. § 9607(c)(1)(D). The State gave no indication of the number of releases nor even an estimated value of actual damage to natural resources. ASARCO argues that presentment of a claim letter to a potentially responsible party is a condition precedent to bringing a § 107 action and that since the condition was not fulfilled, the claim must be dismissed. See Bulk Distribution Centers, Inc. v. Monsanto Co., 589 F.Supp. 1437 (S.D.Fla.1984) (before a private claimant can commence a cost recovery action against another private party, it must first serve a letter demanding a “sum certain” to cover the costs of the clean-up operation; presentment of a demand letter is a condition precedent to bringing the action.) United States v. Allied Chemical Crop., 587 F.Supp. 1205 (N.D.Cal.1984) (notice of claim pursuant to § 112(a) is a prerequisite to bringing suit under § 107, including actions brought by the government); see also Dedham Water Co. v. Cumberland Farms Dairy, Inc., 588 F.Supp. 515 (D.Mass.1983).

Plaintiff argues that presentation of a claim letter is not a jurisdictional prerequisite to suit under § 107. It bases this argument on the prefatory language of that section which states, “Notwithstanding any other provision or rule of law____” Plaintiff contends that this language means that § 107 stands completely apart from the procedures in § 112 (and from all other provisions of the Act.)

Other courts have relied on this language in holding that § 107 is entirely distinct from other sections of the Act and that § 107 is not subject to the procedures of § 112. See Homart Development Co. v. Bethlehem Steel Corp., 22 E.R.C. 1357, 1367 (N.D.Cal.1984); Pinole Point Properties v. Bethlehem Steel Corp., 596 F.Supp. 283, 288-89 (N.D.Cal.1984); United States v. Wade, 577 F.Supp. 1326, 1334-36 (E.D. Pa.1983); Wehner v. Syntex Corp., 22 E.R.C. 1373, 1375 (E.D.Mo.1983); United States v. Reilly Tar & Chemical Corp., *825 546 F.Supp. 1100, 1117-18 (D.Minn.1982). In my view, this is not a proper basis for holding § 112 inapplicable to § 107 actions. It is true that many of the provisions of § 112 apply only to claims asserted against the Superfund and have no meaning in a § 107 court action. However, § 112(d) contains the statute of limitations applicable to both court actions and claims against the Fund. The prefatory language of § 107 clearly was not intended to exempt § 107 actions from the statute of limitations. Section 112, therefore, cannot be ignored in its entirety; rather each of its provisions must be analyzed separately to determine its applicability.

While the prefatory language of § 107 does not resolve the issue, the language of § 112 itself suggests that the plaintiffs failure to comply with the notice requirement does not bar this action. Under § 112(a), the notice requirement applies to “All claims which may be asserted against the Fund pursuant to section 111 [42 U.S.C. § 9611]____” The plaintiffs claim in this case is not one which may be asserted against the Fund under § 111. The State could not obtain any money from the Fund for “restoration, rehabilitation, or replacement or acquisition of the equivalent of any natural resources” (§ 107(f)) because the Environmental Protection Agency (“EPA”) and the governor have not developed and adopted any plan for use of such funds as required by § 111(i).

Free access — add to your briefcase to read the full text and ask questions with AI

State of Colo. v. Asarco, Inc., 616 F. Supp. 822, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1985 U.S. Dist. LEXIS 16365 (D. Colo. 1985).

616 F. Supp. 822 (State of Colo. v. Asarco, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

People v. Salgado
444 P.3d 829 (Colorado Court of Appeals, 2019)
Kelley v. Thomas Solvent Co.
714 F. Supp. 1439 (W.D. Michigan, 1989)
Artesian Water Co. v. Government of New Castle County
659 F. Supp. 1269 (D. Delaware, 1987)
Utah State Department of Health v. Ng
649 F. Supp. 1102 (D. Utah, 1986)
Dedham Water Company v. Cumberland Farms Dairy, Inc.
805 F.2d 1074 (First Circuit, 1986)
United States v. Dickerson
640 F. Supp. 448 (D. Maryland, 1986)
Walls v. Waste Resources Corp.
640 F. Supp. 79 (E.D. Tennessee, 1986)
State of Idaho v. Bunker Hill Co.
634 F. Supp. 800 (D. Idaho, 1986)
State of Idaho v. Howmet Turbine Component Corp.
627 F. Supp. 1274 (D. Idaho, 1986)