The evidence objected to was clearly admissible and there was no error in overruling the objections thereto. It will be seen that the condemnor was seeking to acquire all rights of every kind, including those of a licensee or permittee, and in such a proceeding the condemnee is entitled to prove every element of consequential damage that may be relevant. There was no evidence as to whether the “permit” [108]*108to install the water line was written or oral or as to what the terms thereof may have been. But it is obvious that the condemnee had, on the faith of the license or permit, expended money in laying and installing the water line. The license or permit, not otherwise terminated, was sought to be condemned in this proceeding. Consequently, the loss of the line, or the interruption of a water supply by reason thereof, is an element of consequential damage, and evidence thereof was properly admitted. Code § 85-1404.
The testimony that the interruption of the water supply would make it necessary to drill a well to replace it was enough to support the estimate of $3,000 in consequential damages. Moreover, this testimony was elicited on cross-examination by the condemnor.
The general grounds of the motion were expressly abandoned in the oral arguments before the court.
Judgment affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
121 S.E.2d 275, 104 Ga. App. 106, 1961 Ga. App. LEXIS 616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-department-v-morton-gactapp-1961.