State Group Industrial (USA) Ltd. v. Murphy & Associates Industrial Services, Inc.

878 N.E.2d 475, 2007 Ind. App. LEXIS 2949, 2007 WL 4555276
CourtIndiana Court of Appeals
DecidedDecember 28, 2007
Docket82A04-0703-CV-158
StatusPublished
Cited by10 cases

This text of 878 N.E.2d 475 (State Group Industrial (USA) Ltd. v. Murphy & Associates Industrial Services, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Group Industrial (USA) Ltd. v. Murphy & Associates Industrial Services, Inc., 878 N.E.2d 475, 2007 Ind. App. LEXIS 2949, 2007 WL 4555276 (Ind. Ct. App. 2007).

Opinion

OPINION

ROBB, Judge.

Case Summary and Issues

The State Group Industrial (USA) Limited (“State Group”) appeals from the trial court’s judgment awarding State Group actual damages but denying State Group’s request for relief under Indiana Code section 34-24-3-1. State Group raises the sole issue of whether the trial court improperly denied it relief under this statute based on a contract provision. Concluding the Contract does not proscribe the relief sought by State Group, we remand with instructions that the trial court determine whether and to what extent damages under this statute are warranted.

Facts and Procedural History

State Group is a Delaware corporation authorized to transact business in Indiana, with its principal place of business in Evansville. Murphy & Associates (“M & A”) is an Indiana corporation with a principal place of business in Evansville. In 2000, the Army Corps of Engineers (the “Corps”) sought bids for a project based on the Sabine-Neches Waterway in Beaumont, Texas (the “Project”). The Project involved a control system, which would identify the salinity content of the water in the Sabine-Neches and relay the data to a control panel, which would in turn process the data and determine whether the tain-ter gates on the waterway’s dam should be opened or closed to regulate salt water infiltration.

State Group was a prime contractor on the Project. In June 2000 M & A requested information from State Group relating to the Project and prepared an estimate for supplying materials for the control system. Jeff Erk and Steve Murphy prepared M & A’s estimate, which came to $394,773. On August 9, 2000, Erk prepared a bill of materials, which listed all the materials that M & A would provide. Included in this list were Falmouth Scientific salinity probes, necessary components of the control system. On March 21, 2001, Murphy met with State Group employees to finalize the terms and conditions of the contract between M & A and State Group (the “Contract”). At this meeting, M & A confirmed that the salinity probes were part of the Contract, that M & A would provide engineering for the start-up process, and that M & A had prior experience with Corps projects.

The Contract’s payment schedule was as follows:

1.1 Due Upon Contract Award. $ 20,000.00
1.2 Due Upon Approval of Submittal Drawings & Documentation. $ 5,000.00
1.3 Due Upon Receipt of Equipment at M & A. $336,895.00
1.4 Due After Customer Acceptance/Witness Testing at M & A. $ 20,002.00
1.5 Due Upon Equipment Delivery/Shipment to Customer. $ 3,250.00
1.6 Due Upon Completion of Installation & Testing . $ 15,345.00
1.7 Due Upon Receipt of Final Deliverables $ 945.00
TOTAL. $401,437.00

Appellant’s Appendix, at 35.

On October 15, 2001, M & A submitted Invoice No. 965, which was prepared by Murphy, for payment number 1.3. Invoice No. 965 indicated that the terms of the Contract required that State Group was *477 required to make payment number 1.2 “Upon Submittal of Drawings and Documentation,” instead of upon approval of these documents. Id. at 144 (emphasis added). Invoice No. 965 also indicated that payment number 1.3 was “Due Upon Submittal Approval/M & A Ordering Equipment,” instead of upon receipt of the equipment. Id. (emphasis added). M & A had not discussed a change in payment terms with State Group. Also, at the time M & A delivered this invoice, it had not ordered or acquired any of the materials for the control system.

After receiving this invoice, State Group contacted M & A and requested proof of ownership of the materials, as the Corps required such proof before it would release payment. In response, M & A supplied State Group with documentation representing that it had paid in full for the materials, and that no other party had any claim on the materials. These representations were false. The trial court found that Murphy knew or should have known these representations were false and that he “made misleading written statements with the apparent intent to receive payment from the Corps.” Id. at 149.

On January 30, 2002, Murphy sent a letter to State Group indicating that payment on Invoice No. 965 was 107 days past due, at which time Murphy “knew or should have known that such representation was false and that according to the contract terms Invoice No. 965 was not due and payable until 60 days after the materials had been received at [M & A].” Id. Over the next few months, State Group made payments to M & A, making the final payment on May 6, 2002. M & A did not make its first payment to its supplier until three days after it received this final payment.

On August 19, 2002, M & A shipped materials to Beaumont. This shipment did not include the salinity probes and necessary cabling. On October 28, 2002, State Group forwarded a letter to M <& A informing it of the missing equipment. On November 11, 2002, State Group sent another such letter. On December 18, 2002, State Group’s General Manager, Steve Theodora, met with Murphy to discuss the missing materials. Theodora stated that he would be willing to discuss with the Corps the possibility of M & A receiving payment from the Corps on a “compassionate basis.” Id. at 154. Following discussions, the Corps indicated that it was not inclined to provide such relief.

On January 18, 2003, State Group notified M & A that State Group needed to review the software programming developed by M & A. On February 12, 2003, State Group provided M & A with a forty-eight-hour deficiency notice requesting supply of the salinity probes and cabling. M & A failed to supply the materials, and State Group was forced to hire a replacement subcontractor, KAPOS Machine Control. Additionally, M & A refused to provide the necessary software and start-up procedures, stating that it would begin these procedures after money it claimed State Group owed in relation to alleged finance charges and labor cost increases was placed in escrow. At this point, M & A also took the position that the salinity probes were not part of the Contract. State Group purchased the missing materials from KAPOS, and incurred additional on-site expenses resulting from M & A’s breach.

On April 2, 2003, M & A filed a complaint against State Group alleging breach of contract. On May 8, 2003, M & A filed its amended complaint. On May 8, 2003, State Group filed its response, affirmative defenses, and counterclaim alleging that M & A breached the Contract. On July 26, 2005, State Group filed its amend *478

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
878 N.E.2d 475, 2007 Ind. App. LEXIS 2949, 2007 WL 4555276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-group-industrial-usa-ltd-v-murphy-associates-industrial-indctapp-2007.