State ex rel. Yost v. Osborne Co., Ltd.

2022 Ohio 2627
Ohio Court of Appeals·Decided August 1, 2022·No. 2021-L-020·Published

Opinion

IN THE COURT OF APPEALS OF OHIO ELEVENTH APPELLATE DISTRICT LAKE COUNTY

STATE OF OHIO ex rel. CASE NO. 2021-L-020 DAVE YOST, OHIO ATTORNEY GENERAL, Civil Appeal from the

Plaintiff-Appellee, Court of Common Pleas

-v-

Trial Court No. 2014 CV 000166 OSBORNE CO., LTD., et al.,

Defendants-Appellants.

OPINION

Decided: August 1, 2022

Judgment: Affirmed

Dave Yost, Ohio Attorney General; Gregg H. Bachmann and Catherine A. English, Assistant Attorneys General, Environmental Enforcement Section, 30 East Broad Street, 25th Floor, Columbus, OH 43215 (For Plaintiff-Appellee).

Richard N. Selby, II and Grant J. Keating, Dworken & Bernstein Co., LPA, 60 South Park Place, Painesville, OH 44077 (For Defendants-Appellants).

THOMAS R. WRIGHT, P.J.

{¶1} Appellants—Osborne Co., Ltd. and the Executors of the Estate of Jerome T. Osborne—appeal from the trial court’s judgment entry imposing a civil penalty for violations of Revised Code Chapter 6111, Ohio’s Water Pollution Control Laws. The judgment is affirmed.

{¶2} The East Branch Chagrin River (“River”) is a rare, cold water stream the state of Ohio seeks to protect. Between 2001 and 2007, pursuant to an agreement with the Village of Kirtland Hills (“Village”), Defendants Osborne Co., Ltd. (“Osborne Co.”) and Jerome T. Osborne (“Osborne”) dredged the River twenty-four times. Defendants placed eight spoil piles of dredged material, each eight to twenty feet high, in the riverbed and along the riverbank on property owned by either the Village or Osborne, with the exception of one pile placed on property owned by the Oliva family (“Oliva Pile”). Neither Defendants nor the Village applied to the Ohio Environmental Protection Agency (“OEPA”) or the Army Corps of Engineers for a permit for this activity. The OEPA discovered the activity in July 2007 and ordered Defendants to cease. The Defendants ceased all activity in the River, but the spoil piles remained until the Village removed all but the Oliva Pile in November 2013. The Oliva Pile has not been removed.

{¶3} The extensive procedural history of this matter is recounted in two previous opinions of this court: State ex rel. DeWine v. Osborne Co., Ltd., 2018-Ohio-3109, 104 N.E.3d 843 (11th Dist.) (“Osborne I”) and State ex rel. Yost v. Osborne Co., Ltd., 2020- Ohio-3090, 154 N.E.3d 183 (11th Dist.) (“Osborne II”).

{¶4} The trial court found Defendants jointly and severally liable for violating R.C.

6111.04(A) and 6111.07(A) by dredging the River and leaving the spoil piles in place, thereby causing pollution of the River. The trial court ordered injunctive relief in favor of the state of Ohio and imposed civil penalties against Defendants for dredging ($180,000.00) and for the spoil piles ($224,240.00). This court reversed the judgment in part, holding that dredging the River was not a violation of the specific statutes pleaded in the complaint. Osborne I at ¶ 47. We remanded the matter to the trial court “to make

a finding specifically related to the violations alleged in the complaint [i.e., discharge of materials into the East Branch Chagrin River without permits, as provided in R.C. 6111.04(A) and R.C. 6111.07(A)] and thereafter limit any civil penalty and injunctive relief to the consequences of that conduct.” Id. at ¶ 72.

{¶5} On remand, the trial court considered only the findings in its original decision that related to the spoil piles and pollution of the River, incorporated those findings into its decision, and again imposed a civil penalty of $224,240.00 for that conduct ($80/day of violations). This court reversed the judgment in part, holding that “the trial court abused its discretion when assessing the civil penalty against [Defendants] by not properly applying the Dayton Malleable factors.” Osborne II at ¶ 71, citing State ex rel. Brown v. Dayton Malleable, Inc., 1 Ohio St.3d 151, 438 N.E.2d 120 (1982). We remanded the matter to the trial court for further proceedings “solely related to the assessment of the civil penalty after considering the appropriate factors supported by the record.” Osborne II at ¶ 73.

{¶6} On remand, the trial court explicitly considered the Dayton Malleable factors and again imposed a civil penalty of $224,240.00 for the spoil piles and pollution. The trial court calculated the penalty as follows:

Based on the Dayton Malleable factors as discussed above, the court finds that a $100/day civil penalty would be appropriate for the actual harm and great risk of harm caused by Defendants’ placing of dredged material in and near the River, Defendants’ indifference, and the extraordinary enforcement costs incurred by the State, but that the amount should be reduced to $80/day due to the Eleventh District’s finding of lack of evidence of economic benefit gained by the violation. Accordingly, the court imposes a civil penalty of $80/day for the 2,301 days (7/13/07 to 11/1/13) that the Stockpiles remained along the River.

Applying the Dayton Malleable factors to the 1,004 days between when the Village removed all of the piles except for the Oliva Pile and the date of [the trial court’s] first order, the court finds that the risk of harm was reduced because there was less material that could fall into the River, and that the remaining factors are unchanged. The court further finds that this reduced risk of harm was due solely to the actions of the Village, and not to any action taken by Defendants, and therefore this court will only reduce the civil penalty by 50%.

Accordingly, the court imposes a civil penalty of $40/day for the 1,004 days (11/2/13 to 7/29/16) that the Oliva Pile remained along the River.

This court imposes a civil penalty of $224,240.00, consisting of $184,080.00 for the first period ($80/day * 2,301 days) and $40,160.00 ($40/day * 1,004 days) for the second period.

{¶7} From this decision, Appellants advance one assignment of error:

The trial court abused its discretion in assessing a civil penalty against Defendants in the amount of $224,240.

{¶8} “Assessing an environmental civil penalty lies within the trial court’s discretion. As long as the amount assessed is [equal to or] less than the statutory maximum, it is within the trial court’s discretion to fix that amount.” State ex rel. DeWine v. Deer Lake Mobile Park, Inc., 2015-Ohio-1060, 29 N.E.3d 35, ¶ 41 (11th Dist.), citing State ex rel. Ohio Atty. Gen. v. Shelly Holding Co., 135 Ohio St.3d 65, 2012-Ohio-5700, 984 N.E.2d 996, ¶ 23 and Dayton Malleable, 1 Ohio St.3d at 157-158. Thus, this court will not reverse the amount of the civil penalty imposed absent an abuse of the trial court’s discretion. An abuse of discretion occurs when a trial court fails to “‘exercise sound, reasonable, and legal decision-making.’” State v. Beechler, 2d Dist. Clark No. 09-CA-54, 2010-Ohio-1900, ¶ 62, quoting Black’s Law Dictionary 11 (8th Ed.2004); see also Dayton

Malleable at 157 (a trial court abuses its discretion by assessing a penalty that is “unreasonable, arbitrary, or unconscionable”).

{¶9} “The General Assembly intended to use economic sanctions to deter violations of R.C. Chapters 6109 and 6111, and thereby to promote the goal of clean water in the state of Ohio, when it provided for substantial monetary penalties.” Deer Lake at ¶ 42, citing Dayton Malleable at 157. Specifically, “[a]ny person who violates section 6111.07 of the Revised Code shall pay a civil penalty of not more than ten thousand dollars per day of violation.” R.C. 6111.09(A).

Free access — add to your briefcase to read the full text and ask questions with AI

State ex rel. Yost v. Osborne Co., Ltd., 2022 Ohio 2627 (Ohio Ct. App. 2022).

2022 Ohio 2627 (State ex rel. Yost v. Osborne Co., Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Detrex Chemical Industries, Inc.
393 F. Supp. 735 (N.D. Ohio, 1975)
State Ex Rel. Ohio Attorney General v. Shelly Holding Co.
2012 Ohio 5700 (Ohio Supreme Court, 2012)
State ex rel. Cordray v. U.S. Technology Corp.
2012 Ohio 855 (Ohio Court of Appeals, 2012)
State Ex Rel. Rogers v. Elbert
905 N.E.2d 235 (Ohio Court of Appeals, 2008)
State, Ex Rel. Brown v. Howard
444 N.E.2d 469 (Ohio Court of Appeals, 1981)
State ex rel. Cordray v. Evergreen Land Dev., Ltd.
2016 Ohio 7038 (Ohio Court of Appeals, 2016)
McConnell v. Bare Label Prods., Inc.
2017 Ohio 9325 (Ohio Court of Appeals, 2017)
State v. Beasley (Slip Opinion)
2018 Ohio 16 (Ohio Supreme Court, 2018)
State ex rel. DeWine v. Osborne Co., Ltd.
2018 Ohio 3109 (Ohio Court of Appeals, 2018)
In re Estate of Brunger
2018 Ohio 4474 (Ohio Court of Appeals, 2018)
State ex rel. Yost v. Osborne Co., Ltd.
2020 Ohio 3090 (Ohio Court of Appeals, 2020)
Martin v. Taylor
2021 Ohio 4614 (Ohio Court of Appeals, 2021)
Weglicki v. Rachitskiy
2022 Ohio 254 (Ohio Court of Appeals, 2022)
State ex rel. Brown v. Dayton Malleable, Inc.
438 N.E.2d 120 (Ohio Supreme Court, 1982)
Nolan v. Nolan
462 N.E.2d 410 (Ohio Supreme Court, 1984)
Disciplinary Counsel v. O'Neill
815 N.E.2d 286 (Ohio Supreme Court, 2004)