State ex rel. West Virginia Parkways Authority v. Barr

716 S.E.2d 689, 228 W. Va. 27, 2011 W. Va. LEXIS 11
CourtWest Virginia Supreme Court
DecidedMarch 1, 2011
DocketNo. 35757
StatusPublished
Cited by3 cases

This text of 716 S.E.2d 689 (State ex rel. West Virginia Parkways Authority v. Barr) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. West Virginia Parkways Authority v. Barr, 716 S.E.2d 689, 228 W. Va. 27, 2011 W. Va. LEXIS 11 (W. Va. 2011).

Opinion

WORKMAN, Chief Justice:

In this original jurisdiction action, the petitioners, the West Virginia Parkways Authority, Erica M. Mani, in her official capacity as Chairman Designee of the West Virginia Parkways Authority, and Cameron Lewis, in his official capacity as Vice Chairman of the West Virginia Parkways Authority (jointly “Petitioners”), sought a writ of mandamus against the respondents, the County Commission of Mason County, West Virginia, Miles S. Epling, in his official capacity as President of the County Commission of Ma[29]*29son County, and Robert C. Baird and Rick L. Handley, in their official capacities as Commissioners of the County Commission of Mason County (jointly “the Commission Respondents”), and Gregory C. Barr, in his Official Capacity as General Manager of the West Virginia Parkways Authority (“Respondent Barr”). Specifically, on November 18, 2010, the Petitioners filed a petition seeking to compel Respondent Ban’ to proceed with his statutory duties as General Manager of the Parkways Authority with regard to the “U.S. Route 35 parkway project.” Respondent Barr had refused to carry out his non-discretionary duties with regard to this project after the Commission Respondents voted to rescind their approval of the project.

On November 22, 2010, this Court issued a rule to show cause. Separate responses were received from the Commission Respondents and Respondent Barr.1 On December 7, 2010, the Court entered an order finding that the Commission Respondents had no legal authority to rescind their approval of the U.S. Route 35 parkway project. Accordingly, the Court granted the requested writ of mandamus and compelled Respondent Barr to proceed with his statutory duties with regard to that project. Because the Petitioners had established a need for a timely resolution of the issue, the Court issued a mandate in conjunction with its December 7, 2010, order, while indicating that an opinion would follow in due course.

This opinion, therefore, sets forth the Court’s basis for issuing the December 7, 2010, order and mandate.

I. FACTS

In 2010, the West Virginia Legislature enacted Senate Bill 427 (“SB 427”), which amended West Virginia Code §§ 17-16A-1 to -30 (2009 & Supp.2010) to enable the West Virginia Parkways Authority (“Parkways Authority”) to work with the West Virginia Department of Transportation, Division of Highways (“DOH”) in implementing new toll roads in the State. Pursuant to SB 427, the Parkways Authority is authorized to “construct, reconstruct, improve, maintain, repair and operate projects, at such locations within the state as may be determined by the Parkways Authority subject to the provisions of section thirty [§ 17-16A-30] of this article ...” Id. at § 17-16A-6(a)(5). Section thirty of Article 16A provides that, after the Parkways Authority has identified a new parkway project, the Governor must appoint two persons from each county where the parkway project is located to sit on a local advisory committee (“LAC”). Id. at § 17-16A-30. The LAC is tasked with studying the proposed project and submitting its written findings to the county commissions of the affected counties. Id. Those county commissions must then, by resolution, approve the proposed parkway project. Id. Specifically, the statute provides that “[p]rior to any final approval of a parkway project, the county commissions of the counties in which a parkway project is located shall by resolution approve the parkway project.” Id.

To fund such projects, the Parkways Authority is authorized “[t]o issue parkway revenue bonds ... payable solely from revenues, for the purpose of paying all or any part of the cost of any one or more parkway projects_” Id. at § 17-16A-6(a)(6). Furthermore, the Parkways Authority may “fix and revise, from time to time, tolls for transit over each parkway project constructed or improved by it_” Id. at § 17-16A-6(a)(8). The toll revenue is used to fund both “[t]he cost of maintaining, repairing and operating” the project as well as repaying the principal and interest on any parkways bonds issued to fund the project. Id. at § 17-16A-13(a)(1). “Such tolls ... shall not be subject to supervision or regulation by any other commission, board, bureau, department or agency of the State.” Id.

Before the Parkways Authority may “[fjix initial rates, tolls or charges along any portion of a parkway project” or approve any contracts that would require such tolls, the Authority must provide public notice and [30]*30hearing. Id. at § 17-16A-13a(a)(1). The notice, which must be published and circulated in all counties bordering the proposed parkway project, must disclose “any proposed contract, project or bond” as well as “the associated initial rate” of the toll. Id. at § 17-16A-13a(b). The Parkways Authority shall then conduct a public hearing in each affected county, not less than forty-five days from the publication of the notice. Id. at § 17-16A-13a(c).

At the conclusion of all required public hearings, the Parkways Authority shall render a final decision which shall include written findings of fact supporting its final decision on any proposed project which would result in or require initial rates, a rate increase, or prior to finally approving any proposed initial rate or toll or rate or toll increase, and such required findings and conclusions must reference and give due consideration to the public comments and additional evidence offered during the public hearings.

Id. at § 17-16A-13a(e).

Turning to the instant case, on July 8, 2010, the Parkways Authority adopted a resolution identifying and designating a new parkway project in Mason and Putnam counties. The goal of the project is to complete 14.6 miles of what is commonly referred to as the “new U.S. Route 35” to create a “modern four-lane highway” between Mason and Putnam counties. New U.S. Route 35 extends from the Ohio-West Virginia border in Mason County to Interstate 64 in Putnam County, and is intended to replace the older, two lane road known as “old U.S. Route 35.” To fund this project, the Parkways Authority proposes to toll 31.88 miles of the new U.S. Route 35. The construction of the remaining 14.6 miles of the road, as well as the toll plazas, would be paid for, in part, by issuing parkway revenue bonds. Those bonds would be repayable solely from revenues generated from the tolled portion of the road.

Following the Parkways Authority’s identification of U.S. Route 35 as a new parkway project, Governor Joe Manchin, III appointed two people each from Mason and Putnam counties to serve on the LAC. On September 23, 2010, the LAC issued a report recommending that “[n]ew U.S. Route 35 should be completed as a modern four-lane highway as soon as possible,” and finding that the only way to do so in a timely manner would be to make the 31.88-mile section a toll road. It further recommended that the Parkways Authority issue toll revenue bonds to help finance the construction of the final section of the road.

On September 28, 2010, following a presentation by the LAC of its findings, the County Commission of Putnam County unanimously issued a written resolution approving the proposed U.S. Route 35 parkway project. Two days later, on September 30, 2010, the LAC made a similar presentation to the County Commission of Mason County. Following the presentation, the Commission Respondents voted two-to-one to approve the U.S. Route 35 parkway project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnett v. Cummings
S.D. West Virginia, 2022
State ex rel. Public Service Commission v. Lackawanna Transport Co.
736 S.E.2d 741 (West Virginia Supreme Court, 2012)
STATE EX REL. PARKWAYS AUTHORITY v. Barr
716 S.E.2d 689 (West Virginia Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
716 S.E.2d 689, 228 W. Va. 27, 2011 W. Va. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-west-virginia-parkways-authority-v-barr-wva-2011.