State ex rel. Warehouse & Realty Co. v. City of Spokane

118 P. 321, 65 Wash. 385, 1911 Wash. LEXIS 935
CourtWashington Supreme Court
DecidedOctober 24, 1911
DocketNo. 9565
StatusPublished

This text of 118 P. 321 (State ex rel. Warehouse & Realty Co. v. City of Spokane) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Warehouse & Realty Co. v. City of Spokane, 118 P. 321, 65 Wash. 385, 1911 Wash. LEXIS 935 (Wash. 1911).

Opinion

Parker, J.

— This is a mandamus proceeding, wherein the relator seeks to compel the city engineer and the board of public works of' the city of Spokane to make an estimate in [386]*386the sum of $18,866.52 for work done by the relator upon a contract with the city in the construction of a street improvement. The defendants demurred to the affidavit for the writ, upon the ground of insufficiency of facts to entitle the relator to the relief prayed for, which demurrer was overruled. The defendants answered and a trial followed, resulting in findings and judgment in favor of the relator. The defendants have appealed.

We need notice only certain facts stated in the court’s findings, to which no exceptions were taken, and which may therefore be considered as no longer in dispute. These facts are also set forth in the affidavit for the writ, and therefore will be sufficient for our consideration of the court’s ruling upon the demurrer. They are, in substance, as follows: On August 24, 1908, the relator entered into a contract with the city to construct a viaduct and fill upon Sprague avenue according to plans and specifications prepared therefor. By the terms of the contract, it was agreed, among other things, as follows:

“It is further understood and agreed, between the parties hereto, that all of said work shall be performed and all of said material shall be furnished under the supervision, direction and control and to the complete satisfaction of the board of public works, and its representative, the city engineer, who is acknowledged to be the representative of said board of public works, . . .
“In consideration of the performance of the terms and conditions of this contract by the party of the. second part, said party of the first part agrees to pay to said party of the second part the sum of eighty-six thousand nine hundred ($86,900) dollars, the same to be paid upon estimates made in the following manner: On the first of the month, sixty (60) days after work has been started, and each sixty (60) days thereafter, the party .of the second part .shall be allowed an estimate of eighty (80%) per cent of the work completed at such times, such estimate to be made by the city engineer, it being understood, however, that twenty (20%) per cent of the total contract price shall be withheld until the work is finished and accepted, and it is further understood and agreed [387]*387that the first twenty thousand ($20,000) dollars, paid to said party of the second part in accordance with the terms hereof shall be paid in cash or by warrants upon the general fund, and the payment of the balance of said contract price, to wit, the sum of sixty-six thousand nine hundred ($66,900) dollars shall be paid in such manner that sixteen thousand seven hundred and twenty-five ($16,725) dollars shall be due in one year from the date of the issuance of the warrants covering said named sum; sixteen thousand seven hundred and twenty-five ($16,725) dollars to be paid in two years from the date of the issuance of the warrants covering said named sum; sixteen thousand seven hundred twenty-five ($16,725) dollars to be paid in three years from the date of the issuance of the warrants covering said named sum; and sixteen thousand seven hundred twenty-five ($16,725) dollars to be paid in four years from the date of the issuance of the warrants covering said named sum. All warrants evidencing the payment of said sixty-six thousand nine hundred ($66,-900) dollars shall bear interest at the rate of six (6%) per cent per annum . . .”

Thereafter the relator entered upon the construction of the improvement, in pursuance of the plans and specifications as interpreted by the city engineer and the board of public works, until February 5, 1909, when the specifications were modified in certain particulars by the defendants with the consent of the relator, but without materially altering the character or the nature of the work to be performed. Thereafter the relator continued the construction in accordance with the plans and specifications as modified and as interpreted by the city engineer and the board of public works, and has completed a large part of the work. All of this work was performed under the direction and supervision of the city engineer and the board of public works, and to their entire satisfaction, and the same was from time to time, as- it was constructed and done, accepted by the city engineer and the board of public works. Estimates were made from time to time, as provided by the contract, upon completed portions of the work, and as the estimates were made, there was paid to the relator in cash and warrants eighty per cent of the amount [388]*388thereof, aggregating the sum of $35,575.75. Since August 7, 1909, the date of the last estimate, the city engineer and board of public works have wrongfully, capriciously, and without reason therefor, failed and refused to make or allow to the relator any further or other estimates. The relator became entitled to have estimates made on the 1st day of October and December, 1909, and the first day of February, 1910, for work theretofore performed under the contract. Prior to February 1, 1910, the relator completed work under the terms of the contract of the value of $71,052.84, and is now entitled to an estimate on such work of eighty per cent of that sum less estimates heretofore allowed and paid, amounting to the sum of $18,866.52, being the amount claimed to be due the relator in its complaint. The findings of the court as to acceptance of the work by the city engineer and board of public works, the substance of which we have above stated, has reference to all of this work.

The first and principal contention made by counsel for the city is that the relator cannot invoke the remedy of mandamus to litigate the questions presented by his affidavit for the writ and the appellant’s answer thereto. It seems to us that the previous holding of this court as to the nature of mandamus proceedings under our law show that this contention cannot be successfully maintained. We are not able to distinguish the case of State ex rel. Brown v. McQuade, 36 Wash. 579, 79 Pac. 207, from this case, in so far as the principle involved is concerned. In that case mandamus was held to be a proper remedy to compel a school board to issue a warrant to a teacher in payment of a balance due on his salary, payable by warrants under his contract of employment, notwithstanding there was involved an issue of fact as to amount due upon the contract of employment. The contention there made was that mandamus was not a proceeding in which disputed claims could be litigated. The right of the teacher to a warrant in that case, like the right of this relator to an estimate in this case, was simply a right to [389]*389have evidenced in writing, as provided by the terms of the contract, the amount due thereunder. At page 582 of the decision in that case, the court said:

“As his contract with the district provided that he was to be paid by a warrant drawn by the school board on the county treasurer, in no other way was he entitled to receive payment for his services, and unless he can force the board to act, it is difficult to see how he is going to get paid at all. An action at law against the district will not furnish him relief. The most he could obtain by such an action would be a judgment against the district, which would entitle him to a warrant drawn by the directors on the county treasurer. He could not obtain a judgment which could be collected by execution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Brown v. McQuade
79 P. 207 (Washington Supreme Court, 1905)
State ex rel. Gillette v. Clausen
87 P. 498 (Washington Supreme Court, 1906)
State ex rel. Maltbie v. Will
103 P. 479 (Washington Supreme Court, 1909)
Smith v. City of Centralia
104 P. 797 (Washington Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
118 P. 321, 65 Wash. 385, 1911 Wash. LEXIS 935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-warehouse-realty-co-v-city-of-spokane-wash-1911.