State ex rel. Texas Grading Co. v. Buie

80 So. 191, 144 La. 39, 1918 La. LEXIS 1689
CourtSupreme Court of Louisiana
DecidedJune 29, 1918
DocketNo. 23032
StatusPublished
Cited by6 cases

This text of 80 So. 191 (State ex rel. Texas Grading Co. v. Buie) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Texas Grading Co. v. Buie, 80 So. 191, 144 La. 39, 1918 La. LEXIS 1689 (La. 1918).

Opinion

LECHE, J.

Relator prays for a writ of mandamus, directing the state highway engineer to issue in its favor Ms warrant, and directing the president of the state board of engineers to approve same, upon the state [41]*41treasurer of Louisiana, for tlie sum of $9,-306.48 to be paid out of the fund created by Act No. 49 of 1910. A rule to show cause was issued, and, after trial and hearing, the district court rejected relator’s demand, and from that ruling the present appeal was taken.

Relator, as the successful bidder, was awarded a contract to build about 13% miles of highway in the parish of Bossier. The work was undertaken and completed according to the written contract and specifications, in consideration of a sum exceeding $50,000, all of which has been paid to relator, except $7,245.57. Defendants refuse to comply with relator’s demand for the reason that there were filed with the recorder of mortgages for the parish of Bossier claims for materials, supplies used, and labor performed in the construction of said highway, amounting to the sum thus withheld by them, and which would otherwise still be due to relator under its contract. It is admitted by the parties that the work was properly performed and that the balance of the contract price remaining unpaid is $7,245'.57.

Two defenses were pleaded to relator’s action. The first one is directed at the mode of proceeding, and the other is founded on the allegation that, though the work was properly completed, the stipulations in the contract have not entirely been complied with, in this, that there remains unfulfilled a condition in the bond furnished by relator to the effect that “all sums due upon material and supplies used and for wages earned by laborers and workmen employed upon the work to be done” shall be paid by relator.

[1] The writ of “mandamus” is an order issued in the name of the state by a tribunal of competent jurisdiction and may be addressed to a public officer directing him to perform some act or some duty imposed upon him by law. C. P. arts. 829-834. The duty must be one imposed by law and must not merely result from a conventional obligation. State ex rel. New Orleans v. Carrolton R. R., 37 La. Ann. 589. While in the case at bar the duty sought to be enforced is contained in a contract, it arises out of the provisions of Act No. 49, p. 74, of 1910. Respondents would, without the legislative sanction contained in said act, have been powerless to enter into ■ any contract in the premises with relator or any one else. State ex rel. McEnery v. Nicholls, 42 La. Ann. 222, 7 South. 738. We are then of the opinion, as the written contract is merely a recognition on the part of respondents of a duty which in point of fact is imposed, not by the contract, but by the law which authorized them to enter into the contract, that the present proceeding by mandamus is not amenable to the objection that it attempts to enforce the stipulations of a conventional obligation.

[2, 3] It is also well settled by our jurisprudence that the duty must not only be imposed by law, but that it must be ministerial in its nature and not depending upon the exercise of legal discretion. Courts have no right to ignore or control the discretion which the law has vested in public officials, except where such discretion has been grossly abused. It is, however, within the province of the courts to decide whether an act sought to be enforced is or is not ministerial. State ex rel. Ecuyer v. Burke, 33 La. Ann. 969. The decision of that question is involved in the second defense of respondents.

It appears from the record that the contract, entered into on June 13, 1916, contains the following stipulation:

“Final payment and cancellation of bond will not be made until the contractor (relator herein) and his sureties have satisfactorily adjusted all claims and liens recorded in the office of the recorder of mortgages in the parish of Bossier against the contractor for all sums due upon materials used and for wages, earned by laborers and workmen employed in connection with the construction of this work.”

[43]*43Tlie bond furnished by the relator also contains the condition that the relator “shall pay all sums due on materials and supplies used and for wages earned by laborers and workmen employed on the work to be done, etc.”

Relator contends that there are no claims of any kind pending against it for the work performed under the contract, but that the said claims, alleged to be of record in the parish of Bossier, are against Bishop & By-bee for materials, supplies, and labor furnished the said Bishop & Bybee; that said Bishop & Bybee were to the knowledge of respondents, and, with their consent, subcontractors who performed part of the work on said highway; that it (the relator) has paid the said Bishop & Bybee, and therefore cannot be held in law, or under the contract, bound for the payment of said claims.

There are several letters in the record, written by Mr. Cappel, bridge and office engineer, and others written to him, in which allusions are made to subcontractors. This correspondence, however, was entirely between the relator and the engineer in charge of the construction of the highway and in no manner releases the relator from the execution of any of the stipulations of the contract. On, the contrary, relator in a letter written November 11, 1916, expressly admits that it alone is responsible to the respondents for the work which it undertook under the contract of June 13, 1916. We find nothing in the record to justify relator’s contention that any part of the contract was sublet with the consent of respondents; but, on the contrary, we find a stipulation in the contract to the effect that “this contract shall not be assigned, nor shall any portion of the work thereunder be subcontracted without written authority of the state highway engineer,” and it is not pretended that there is any written authority from the state highway engineer to that effect. Bishop & Bybee must therefore be considered, so far as respondents are concerned, only as employes and agents of relator and not as its subcontractors.

[4] Conceding, however, that the claims against Bishop & Bybee, recorded in the parish of Bossier, for work performed and for materials used in the construction of the highway, are such claims as are contemplated in the stipulation of the contract and the condition of the bond, it must first be ascertained whether respondents had the authority, under the law, to bind the relator, as contractor, by such a stipulation and such a condition. That is the pivotal question in the case.

The Act No. 49 of 1910, which is the mandate from the state of Louisiana under which respondents are carrying out their public trust, is the only source from which the authority they may exercise in the construction of public highways is derived. That act contains no provision, either to safeguard the claims of laborers and furnishers of material, or to authorize the state highway department to require from contractors any guaranty for the payment of such claims, and there is no law granting any lien or privilege on the public highways to secure the same.

In the case of State v. C. S. Jackson & Co., 137 La. 934, 69 South.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Vullo v. Plaquemines Parish Police Jury
115 So. 2d 70 (Louisiana Court of Appeal, 1959)
State ex rel. Gill v. Soule
61 So. 2d 605 (Louisiana Court of Appeal, 1952)
Montegut v. Louisiana State Board of Dentistry
55 So. 2d 58 (Louisiana Court of Appeal, 1951)
Charbonnet v. Board of Architectural Examiners
17 So. 2d 261 (Supreme Court of Louisiana, 1944)
Gray v. City of Santa Fe
89 F.2d 406 (Tenth Circuit, 1937)
State Ex Rel. Martin v. Bailey
123 So. 125 (Supreme Court of Louisiana, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
80 So. 191, 144 La. 39, 1918 La. LEXIS 1689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-texas-grading-co-v-buie-la-1918.