State Ex Rel. State Highway Commission v. Shain

62 S.W.2d 711, 333 Mo. 235, 1933 Mo. LEXIS 615
CourtSupreme Court of Missouri
DecidedJuly 20, 1933
StatusPublished
Cited by5 cases

This text of 62 S.W.2d 711 (State Ex Rel. State Highway Commission v. Shain) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. State Highway Commission v. Shain, 62 S.W.2d 711, 333 Mo. 235, 1933 Mo. LEXIS 615 (Mo. 1933).

Opinion

GANTT, C. J.

Original proceeding in mandamus. Relator seeks to compel the judges of the Kansas City Court of Appeals to set aside its order dismissing the appeal in the case of Euler v. State Highway Commission and to reinstate said case on its docket.

The case was before said court at the March Term, 1931. At that time the judgment was affirmed because of certain defects in the abstract. However, appellant under Rule 15 of said court sought to correct said defects by filing a supplemental abstract. The Court of Appeals ruled that the correction was not authorized under the rule. In an original proceeding in mandamus in this court it was ruled to the contrary, and the Court of Appeals was commanded to proceed in due course to a disposition of the case. [State ex rel. State Highway Commission v. Trimble, 329 Mo. 987, 47 S. W. (2d) 779.]

' The State Highway Commission (appellant) then filed a new abstract and brief in said court. Thereupon respondent Euler filed a motion to dismiss the appeal on the ground that the abstract did not comply 'with Section 1028, Revised Statutes 1929, and Rule 15 of said court.

He also filed a motion to dismiss the appeal on the ground that the statement of the case made by appellant (State Highway Com *236 mission) did not comply with Section 1060, Revised Statutes 1929, and Rule 16 of said court.

The section requires a clear and concise statement of the ease. The rule also requires a clear and concise statement that the court may be informed of the material facts from the statement without being compelled to glean them from the abstract of the record.

The motions were sustained. In doing so the court said:

“We see no escape from the necessity of dismissing the appeal for either one or both of the aforesaid violations of the rules in relation to the presentation of appeals. It is not a matter within our discretion. It is our duty to enforce the rules made to further the purpose and efficient dispatch of business.” [Euler v. State Highway Comm., 55 S. W. (2d) 719, l. c. 722.]

The circumstances considered, the statement should speak for itself. It follows:

“In 1924 Ernest Ii. Euler, a contractor from Kansas came into Missouri. The occasion for his appearance in Missouri was the letting of two contracts for the construction of Sections 5 and 6 of Missouri State Highway No. 6 in DeKalb County, Missouri.
“In contemplation of being awarded the work, the Respondent moved a subcontractor on the ground during the latter part of August, 1924. On the 3rd day of September, 1924, the Appellant sent out to the Respondent the regular ‘Notice to Proceed,’ which is the contractor’s. authorization to begin work.
“Under the terms of these two contracts signed by Ernest H. Euler and the State Highway Commission of Missouri, no part of the work was to be finally approved and accepted until the whole thing covered in the contract was finished. By the terms of the contract for the construction of Section 5 and also by the terms of the other contract for the construction of Section 6, Mr. Euler had bound himself to complete the work by the 31st day of December, 1924.
“It soon became apparent that the construction of these two sections could not be finished by the Respondent by the 31st day of December, 1924, the completion date in the two contracts. Therefore, the State Highway Commission, at the request of Mr. Euler, granted an extension of time and set the completion date for the 18th day of February, 1925. In this connection, we might say that no further extension of time was ever asked by Mr. Euler or granted by the Commission.
“Section 5 was completed and accepted on the 26th day of September, 1926, exactly one year, one month and eight days after the extended completion date of the contract. And Section 6 was completed and accepted on the 9th day of August, 1926, exactly one year, five months and twenty-two days after the extended completion date of that contract.
*237 “Under the provisions of Sections 4-37, 3-8 and 3-39 of these two contracts, the State Highway Commission was authorized to hold back ten per cent of the contract price (the rest being paid over to the contractor as parcels of a mile or so were completed and taken over for maintenance but not finally accepted); and from this retent the Commission was authorized to deduct any liquidated damages provided for in the contract and arising from a breach of the contract. It was provided in Section 4-35 of the contract that if the contractor should not complete the work by the completion date, liquidated damages upon both contracts should be assessed against him in the amount of $25 for each day’s delay.
“Pursuant to this provision in the contract, the Commission assessed against the contractor and retained from his retent upon the contract for Section 5 (which he completed one year, one month and eight days late) thirty-five days’ delay at $25 per day. And upon Section 6 (which the contractor completed one year, five months and twenty-two days late) the Commission assessed liquidated damages for only fifty-seven days at $25 per day.
“It should be pointed out here that this assessment of liquidated damages was exercised by the Commission only to the extent necessary to compensate it for actual loss due to the contractor’s delay. In other words, although the contractor was 403 days late in completing the contract on Section 5, the Appellant assessed liquidated damages for only thirty-five days. And that although the contractor was 537 days late in the completion of the contract on Section 6, the Appellant assessed liquidated damages for only fifty-seven days.
“It should be pointed out that.the two contracts signed by Mr. Euler were the regular State construction contracts which contain provisions to the effect that the Appellant’s Chief Engineer shall be constituted arbiter of any dispute arising between the contractor and the State as to the interpretation of the contract, the order and manner of prosecuting the work, and the acceptability of the work when completed. These provisions are found in Section 4-29 of the contract. In fact Section 4-38 provides that payments shall only be made upon estimates prepared and approved by the Appellant’s Chief Engineer as arbiter.
“ Among other provisions, this contract provided that all materials encountered in the roadbed should be classified under three types: (1) ‘Earth Excavation,’ for which the price was 33 cents per cubic yard; (2) ‘Loose Rock Excavation,’ for which the price was 85 cents per cubic yard; and (3) ‘Solid Rock Excavation,’ for which the price was $1.75 per cubic yard.
“Section 77 of the contract provided for the application of the ‘plow test’, for the purpose of determining into which of the three classifications any material encountered should be put. That is to say, all material which could be ‘satisfactorily loosened with a road *238 plow and four powerful horses’ should be classified as earth excavation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Kociolek
129 A.2d 417 (Supreme Court of New Jersey, 1957)
Produce Exchange Bank of Kansas City v. Winn
133 S.W.2d 419 (Supreme Court of Missouri, 1939)
Myers v. Union Electric Light & Power Co.
125 S.W.2d 950 (Missouri Court of Appeals, 1939)
Evans Ex Rel. Evans v. Hilliard
112 S.W.2d 886 (Missouri Court of Appeals, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
62 S.W.2d 711, 333 Mo. 235, 1933 Mo. LEXIS 615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-state-highway-commission-v-shain-mo-1933.