STATE EX REL. STATE ELECTRIC SUPPLY CO. v. McBride

444 P.2d 978, 79 N.M. 467
CourtNew Mexico Supreme Court
DecidedSeptember 9, 1968
Docket8485
StatusPublished

This text of 444 P.2d 978 (STATE EX REL. STATE ELECTRIC SUPPLY CO. v. McBride) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STATE EX REL. STATE ELECTRIC SUPPLY CO. v. McBride, 444 P.2d 978, 79 N.M. 467 (N.M. 1968).

Opinion

OPINION

CHAVEZ, Chief Justice.

Plaintiff-appellant State Electric Supply Company, Inc., a corporation, hereinafter referred to as “Electric,” brought suit on a general contractor’s payment bond under § 6-6-12, N.M.S.A., 1953 Comp., for use in the construction of an annex to the science building of the Farmington High School. The case was tried to the court sitting without a jury, who denied use plaintiff Electric recovery on the ground that it had failed to comply with the notice requirement specified in § 6-6-12, supra, in that the written notice was not timely mailed. From said judgment Electric appeals.

Electric’s amended complaint alleged the furnishing of certain electrical materials and supplies to a subcontractor defendantappellee H. R. McBride d/b/a PI. R. McBride Construction Company, hereinafter referred to as “McBride,” to be used in the construction of said public building for which it had not received payment. After alleging a public contract between the prime contractor and the Farmington School Board for the construction of said building, and the furnishing of a payment bond pursuant to § 6-6-11, N.M.S.A., 1953 Comp., Electric sought recovery on said payment bond. McBride answered, denying generally said allegations and alleged that Electric failed to comply with the notice and limitation provision of § 6-6-12, supra, and therefore was barred from recovery therein.

The trial court denied recovery to Electric on the ground that it failed to comply with the notice requirement specified in § 6-6-12, supra, in that the written notice was not mailed to the prime contractor within ninety days from the date on which the last material was furnished for which claim was made.

Of the eighteen findings of fact made by the trial court, appellant Electric appears to challenge the following findings:

“7. The voltage requirement of the new system was not specified in the plans and specifications.
“12. No charge was made by the use plaintiff for the 12 volt horn, nor was it listed as a part of the materials for which claim was made.
“13. The use plaintiff furnished the last of the material for which claim tvas made on or before December 7, 1964.
“17. The written notice mention'ed in Finding No. 15 was mailed to McBride more than 90 days from the date on which the last material was furnished for which claim was made.”

The pertinent findings of fact not chai-' lenged by Electric are as follows:

“1. On May 12, 1964, defendant McBride entered into a contract with the Board of Education of the town of Farmington, New Mexico, to construct an annex to the science building of the Farming-ton High School in accordance with plans and specifications provided by the Board of Education.
“2. On or about the 12th day of May, 1964, and pursuant to § 6-6-11, N.M.S.A., 1953, McBride furnished the Board of Education a bond executed by him as principal, and defendant, United States Fidelity and Guaranty Company, a corporation, as surety.
“3. On or about the 15th day of May, 1964, McBride entered into a subcontract with Fulkerson by 'the terms of which Fulkerson agreed to perform all labor and furnish all material necessary to complete the electrical work required to be performed under the contract between McBride and the Board of Education.
“4. The use plaintiff, State Electric Supply Company, Inc., at the instance and request of Fulkerson furnished substantially all materials used in the prosecution of the sub-contract.
“5. The sub-contract required, among other things, that Fulkerson furnish and install a fire' alarm system consisting of an ' alarm horn, fire alarm stations, and the alarm system was to be connected with one located in the old part of the science building.
“6. The fire alarm system located in the old part of the building and to which the system required under the sub-contract was to be connected, was a 12 volt system.
“8. Fulkerson ordered a fire alarm horn and two fire stations from the use plaintiff but did not specify the voltage or other characteristics.
“9. The use plaintiff caused a 24 volt fire alarm horn and two fire alarm stations to be delivered to Fulkerson on November 25, 1964, which horn and stations were accepted by Fulkerson and installed in the building before December 16, 1964.
“10. The fire alarm system would not operate with the use of a 24 volt horn.
“11. After Fulkerson had learned that the fire alarm system required a 12 volt horn to be operative he obtained such horn on February 25, 1965, through the use plaintiff and in the early part of April 1965, installed it in the system.
“14. The price agreed upon between Fulkerson and use plaintiff for the materials was the sum of $8,160.-22, of which $400.33 was paid by Fulkerson, leaving a balance of $7,759.89 unpaid and owing, which Fulkerson has failed to pay although demand was made upon him.
“15. On March 26, 1965, the use plaintiff gave written notice to McBride that it claimed $7,759.89 for electrical supplies furnished to the sub-contractor, Fulkerson, for use in the prosecution of the work required by the contract that materials were furnished between June 30, 1964, and February 22, 1965. The notice was served by mailing the same to McBride. “18. Use plaintiff had no contractual relationship express or implied with McBride.”

Electric claims error by reason of the trial court’s refusal to adopt its requested finding of fact which reads as follows :

“5. The first of said materials and supplies was furnished to Fulkerson by the plaintiff on June 30, 1964 and the last on February 25, 1965.”

Electric also challenges' the following conclusions of law made by the trial court:

“3. The use plaintiff had an enforceable claim against Fulkerson for all material furnished and for which claim was made on or before December 7, 1964.
“4. Use plaintiff failed to comply with the notice requirement specified in § 6-6-12, N.M.S.A., 1953, in that notice was not timely mailed.
“5. Use plaintiff is not entitled to judgment in this cause and the complaint should be dismissed.”

By letter dated March 26, 1965, Electric gave written notice to McBride, claiming a balance due of $7,759.89 for materials furnished to Fulkerson, and which were used in the construction of the Farmington High School building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
444 P.2d 978, 79 N.M. 467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-state-electric-supply-co-v-mcbride-nm-1968.