State Ex Rel. Reynolds v. Rio Rancho Estates, Inc.

624 P.2d 502, 95 N.M. 560
CourtNew Mexico Supreme Court
DecidedFebruary 3, 1981
Docket12882
StatusPublished
Cited by20 cases

This text of 624 P.2d 502 (State Ex Rel. Reynolds v. Rio Rancho Estates, Inc.) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Reynolds v. Rio Rancho Estates, Inc., 624 P.2d 502, 95 N.M. 560 (N.M. 1981).

Opinion

OPINION

FEDERICI, Justice.

Appellee undertook a drilling program in 1971 just outside the boundaries of the Rio Grande Underground Water Basin. Of six holes drilled, only the well at issue in this case was logged, reamed and cased. A short pump test of the well was conducted and the hole was capped some time prior to October 1971. The outside diameter of the casing was seven inches and the depth of the well was 1,500 feet.

On September 7,1973,- the State Engineer extended the Rio Grande Basin to include the land on which the capped well was situated.

On July 2, 1975, appellee filed a declaration of a pre-basin water right and applied for a permit to repair the well. The State Engineer approved the permit subject to the condition that the well would not be deepened or enlarged. Because the well could not be repaired for a number of reasons, appellee applied on December 5, 1975 for a permit to change the location of the well. This application requested an 18-inch diameter well to replace the original 7-inch well. The State Engineer approved the application subject to certain conditions, including limitations that the maximum amount of water diverted annually would not exceed 2419.51 acre feet, that the diameter of the casing not exceed seven inches, and that the depth not exceed 1,500 feet.

Appellee notified the State Engineer that it was aggrieved by these latter two conditions and a hearing was held pursuant to Section 72-2-16, N.M.S.A. 1978. The recommendation of the hearing officer, as adopted by the State Engineer, imposed the size limitations. On de novo appeal'^' the district court found that appellee, in accordance with its intention to appropriate water, was entitled to continue to construct the well pursuant to the doctrine of relation back under State v. Mendenhall, 68 N.M. 467, 362 P.2d 998 (1961). This right included the right to change the location of the well as a part of the normal course of well drilling. The court held that the size limitations could not be imposed. We affirm the trial court.

We address the following issues:

1. Whether appellee’s failure to object to size limitations imposed by the State Engineer on the permit to repair the well operates to bar litigation of the size limitations now;

2. Whether the Mendenhall doctrine applies in this case, giving appellee an inchoate water right, not subject to limitation by the State Engineer;

3. Whether the trial court exercised independent discretion in making its findings of fact and conclusions of law; and

4. Whether the trial court committed reversible error in admitting certain documents concerning appellee’s diligence in development of the well.

I.

When appellee applied for the permit to repair the well, it was required to describe the purpose of the acquired right, and the type of repair contemplated. It stated the “[rjight was acquired for subdivision, municipal, recreational and related purposes.” Appellee indicated that the only type of repair contemplated was cleaning out the well to its original depth. The State Engineer approved this application, subject to the conditions that “[t]he well shall not be deepened or the diameter enlarged.”

Section 72-2-16 provides that “any person aggrieved by the decision, act or refusal to act [by the State Engineer], is entitled to a hearing, if a request for a hearing is made in writing within thirty days.” Appellee did not request a hearing on that decision. The State Engineer asserts- that the doctrine of administrative res judicata bars litigation of the issue of the depth of the well and the diameter of the pipe. It is not disputed that the decision of the State Engineer in granting the permit had the force and effect of a judicial judgment.- The seminal case on this question in New Mexico is City of Socorro v. Cook, 24 N.M. 202, 173 P. 682 (1918). However, for the prior judgment to apply to the case here it must have addressed “questions, points or matters of fact in issue ... which were essential to a decision, and which were decided in support of the judgment.” (Emphasis added.) Paulos v. Janetakos, 46 N.M. 390, 393, 129 P.2d 636, 638 (1942).

In its application for repair, appellee did not request a change in the amount of water it could use, nor was a statement of limitation of the right required for the State Engineer to grant approval. A party should not be required to litigate every incidental matter which might come up in the course of a proceeding before the State Engineer or forever lose its claim. Since the depth of appellee’s well and the diameter of the pipe and .the amount of water were not in issue and not essential to the prior decision, the State Engineer’s determination did not bar the subsequent litigation of those issues here.

II.

In State v. Mendenhall, supra, the issue before the Court was:

Does a landowner who lawfully initiates the development of an underground water right and carries the same to completion with reasonable diligence acquire a water right with a priority date as of the beginning of his work, notwithstanding the fact that the lands involved were put into a declared artesian basin before work was completed and the water put to beneficial use on the ground?

Id. 68 N.M. at 468, 362 P.2d at 999.

In that case, Mendenhall’s predecessors commenced drilling for the development of water for irrigation until they believed an adequate supply was reached. Upon testing, they determined the supply was inadequate. Five months later, they entered into an oral contract for further drilling. The contract was reduced to writing two months later. The renewed drilling began almost simultaneously with a declaration by the State Engineer that the area encompassing the drilling operation was within an underground water basin. The drilling efforts were successful in providing sufficient water for Mendenhall’s desired use, and irrigation began the same year. The State Engineer claimed that Mendenhall did not have a valid water right because it was not applied to beneficial use prior to declaration of the basin. However, this Court ruled that “the right to continue to develop underground water under the general law was in no way altered pending a declaration.” Id. at 472, 362 P.2d at 1002.

Section 72-12-4, N.M.S.A. 1978 provides: “Existing water rights based upon application to beneficial use are hereby recognized. Nothing herein contained is intended to impair the same or to disturb the priorities thereof.” In Mendenhall, this Court interpreted the statute as follows:

[W]hen the legislature used the term “based upon” it had in mind the entire procedure necessary to accomplish a beneficial use of water. It is ofttimes a long drawn out enterprise that must be accomplished between initiation of a right and the final act of irrigating a quantity of land. Months and years may reasonably elapse. A four year span is recognized under certain circumstances in [former statutory law].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Office of the State Eng'r v. Gray
2021 NMCA 066 (New Mexico Court of Appeals, 2021)
Curry v. Pondera County Canal & Reservoir Co.
2016 MT 77 (Montana Supreme Court, 2016)
Eldorado Utilities, Inc. v. State Ex Rel. D'Antonio
2005 NMCA 041 (New Mexico Court of Appeals, 2005)
Herrington v. State Ex Rel. Office of the State Engineer
2004 NMCA 062 (New Mexico Court of Appeals, 2004)
Department of Ecology v. Theodoratus
135 Wash. 2d 582 (Washington Supreme Court, 1998)
State, Dept. of Ecology v. Theodoratus
957 P.2d 1241 (Washington Supreme Court, 1998)
State Ex Rel. Martinez v. McDermett
901 P.2d 745 (New Mexico Court of Appeals, 1995)
State v. Young
875 P.2d 1119 (New Mexico Court of Appeals, 1994)
Amoco Production Co. v. Heimann
904 F.2d 1405 (Tenth Circuit, 1990)
Amoco Production Company v. Heimann
904 F.2d 1405 (Tenth Circuit, 1990)
Atty. Gen. of State v. Nm Pub. Ser. Com'n
685 P.2d 957 (New Mexico Supreme Court, 1984)
Attorney General v. New Mexico Public Service Commission
685 P.2d 957 (New Mexico Supreme Court, 1984)
Roberts v. Sparks
655 P.2d 539 (New Mexico Court of Appeals, 1982)
Reynolds v. City of Roswell
654 P.2d 537 (New Mexico Supreme Court, 1982)
Jicarilla Apache Tribe v. United States
657 F.2d 1126 (Tenth Circuit, 1981)
T.W.I.W., Inc. v. Rhudy
630 P.2d 753 (New Mexico Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
624 P.2d 502, 95 N.M. 560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-reynolds-v-rio-rancho-estates-inc-nm-1981.