State Ex Rel. Petro v. Rsv, Inc., Unpublished Decision (1-13-2006)

2006 Ohio 376
CourtOhio Court of Appeals
DecidedJanuary 13, 2006
DocketNo. 03-JE-7.
StatusUnpublished
Cited by2 cases

This text of 2006 Ohio 376 (State Ex Rel. Petro v. Rsv, Inc., Unpublished Decision (1-13-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Petro v. Rsv, Inc., Unpublished Decision (1-13-2006), 2006 Ohio 376 (Ohio Ct. App. 2006).

Opinion

OPINION
{¶ 1} Defendants-appellants/cross-appellees, RSV, Inc., et al., appeal a decision of the Jefferson County Common Pleas Court finding them in contempt and in violation of Ohio's environmental laws. Plaintiff-appellee/cross-appellant, State of Ohio, ex rel. Jim Petro, Attorney General of Ohio, appeals the same decision arguing that the trial court failed to impose adequate injunctive relief.

{¶ 2} Defendant-appellant/cross-appellee, RSV, Inc. (RSV), operates a construction and demolition debris landfill facility known as the Pine Hollow Construction Demolition Debris Facility (Pine Hollow). RSV is controlled exclusively by defendant-appellant/cross-appellee, Robert S. Vukelic (Vukelic). Vukelic, through RSV, purchased the facility in 1994 and commenced operations. The facility is not a solid waste landfill and is only authorized to accept construction and demolition debris materials. Construction and demolition debris materials are "those materials resulting from the alteration, construction, destruction, rehabilitation, or repair of any manmade physical structure, including, without limitation, houses, buildings, industrial or commercial facilities, or roadways." R.C.3714.01(C). Examples of such materials include bricks, wood, shingles, drywall, etc., which are generated as the result of construction or demolition activities.

{¶ 3} In 1990, the Ohio General Assembly passed R.C. Chapter 3714, comprehensive legislation designed to regulate construction and demolition debris facilities. On September 30, 1996, the Ohio Environmental Protection Agency adopted construction and demolition debris (CDD) regulations. Ohio Adm. Code 3745-400-01 et seq. The regulations require the owners and operators of construction and demolition debris facilities to obtain operational licenses. Because Pine Hollow was an "existing facility" under the regulations at the time of their adoption, the facility was allowed to continue operating without a license until the Director of the OEPA denied the license and RSV exhausted its administrative appeals. RSV applied for a license each year from 1997 through 2001, but no license was ever issued due to its noncompliance with the regulations. However, RSV continued to operate the facility while it appealed the OEPA's proposed denial of the licenses.

{¶ 4} Nearly from the time RSV began operations at the facility, it experienced numerous and repeated regulatory compliance problems. This appeal focuses only on two of those problems. First, RSV unlawfully accepted solid waste into its CDD landfill from November 1996 until September 2001. The second problem at the facility concerned a stream known as Rush Run. Waste deposited at the site blocked its flow. In early 1997, after repeatedly being cited for failing to divert Rush Run around the facility in accordance with CDD regulations and the Surface Water rules, RSV routed Rush Run through the facility with a culvert pipe which created a number of compliance issues. RSV was required to obtain permits before changing the course of Rush Run. Also, problems developed with the pipe and water did not flow through it properly causing water to divert into other areas of the landfill.

{¶ 5} On March 23, 2001, the plaintiff-appellee/cross-appellant, State of Ohio, ex rel. Jim Petro, Attorney General of Ohio (the State), on behalf of the OEPA, filed an injunctive action against RSV and Vukelic. The complaint set forth 24 counts alleging numerous violations of the construction and demolition debris regulations. The complaint also sought monetary fines and corrective action to bring the facility into compliance with the regulations.

{¶ 6} The parties attempted to resolve disputed issues and reached an agreement embodied in a consent order filed April 10, 2001.1 RSV was ordered to abate surface water violations at the site because of concerns about the flow of a stream into the landfill. Unsatisfied with RSV's efforts to comply with the order, the State filed charges in contempt in February 2002.

{¶ 7} On April 10, 2002, the trial court again ordered RSV to remedy the surface water violations at the facility and imposed a civil penalty of $10,000. Both orders set forth stipulated penalties should RSV fail to comply with the terms of the agreements.

{¶ 8} Still unsatisfied with RSV's efforts to comply with the terms of the two consent orders, the State filed a second motion for contempt on August 1, 2002. On September 17, 2002, the trial court combined the bench trial and contempt hearing and heard the case.

{¶ 9} On November 13, 2002, the trial court issued a ruling of liability and then a final order on December 12, 2002. The trial court found RSV in violation of thirteen counts of Ohio's environmental laws and two counts of contempt. The court also awarded the State a monetary penalty of $413,225. Both parties appealed.

{¶ 10} RSV's first assignment of error states:

{¶ 11} "The trial court erred in imposing a penalty against Defendants on Count III of the State's Charges in Contempt, when, at the conclusion of the liability phase, the trial court had found `substantial efforts' on the part of the Defendants to comply with this agreement and therefore not in contempt for failing to complete the channel."

{¶ 12} RSV argues that the trial court's decision with regard to the surface water diversion plan (i.e., Rush Run) was inconsistent with its factual findings. It appears that RSV's argument contains some merit. Additionally, the State does not really dispute that the trial court's decision and findings are inconsistent in this respect.

{¶ 13} Both Counts II and III of the State's Second Motion for Contempt relate to the building of a diversion channel on the west side of the facility. Count II related to the construction of an open trapezoidal channel on the southwest portion of the landfill. Count III related to the installation of a storm sewer pipe on the northwest portion of the landfill. It is undisputed that these were not considered separate and distinct diversion channels.

{¶ 14} The trial court did not find RSV liable under Count II in connection with construction of the open channel, concluding that RSV had performed "substantial efforts" to comply with the agreed judgment entry. The trial court specifically noted that RSV had made substantial efforts in attempting to remove large quantities of rock, and that these efforts were hampered by a gas line and the State's concerns about that gas line.

{¶ 15} The trial court then found RSV liable under Count III of the State's Second Motion for Contempt, finding that RSV's failure to install the storm pipe was "without showing good cause." The pipe portion of the diversion channel, which is the area relevant to Count III of the contempt motion, is the area where the rock needed to be removed before installing the pipe. The trial court acknowledged that RSV had made "substantial efforts" in attempting to remove the rock, and that these efforts, coupled with unforeseen circumstances, justified RSV's failure to meet the deadline set forth in the agreed judgment entry. Count II, on the other hand, related to the construction of an open channel which did not require the removal of any rock, as was needed to install the pipe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-petro-v-rsv-inc-unpublished-decision-1-13-2006-ohioctapp-2006.