State Ex Rel. Park County v. Montan

CourtMontana Supreme Court
DecidedJune 30, 1992
Docket92-246
StatusPublished

This text of State Ex Rel. Park County v. Montan (State Ex Rel. Park County v. Montan) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Park County v. Montan, (Mo. 1992).

Opinion

IN THE SUPREME COURT OF THE STATE OF MONTANA

No. 92-246

STATE ex rel. PARK COUNTY,

Relator, ORDER -v- ; ) OPIyDIOVN MONTANA SIXTH JUDICIAL DISTRICT TTE $7 ;: COURT, PARK COUNTY, THE HONORABLE jp ,ji, jj _,:, y i ,:,, j BYRON L. ROBB, Presiding Judge, iJi-1 2 3 'i.?J:!z, F,~j Respondent. ,~ ;., i&i _~ i :, ~: CiJfi;~.;';i: $1., ;~';:ci-;~ ;& This Court on May 28, 1992, in response to an application for

writs, ordered the respondent/plaintiff (Kenneys), to respond to the application within a determined time period and further ordered

that the preliminary and permanent injunctions enjoining Park

County from interfering with Kenneys' removal and disposal of

sludge and debris temporarily be vacated and stayed. Kenneys having now filed its response and brief the matter is ripe for

decision. We dissolve the injunctions.

Park County has filed herein an application for a writ of

supervisory control and other appropriate writs of relief.

However, we will treat the application as an appeal. Under Rule

1 (b) (2) , M.R.App.P., a party may appeal from a judgment or order granting or dissolving an injunction, or refusing to grant or

dissolve an injunction. We will not consider whether the facts set forth meet the criteria for our consideration and exercise of

1 jurisdiction over an application for writ of supervisory control.

In 1991 Park County (County) entered into a contract with

Kenneys, which called for repairs and renovations to the Waste

Water Treatment Plant in Gardiner, Montana, including the

installation of an impermeable liner under two large settling

ponds. As part of the repair process, Kenneys was to remove and

dispose of the sludge which had settled to the bottom of each pond.

In the contract there was a base amount for the removal of 60 cubic

yards of sludge based on an estimated quantity of sludge in the ponds. This estimate was prepared by H.K.M. Associates

Engineers/Planners, the engineering firm retained by the County. Also in the contract was a requirement that a unit price be

submitted for each additional cubic yard over and above the 60

cubic yards of sludge which might be removed. Kenneys proceeded to

remove the sludge from the first of the two ponds. Thereafter it submitted a claim for $120,000, alleging that it had removed at the

very least 2400 cubic yards of sludge based on a percentage of

solid content. Kenneys further asserted a right to $240,000 for

4800 cubic yards of sludge based on a different percentage of solid

content. The County objected to this claim and has not paid the

same.

On March 19, 1992, the County ordered deletion from the

contract the sludge removal on the second aeration pond which it

argued was permissible under the construction contract. Previous

to the deletion, on February 25, 1992, Kenneys filed suit in the District Court of the Sixth Judicial District for breach of

2 contract, claiming nearly $200,000 in damages for payment allegedly

due for work on the first pond. As part of that lawsuit, on April

29, 1992, the District Court granted a preliminary injunction and

ordered that the County was enjoined from interfering with Kenneys'

performance of the sludge removal work on the second aeration pond.

Subsequently, both parties filed motions, including motions to

dissolve, and motions for contempt. A hearing was set on the

motions for May 11, 1992. On May 6, 1992, Kenneys filed a motion

for summary judgment contending that the County's deletion order

constituted a breach of contract. On May 7, 1992, Kenneys filed a

second motion for summary judgment asking the court to convert the

preliminary injunction into a final injunction. On May 8, 1992,

the County telefaxed to Kenneys' counsel a formal objection to the

hearing on the motions for summary judgment and especially declined

to waive the County's right to the ten day notice period on these

motions. The County's formal objection to the early hearing on

Kenneys' motion for summary judgment was hand delivered to the

court on May 11, 1992. The District Court overruled the County's

objections to the hearing on the summary judgment motions.

Following oral argument, the District Court denied Kenneys' motion

for contempt, and denied Kenneys' motion for summary judgment on

the contract. Further, the District Court denied the County's

motion to dissolve or modify the injunction, and denied the

County's motion for summary judgment relative to Kenneys' claim for

injunctive relief. However, the District Court granted Kenneys'

motion for summary judgment requesting the County be permanently

3 enjoined from interfering with Kenneys' performance of the sludge

removal contract. The oral ruling was reduced to writing on May

12, 1992 and this application followed.

Our scope of review relative to the issue of whether or not

injunctive relief was improper, is to determine whether the

District Court's determination as to the law is correct. See

Steer, Inc. v. Dept. of Revenue (1990), 245 Mont. 470, 803 P.2d

601.

Section 27-19-103(5), MCA (1991), provides as follows:

An injunction cannot be granted: . . . (5) to prevent the breach of a contract the performance of which would not be specifically enforced: . . .

Generally construction contracts cannot be specifically enforced

because performance would constitute a personal service

approximating involuntary servitude. Further, money damages

provide an adequate legal remedy. One of the most common

applications of this rule is found in cases involving building and

construction contracts. These contracts will not be specifically

enforced, partly because damages at law are an adequate remedy, and

partly because of the incapacity of the court to superintend their

performance. See 71 Am.Jur.2d, Specific Performance 5 165 (1973).

Here, Kenneys have an adequate remedy at law for damages under

the contract. As to this contract, it can be readily envisioned,

that questions will arise and be presented to both the District

Court and to this Court, as they have in the past, which will put

the court system in the position of superintending the performance

4 of a contract. As stated above, this is one of the major reasons

why the performance of this contract should not be specifically

enforced.

Kenneys argue that injunctive relief is appropriate because

section 6.29 of the contract creates an obligation of specific

performance on the part of the contractor. If the contract is

found to require specific performance, then the remedy of specific

performance is made reciprocal by operation of law. See § 27-1-

414, MCA. Section 6.29 of the contract provides as follows:

CONTRACTOR shall carry on the work and adhere to the progress scheduled during all disputes or disagreements with owner. No work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 15.5 [termination] or as CONTRACTOR and OWNER may otherwise agree in writing.

However, section 6.29 is a contractual obligation which informs the

contractor that he is expected to continue his work even though

there might be disputes or disagreements with the owner. This does

not mandate specific performance. A contractor would still be free

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steer, Inc. v. Department of Revenue
803 P.2d 601 (Montana Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
State Ex Rel. Park County v. Montan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-park-county-v-montan-mont-1992.