State ex rel. Martin Machinery Co. v. Line One, Inc.

111 S.W.3d 924, 2003 Mo. App. LEXIS 1321, 2003 WL 21978107
CourtMissouri Court of Appeals
DecidedAugust 19, 2003
DocketNo. 24901
StatusPublished
Cited by2 cases

This text of 111 S.W.3d 924 (State ex rel. Martin Machinery Co. v. Line One, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Martin Machinery Co. v. Line One, Inc., 111 S.W.3d 924, 2003 Mo. App. LEXIS 1321, 2003 WL 21978107 (Mo. Ct. App. 2003).

Opinion

PHILLIP R. GARRISON, Judge

This case involves a contract dispute arising out of a public works project. Har-tec Corporation (“Hartee”) and The Ohio Casualty Insurance Company (“Ohio Casualty”) (collectively, “Appellants”) allege in two points on appeal that the trial court erred in entering judgment against them and in favor of E.A. Martin Machinery Company (“Respondent”) for $44,203.37. We agree and reverse the trial court’s judgment.

On June 20, 1997, Public Water Supply District Number 2 of McDonald County, Missouri (“the District”) entered into a contract (“Bonded Contract”) with Still Construction Company, Inc. (“Still”) whereby Still was to serve as the general contractor responsible for building water distribution lines for a public works project owned by the District. The same day, a payment bond in the amount of $1,735,878 was executed by the District, Still, and Ohio Casualty wherein Ohio Casualty agreed to serve as surety for the project. Ohio Casualty apparently also executed a performance bond guaranteeing completion of the project, although the record does not indicate when this occurred.

In preparation for work on the project, Still entered into a subcontract with Line One, Inc. (“Line One”) for the excavation and installation of the pipeline. Line One, in turn, entered into at least two contracts with Respondent, on June 10, 1998 and again on July 20, 1998, for the rental of heavy construction equipment to complete Line One’s work on the project. Line One failed to pay Respondent a significant portion of the rent due under these contracts, as well as for repair services provided by Respondent during the course of Line One’s work. This past due amount, some $28,120.49, plus interest, served as the basis for the suit underlying this appeal.

In or around February 1998, Still informed the District and Ohio Casualty of financial difficulties it was experiencing which could jeopardize its ability to complete the project. Eventually, Still was defaulted by the District when Still acknowledged its inability to complete its work. As a result of Still’s default, Ohio Casualty, as surety for the project, entered into an agreement (“Completion Agreement”) with Hartee, by which Hartee committed “to complete the Project pursuánt to the terms and conditions of the Bonded Contract.” On July 17, 1998, the substitution of Hartee as the general contractor for the project was ratified by the District and Ohio Casualty in a document entitled [927]*927“Contract Takeover Agreement” (“Takeover Agreement”).

On March 18, 1999, Respondent presented a ■written claim against the payment bond to Ohio Casualty in which Respondent sought payment of Line One’s indebtedness from the rental contracts and repairs performed by Respondent. No written notice or request for payment was sent to Hartec or the District. On January 18, 2000, Respondent filed a petition in the trial court naming Line One, Hartec, and Ohio Casualty as defendants and seeking damages in the amount of Line One’s indebtedness, plus interest and attorney fees.

Respondent’s petition contained three counts: Count I named only Line One as defendant and sought damages for breach of contract in the amount of $34,565.01. Count II incorporated the allegations of Count I by reference, named Appellants as defendants, and sought a judgment establishing the joint and several liability of Appellants for the indebtedness of Line One. In Count III, Respondent repeated the allegations of Counts I and II, but founded its claim upon Section 84.057,1 the “Public Works Prompt Pay Statute.” Pursuant to that statute, Respondent sought from Appellants and Line One attorney fees and court costs in addition to its actual damages. See Section 84.057(6).

On June 23, 2000, Appellants filed their amended answer to Respondent’s petition, in which they submitted the affirmative defense that Respondent had failed to state a claim upon which relief could be granted in that Respondent had failed to comply with the payment bond’s notice requirements prior to filing its petition. Appellants also filed a cross-claim against Line One seeking indemnification from Line One should Respondent be granted judgment against Appellants.

Line One failed to appear or respond to Respondent’s petition. On June 5, 2000, Respondent filed a motion for interlocutory order and judgment by default against Line One. On December 27, 2000, the trial court entered a judgment by default against Line One as to Count I of Respondent’s petition in the amount of $28,120.49 plus interest and costs. Prior to trial of the remaining two counts, Respondent voluntarily dismissed Count III with prejudice, in consideration of Appellants’ agreement not to seek a jury trial.

Trial of the remaining count, Count II, was had on January 7, 2002. On April 1, 2002, the trial court entered is final judgment in the amount of $44,203.37 against Appellants as to Count II of the petition, and against Line One, in the same amount, as to Appellant’s cross-claim. The trial court did not render findings of fact or conclusions of law in its judgment. This appeal follows.

In a court-tried case, “[t]he decree or judgment of the trial court will be sustained by the appellate court unless there is no substantial evidence to support it, unless it is against the weight of the evidence, unless it erroneously declares the law, or unless it erroneously applies the law.” Kimberling North, Inc. v. Pope, 100 S.W.3d 863, 871 (Mo.App. S.D.2003) (quoting Ryan v. Spiegelhalter, 64 S.W.3d 302, 305 (Mo. banc 2002)). Where, as here, the trial court’s judgment included no findings of fact or conclusions of law, “the judgment is to be upheld on any reasonable theory within the pleadings and supported by the evidence.” Schaefer v. Rivers, 965 S.W.2d 954, 956 (Mo.App. S.D. 1998).

[928]*928In the first of Appellants’ two points, they allege that the trial court erred in granting judgment against them because Respondent failed to submit substantial evidence that it complied with the express notice provisions of the payment bond.2 Specifically, Appellants contend that notice of Respondent’s claim against Line One on their rental agreements was not presented within ninety days to at least two of the three parties to the payment bond and that Respondent could not, therefore, commence any action against Appellants seeking payment of Line One’s debt.

The payment bond contains the following provision:

PROVIDE[D] FURTHER, that no suit or action shall be commenced hereunder by any claimant: (a) Unless claimant ... shall have given written notice to any two of the following: [the general contractor], the [District] or [Ohio Casualty] ... within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed.

In order to comply with this provision, Respondent must have provided written notice to either Hartec, as the completing general contractor, or the District in addition to its notice to Ohio Casualty. This did not occur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sparks v. PNC Bank
400 S.W.3d 454 (Missouri Court of Appeals, 2013)
Stom v. St. Clair Corp.
153 S.W.3d 360 (Missouri Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
111 S.W.3d 924, 2003 Mo. App. LEXIS 1321, 2003 WL 21978107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-martin-machinery-co-v-line-one-inc-moctapp-2003.