State Ex Rel. Lathers v. Smith

299 N.W. 43, 238 Wis. 291, 1941 Wisc. LEXIS 44
CourtWisconsin Supreme Court
DecidedMay 21, 1941
StatusPublished
Cited by4 cases

This text of 299 N.W. 43 (State Ex Rel. Lathers v. Smith) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Lathers v. Smith, 299 N.W. 43, 238 Wis. 291, 1941 Wisc. LEXIS 44 (Wis. 1941).

Opinion

Wickhem, J.

Since this matter comes up on demurrer, it is necessary to analyze the pleadings of the parties. It may be stated at this point that several exhibits omitted from the petition, consisting of the original and supplemental contracts involved here, standard specifications of the state highway commission, and other papers, were by stipulation included in the record. This was not done by formal amendment to either of the pleadings, but since the question is whether upon the whole record the demurrer should have been sustained, and since the exhibits .are stipulated into the record, we shall simply consider them as facts admitted by the demurrer. ■

The petition, after identifying defendant as the duly elected treasurer of the state of Wisconsin, sets forth that on May 16, 1940, petitioner signed a contract with the state of Wisconsin acting through the state highway commission whereby he undertook to perform certain grading operations involved in the construction of State Trunk Highway No. 30. This *296 contract was approved by the state highway commission on May 27, 1940, by the state chief engineer on May 28, 1940, and by the governor of the state on May 29, 1940. It is alleged that on October 11, 1940, a supplemental contract was entered into- between petitioner and the state of Wisconsin through the highway commission amending the original contract to the extent that the contract unit price for rock excavation was changed from $1 per cubic yard, as provided by the original contract, to1 thirty-five cents per cubic yard. Allegations follow to the effect that the original contract was executed only after proper bids were made, that petitioner entered upon the construction project, and that at the time of the petition he had completed over ninety-five per cent of the work. It is alleged that under the terms of the contract petitioner, is entitled to a partial payment from the state of Wisconsin in the sum of $16,600. It is alleged that standard specifications for road construction of the state highway commission are a part of the original contract between the petitioner and the state, and that section 109.06 of these specifications provides in substance that each month the engineer will make an approximate estimate in writing of materials in place complete and the amount of work performed and the value oí this work at contract unit prices. It is provided that fifteen per cent of this amount is to be retained by the commission until the completion of the contract in an acceptable manner, and the balance certified by the commission for payment unless the balance amounts to less than $500. When not less than ninety-five per cent oí the work has been completed, the specifications provide for a semifinal estimate as to the amount due from which the commission is required to retain a sum equal to not less than twice the contract value or cost of work remaining to be done. It is alleged that prior •to December 27, 1940, the state highway commission, pursuant to the foregoing specifications, made twelve estimates of partial payments due to petitioner. All of these estimates *297 were audited by the secretary of state and paid by defendant. It is alleged that on or about December 23, 1940, the state highway commission prepared estimate No. 13 of the amount of partial payments due to petitioner, and the result of this estimate was a recommendation for the payment of $16,600. The state highway commission thereupon issued a voucher signed by its chairman certifying that petitioner was entitled to $16,600 as a partial payment. On December 23, 1940, this voucher was presented to the financial secretary of the governor and indorsed with his approval. On December 27, 1940, the voucher was presented to the secretary of state for audit. On February 12, 1941, the secretary of state audited and allowed the claim in the sum of $16,600. On February 12, 1941, the secretary of state issued a warrant in the form of a check or draft on defendant in favor of petitioner and transmitted to defendant a copy of the voucher together with the original warrant or check for countersignature and payment. On or about February 18, 1941, defendant countersigned the check and delivered it to the state highway commission for delivery to' petitioner, but at some time subsequent thereto he recalled the check and has since persisted in refusal to countersign or deliver the warrant or check to petitioner. A formal demand on defendant on February 24, 1941, is alleged, together with defendant’s refusal. Various allegations which amount to conclusions of law with respect tO' the powers of the state highway commission and the duties of defendant are added to the petition, and the peremptory writ is prayed for.

The return denies that a supplementary contract was made between petitioner and the state of Wisconsin as alleged in the petition. The return sets forth that on October 11, 1940, the state highway commission approved the so-called “supplemental contract” signed by petitioner and dated October 2, 1940, which in form purported to change the original contract in several particulars by changing the classification *298 of 54,575 cubic yards of estimated excavation from common excavation, which had a contract price'of fifteen cents per cubic yard, to rock excavation, which had a contract unit price of $1 per yard; that the supplemental agreement applied the contract unit price for rock excavation to 5,025 cubic yards of the total' amount involved and a new unit price of thirty-five cents pe-r cubic yard for the remaining 49,550 cubic yards. Defendant further alleges that “as he is informed and believes, the 54,575 cubic yards of excavation thus reclassified was not rock excavation but was common excavation according to the definitions in section 206 of the standard specifications” referred to in the original contract; that “the character of the material comprising such 54,575 cubic yards is designated in the cost analysis appended to the so-called supplemental agreement as ‘hardpan (rock excavation)’ but that by section 206.01 (b) of said standard specifications, ‘hardpan’ was and is classified as ‘common excavation.’ ” It is alleged that by the original contract petitioner was not lawfully entitled to payment for excavating the 54,575 cubic yards at any unit price other than that prescribed for common excavation, namely, fifteen cents per cubic yard, and that the supplemental agreement attempting to change this unit price was and is void. It is alleged that the voucher presented to defendant for payment is void for the same reason. Defendant further sets up that while the original contract was duly executed with the approval of the state chief engineer and the governor, as required by sec. 15.79, Stats.,, the so-called “supplemental agreement” upon which petitioner relies involves an expenditure of more than $1,000, and, not having' been approved in writing by the state chief engineer or the governor, is void for failure to conform to the provisions of sec. 15.79; that petitioner’s claim is void under the same section because not audited by the state chief engineer. Defendant further alleges that the powers of the state highway commission are subject to the limitation that all contracts must be based on competí- *299

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schroeder v. Schoessow
321 N.W.2d 131 (Wisconsin Supreme Court, 1982)
State Ex Rel. Reynolds v. Smith
120 N.W.2d 664 (Wisconsin Supreme Court, 1963)
State Ex Rel. City of Madison v. Bareis
21 N.W.2d 721 (Wisconsin Supreme Court, 1946)
State Ex Rel. Lathers v. Smith
8 N.W.2d 345 (Wisconsin Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
299 N.W. 43, 238 Wis. 291, 1941 Wisc. LEXIS 44, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-lathers-v-smith-wis-1941.