State, Ex Rel. Horvitz Co. v. Riebe

354 N.E.2d 708, 47 Ohio App. 2d 339, 1 Ohio Op. 3d 399, 1975 Ohio App. LEXIS 5883
CourtOhio Court of Appeals
DecidedDecember 9, 1975
Docket34985
StatusPublished
Cited by5 cases

This text of 354 N.E.2d 708 (State, Ex Rel. Horvitz Co. v. Riebe) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State, Ex Rel. Horvitz Co. v. Riebe, 354 N.E.2d 708, 47 Ohio App. 2d 339, 1 Ohio Op. 3d 399, 1975 Ohio App. LEXIS 5883 (Ohio Ct. App. 1975).

Opinion

Keenzi/er, C. J.

This is an original action in mandamus. The relator, a general construction company, filed a petition for writ of mandamus seeking to compel payment of money owed to it by the city of Cleveland .under three contracts, numbered 25,931, 26,631 and 26,455, and held in funds under the control of the respondents, the city’s Director of Finance, Commissioner of Accounts and Treasurer.

In its petition the relator maintains that the city is under a clear legal duty to pay it the money owed and that it had no adequate remedy at law to compel such payment. A motion to dismiss, filed by the respondents, was denied. Subsequently, the respondents filed a joint answer to the petition in which they prayed thát the petition be dismissed for the reason that the. relator failed to state a claim for which relief could be granted in that it had an adequate remedy at law.

The relator and the respondents stipulated to the facts as follows. The relator and the city of Cleveland entered into two contracts, numbered 25,931 and 26,631, involving reconstruction work at Cleveland Hopkins International Airport. This work included the reconstruction of various runways, taxiways, fillets, baggage'roadways .and other air *341 field improvements. The relator periodically submitted written requests for payment, for work completed to various city officials for approval, as required under the contracts. All necessary approvals for payment were obtained from these officials. The total amount due on the two contracts is $819, 876.99.

A third contract, number 26,455, was entered into by the relator and the city of Cleveland whereby the relator was to deliver certain asphaltic materials to the city. The relator in fact delivered the materials to the city and also submitted invoices for such materials. Unpaid invoices on this contract total $229,920.45.

All sums needed to pay the relator under the three ■contracts are available and held in funds of the city under the control of the respondents, the city’s Director of Finance, Commissioner of Accounts, and Treasurer.

The city of Cleveland contends that the relator has an adequate remedy at law by bringing an action on an account. The city further contends that it does not have a clear legal duty to pay the money due the relator because of the pendency of a negligence action, case number 74-935,336, in the Court of Common Pleas of Cuyahoga County, in which action the city of Cleveland and Edgewater Yacht Club, Inc., are the plaintiffs and the relator and the Cleveland Regional Sewer District are the defendants. That lawsuit charges the relator and the Regional Sewer District with the negligent destruction of city property at Edgewater Park. The issue in that lawsuit is unrelated to the issue in the present mandamus action.

R. C. 2731.01 defines mandamus as follows:

“Mandamus is a writ, issued in the name of the state to an inferior tribunal, a corporation, board, or person, commanding the performance of an act which the law specifically enjoins as a duty resulting from an office, trust, or station.”

However, R. C. 2731.05 limits the situations in which a writ of mandamus can be issued. That statute provides:

The writ of mandamus must not be issued when there is a plain and adequate remedy in the ordinary course of the law.”

*342 In the present ease there is no doubt that a remedy at law is available to the relator, namely, an action on an account. However, the question is whether this available remedy is an adequate remedy.

Under the stipulated facts, it is undisputed that the relator has fully performed under the terms of the three contracts and is entitled to be paid the approximate amount of $1,049,796. All necessary approvals by Cleveland city officials required under the contracts have been obtained. The city of Cleveland is obligated to make immediate payment and issue the checks for payment, which is merely a ministerial act.

There is no reason why the relator should be compelled under the narrow circumstances presented in this case to file a lawsuit on an account in the Common Pleas Court seeking payment of the - debts owing to it. An action on an account would result in a lengthy delay before the relator could obtain the money properly due it. This delay would result in serious economic harm. This economic harm would occur because the relator would be deprived of substantial working capital for a long period of time because public officials, the respondents, would not perform their ministerial and clear legal duty.

If the writ is granted in this case, the relator would immediately receive the money due it under the terms of the contract and could use this money as working capital. If the relator were required to maintain an action at law on an account, such action might not be terminated for several years. Interest on such a judgment would only begin to run after judgment was entered and not from the date the city refused to pay the money. Consequently, the relator would suffer serious economic loss. This economic loss coupled with the time loss makes the remedy of suing on an account not an adequate remedy at law.

The Ohio Supreme Court in the case of State, ex rel. The Merydith Construction Co., v. Dean (1916), 95 Ohio St. 108, has defined an adequate remedy at law as one:

“* * * complete in its nature, beneficial and speedy.” (Emphasis supplied.)

*343 In the instant ease, the remedy of an action at law on the contract is neither complete nor speedy. Further, the Supreme Court has held in State, ex rel. Riley Cons truction Co., v. East Liverpool Board of Education (1967), 10 Ohio St. 2d 25, that an action in mandamus, seeking appropriate relief, may be instituted and maintained where time and costs are controlling and make other remedies inadequate. In that case the court stated that it would entertain an original action in mandamus rather than relegate the parties to the Common Pleas Court with the delays incident to a determination there and subsequent appeals. The principles of the Riley Construction case are applicable here. The relator does not have an adequate remedy at law.

In determining whether the city of Cleveland is under a clear legal duty to pay the relator, this court must consider the foregoing stipulations and the fact that the respondents have presented ho defenses on the contract justifying non-payment. These two factors compel the conclusion that the city is under a clear legal duty to issue the required cheeks.’

The mere pendency of another action arising out of an unrelated transaction but involving the same parties does not automatically defeat the maintenance of this mandamus action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Mosser Construction, Inc. v. City of Toledo
676 N.E.2d 602 (Ohio Court of Appeals, 1996)
Sherman v. Haines
1995 Ohio 183 (Ohio Supreme Court, 1995)
State ex rel. Ms. Parsons Constr., Inc. v. Moyer
1995 Ohio 241 (Ohio Supreme Court, 1995)
State ex rel. Ms. Parsons Construction, Inc. v. Moyer
650 N.E.2d 472 (Ohio Supreme Court, 1995)
State ex rel. Fenske v. McGovern
464 N.E.2d 525 (Ohio Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
354 N.E.2d 708, 47 Ohio App. 2d 339, 1 Ohio Op. 3d 399, 1975 Ohio App. LEXIS 5883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-horvitz-co-v-riebe-ohioctapp-1975.