State Ex Rel. Graddick v. St. Paul Fire & Marine Ins. Co.

431 So. 2d 1237
CourtSupreme Court of Alabama
DecidedMay 20, 1983
Docket81-205
StatusPublished
Cited by3 cases

This text of 431 So. 2d 1237 (State Ex Rel. Graddick v. St. Paul Fire & Marine Ins. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Graddick v. St. Paul Fire & Marine Ins. Co., 431 So. 2d 1237 (Ala. 1983).

Opinion

431 So.2d 1237 (1983)

STATE of Alabama, ex rel. Charles A. GRADDICK, Attorney General of the State of Alabama, et al.
v.
ST. PAUL FIRE & MARINE INSURANCE COMPANY, INC., Chris C. Rush, and Franklin Group Architects, P.A., etc., et al.

81-205.

Supreme Court of Alabama.

May 20, 1983.

*1238 J. Knox Argo of Argo & Enslen, Montgomery, for appellants.

John Patterson of Patterson & Rinehart, Montgomery, and W. Terry Bullard of Moody, Burford, Phillips & Bullard, Birmingham, for appellee St. Paul Fire & Marine Ins. Co., Inc.

James W. Garrett, Jr. of Rushton, Stakely, Johnston & Garrett, Montgomery, for appellee Franklin Group Architects.

EMBRY, Justice.

This is an appeal by the State of Alabama from a judgment which denied the State's claims on its complaints against St. Paul Fire and Marine Insurance Company, a corporation (St. Paul); Chris C. Rush d/b/a Rush Building Company (Rush); and James R. Franklin, James R. Franklin Architects/Planners P.A., Franklin Group Architects, P.A. (Franklin) and granted relief for Rush on his third party complaint and directed that a writ of mandamus issue to the Director of the State Department of Conservation and Natural Resources ordering him to take the necessary action to pay Rush $28,028.22 for extra work performed by Rush under contract No. 28-P-20. We affirm.

Plaintiff, State of Alabama, brought suit against St. Paul, Rush, and Franklin for breach of contract and fraud against Rush; breach of contract, fraud and deceit, and negligence against Franklin. In addition it was alleged that Franklin and Rush acted in collusion to plaintiff's detriment. Suit was brought against St. Paul on a performance bond issued by St. Paul as surety for Chris Rush naming the State of Alabama Department of Conservation as obligee. Rush by third party complaint against John M. McMillan, Jr., as Director of the Department of Conservation and Natural Resources of the State of Alabama sought a writ of mandamus ordering payment of $28,028.22 for extra work performed by Rush for plaintiff under contract. Defendant Franklin denied any breach of contract, fraud or negligence and pleaded that the actions were barred by the statute of limitations, laches, estoppel, failure to give proper notice; that plaintiff negligently contributed to its own damages, failed to *1239 mitigate its damages, and that plaintiff's damages were caused by its failure to let contracts for roads and utilities simultaneously with the buildings contract. Defendants, Rush and St. Paul, denied any breach of contract or bond or fraud and pleaded that the actions were barred by the statute of limitations, laches, estoppel, failure to give proper notice; that plaintiff failed to mitigate its damages, that its damages were caused by its failure to let contracts for roads or utilities simultaneously with the buildings contract or failing to let them in the proper order, that the suit was not timely brought, and acceptance and waiver. Defendant St. Paul, further defended on the grounds that the final payment, including retainage, to Rush, without notice to it, discharged it as surety. Plaintiff denied the allegations in Rush's third party complaint.

Plaintiff brought a second suit (utilities contract suit) against St. Paul on a performance bond as surety for Rush naming the State of Alabama Department of Conservation as obligee and against Rush on contract No. 28-P-19. Defendants, Rush and St. Paul, denied any breach of contract or bond, and pleaded that the actions were barred by the running of the statute of limitations, laches, estoppel, failure to give proper and timely notice of defects; that the suit was not timely brought, acceptance and waiver. Defendant St. Paul further defended on the grounds that the final payment, including retainage, to Rush, without notice to it, discharged it as surety. Franklin had originally been a defendant in this latter suit and had filed a third party complaint against Ladd Environmental Engineers, Inc., Ladd Environmental Consultants, Inc., Ladd Engineering Associates, Inc., E.J. Ladd, F.H. Landstreet and C.M. Landstreet; however, prior to trial, on motion of plaintiff and order of the trial court and on motion of Franklin and order of the trial court, the complaint against Franklin and the third party complaint against Ladd were dismissed.

A trial on the merits was held from 25 May to 29 May 1981. The cases, as tried, consisted of:

(1) Suit by the State of Alabama against Rush and St. Paul based upon the State's contentions that there were deficiencies in the work performed by Rush on contract No. 28-P-19, the utilities contract.

(2) Suit by the State of Alabama against Rush, St. Paul and Franklin based upon the State's contention that there were deficiencies in the work performed by Rush and Franklin under contract No. 28-P-20, building contract.

(3) Third party complaint of defendant Rush claiming monies owed by the State of Alabama to Rush for extra work performed by Rush during Rush's performance of contract No. 28-P-20, building contract.

The cases were consolidated for trial by agreement, and tried and submitted for determination by the trial court on the pleadings, testimony ore tenus, briefs and exhibits introduced at trial. After a thorough review of the record and briefs in this case, this court is well-satisfied with the trial court's findings of fact and conclusions of law as set forth in its order of 3 September 1981. The pertinent part of that order is as follows:

"The Court has considered the evidence, arguments of counsel and the brief filed on August 20, 1981 containing the contentions of Rush and Franklin. The Court is of the opinion that the Plaintiff has failed to meet its burden of proof that Rush breached either of the contracts or warranties or any other duty owed the Plaintiff arising out of the construction projects; that Plaintiff also failed to meet its burden of proof that Franklin breached his contract with the State; that Plaintiff also failed to meet its burden of proof that Franklin or Rush were guilty of fraud, collusion or negligence as alleged in the pleadings; and that Rush has met his burden showing a clear right to a writ of mandamus to effect payment for the extra work and expense which he claims. It is the further opinion of the Court that judgment should be rendered in favor of Rush and Franklin and against Plaintiff on both of *1240 Plaintiff's complaints as amended and all counts therein; that Rush is entitled to $28,028.22 for extra work and expenses, and judgment should be rendered in his favor on his third party complaint, and writ of mandamus prayed for, issued; and that judgment should be rendered in favor of St. Paul and against Plaintiff on both of Plaintiff's complaints and all counts therein, as St. Paul is surety for Rush and has all the defenses available to Rush. The evidence shows that St. Paul was not given notice prior to the payment of the retainage. St. Paul contends that in the absence of fraud, this discharged them as surety. The Court agrees...."

A strong presumption as to the correctness of the trial court's findings of fact exists on appeal, and these findings will be set aside only if unsupported by credible evidence or if found to be plainly and palpably wrong. Shepherd Realty v. Winn-Dixie Montgomery, 418 So.2d 871 (Ala.1982); Reliance Ins. Co. v. Substation Products Corp., 404 So.2d 598 (Ala.1981). The trial court's conclusions are amply supported by the evidence of record and we cannot find that its decision was palpably wrong.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aaberg v. Aaberg
512 So. 2d 1375 (Supreme Court of Alabama, 1987)
State Farm Mutual Automobile Insurance Co. v. Hartman
450 So. 2d 152 (Court of Civil Appeals of Alabama, 1984)
Wolfe v. McClung
445 So. 2d 913 (Court of Civil Appeals of Alabama, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
431 So. 2d 1237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-graddick-v-st-paul-fire-marine-ins-co-ala-1983.