State ex rel. Fanning v. Board of Commissioners

6 Ohio N.P. 405
CourtCuyahoga County Common Pleas Court
DecidedJuly 1, 1899
StatusPublished

This text of 6 Ohio N.P. 405 (State ex rel. Fanning v. Board of Commissioners) is published on Counsel Stack Legal Research, covering Cuyahoga County Common Pleas Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Fanning v. Board of Commissioners, 6 Ohio N.P. 405 (Ohio Super. Ct. 1899).

Opinion

Dissette, J.

Waiving the reading of all of the formal matters in this petition, the relator brings this suit as a taxpayer of tliis county, asking that the defendants l)e enjoined from the payment of a certain estimate made to Miller, a contractor, and also a sum claimed by engineer Baker for services on what, is known as the Brecksville road, and, after alleging that he had requested both the county solicitor and the county prosecutor tc institute the present action and they had refused, thereby compelling the relator to bring the suit himself, he says; “That in 1896 the county commissioners instructed the county surveyor to prepare specifications for the improvement of the road known as the Brecksville road, and that the county surveyor did prepare specifications and reported the same to the county commissioners on the 12th daycf September of that year; that the specifications contained a survey, profile and plans, and an estimate for said work; that afterwards another estimte was prepared, and he give» the figures of each estimate; and be says that on the last estimate, which did not differ materially from the first, bids were received but rejected, and in August, 1897, the said county surveyor made a fresh estimate which differed very [406]*406materially from either of the former in that it increased the amount of the earth excavation by about 40,000 to 45,000 yards, and decreased the hard-pan excavation by 11,000 cubic yards, and the loose rock by 20,000 to 21,000 cubic yards and the solid lock by 8.000 cubic yards. ” Complaining of the great disparity between these various specifications of the engineer, lie says, in substance: That, by using tin common methods of examination, well-known to engineers, the amount of the respective kinds of excavation could have been ascertained with very great certainty, and that the con tract could have been let intelligently, and that B iker, the engineer, by neglecting to U36 those means which he had been instructed to use in his last specification, upon which the bids were received for the improvement, grossly over-stated the lower-priced kinds of exoavation and under-stated the higher-priced kinds, and that, by reason of this, afforded an opportunity for bidders to bid much below a reasonable price on the lo-ver-priced work and much above a reasonable price on the higher-priced work, so that the one that was actually the highest bidder, by adopting this method, would seem to be the lowest; and, by means of a favorable classification of the excavations, the cost of the improvement would be made to far exceed the estimated cost, and the contractor would really be among the highest bidders. And, after reciting the fact that the commissioners entered inte a contract with one .Tames M. Miller on the 4th day of September, 1896, on a bid made by one John L. Farley, .and that that contract provided that the contractor should receive five cents for each cubic yard of earth excavation, and sixty cents for each cubic yard of hard pan, twenty-five cents for lóese rock, and $1.25 for solid rock, the plaintiff alleges that if the classification made in the last preliminary estimate furnished by the engineer and which was the basis upon which it was determined who was the lowest bidder, had been correct, the cost of the improvement would have been only $14,900.

This, I understand, to be exclusive of the cost for services of the engineer.

The burden of the plaintiff’s complaint is — without going into the detail which is set out fully and more particularly in ths petition — that the entire cost of this improvement, exclusive of engineer’s services, amount to $66,436.64.

In addition to that, the preliminary estimate mace by the engineer for engineering service, was only $1,950; but that the engineer has now presented a claim for $5,382 for engineering, and $1,191 for inspectors.

He alleges that said Miller has been already grossly over-paid, under his contract. That the statements of the amounts and kinds of excavation made by the contractor, as contained in the various estimates, are grossly inaccurate; and that the county commissioners’ attention was called to the facts at the time of filing the tenth estimate, and they were notified of the facts that the estimates of the amounts of the various kinds of excavation were grossly incorrect, and were such that Miller had already been grossly over-paid, and that nothing was due him, under said contract, by reason of the work already" done; but that the commissioners went on and paid said tenth estimate,and that the engineer afterwards filed an eleventh estimate, and that under this estimate the said contractor Miller now demands the sum of $8,226.84. That, in short, the county commissioners have allowed this estimate, and have ordered the county auditor to draw his warrant upon the county treasurer for the payment thereof, and that the auditor will draw his warrant upon the county treasurer and the county treasurer will pay the same unless restrained by the order of this court. They say that for the several good and sufficient reasons hereafter mentioned, this court should grant an order restraining the payment of this money :

First: The relator claims that the law, under which this improvement was made, in unconstitutional, and, therefore, that the commissioners had no power or authority to enter into this contract.

[407]*407Second: That this estimate contains, and is made up in part, of items for work which were contracted for by the county commissioners contrary to law

Third: Because one item charged in this estimate, for rolling and scrapr ing the road-bed, is not a proper charge, being inoluded in the general contract.

Fourth. Because the contractor has already been grossly over-paid.

Now, with reference to the first reason urged by the relator, to-wit, that the law, uuder which this improvement was made, is unconstitutional — I do not find it necessary -to-pass upon this question.

I regard the law itself as one of the most valuable and most important pieces of legislation that has been passed relating to county affairs, in the last quarter of a century — its purpose, being to improve all the highways leading from the city to the limits of the county, and it was drawn pursuant to the request of representatives from each township at a meeting called for that purpose. Several of the leading highways have been constructed at the cost of the general taxpayers; and it would work an injustice now to those who have paid their proper share of the expense of building these roads and have derived no benefit therefrom, but are expecting the board of county commissioners jn course of time to improve the highways in which they are particularly interested. It would work injustice, to those taxpayers. Besides, I have some doubts, or I might say, a faint hope that the supreme court would so modify its opinion, if it were necessary,'as to sustain this law.

The second reason why it is claimed that this estimate should not be paid, is, that it contains items contracted for by the county commissioners, without any authority of law.

Two particular items are mentioned as being contained in this last estimate; the one is for $2912, formasonr ry. If the contraot for this item was let by the county commissioners at one time, they certainly had no authority either under the general law governing the letting of contracts by them, or under this road law, to let such contract without first advertising for bids fcr the same.

There may be some question as to whether the commissioners violated the law in this respect.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
6 Ohio N.P. 405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-fanning-v-board-of-commissioners-ohctcomplcuyaho-1899.