State ex rel. Evans v. J. A. Swingle Contracting Co.

15 Ohio N.P. (n.s.) 279
CourtMuskingum County Court of Common Pleas
DecidedSeptember 15, 1913
StatusPublished

This text of 15 Ohio N.P. (n.s.) 279 (State ex rel. Evans v. J. A. Swingle Contracting Co.) is published on Counsel Stack Legal Research, covering Muskingum County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Evans v. J. A. Swingle Contracting Co., 15 Ohio N.P. (n.s.) 279 (Ohio Super. Ct. 1913).

Opinion

Frazier, J.

This cause was submittd to the court on the pleadings, the evidence, the arguments and briefs of counsel. By this action plaintiff seeks to enjoin performance of a contract, entered into between the defendant, the-J. A. Swingle Contracting Co., and the (board of county commissioners of Muskingum county, for the erection of the superstructure of a bridge at Sixth street, in the city of Zanesville, in place of one that was demolished by the March flood.

The contract for the proposed superstructure was entered into on the 3d day of September, 1913, and provides for a concrete structure with lift span over the canal. The grounds upon which plaintiff bases his claim for relief may be briefly summarized as follows:

1. That the board of county commissioners failed to comply with the statutes governing the procedure in the matter of bridge superstructures, in the following respects:

(a) That the board of commissioners did not determine the length of the bridge, as required by Section 2344-, General Code.

(Z>) That the proposed superstructure does not correspond with the determination of the board of commissioners as to the required length of the bridge.

(c) That the board of commissioners, as a board, never accepted the proposal of said J. A. Swingle Contracting Co. for the said superstructure.

[281]*281(d) That the board of commissioners did not award the contract at the time and place designated by the statute.

(e) That the board of commissioners considered no other-bid but the bid of the said Swingle Contracting Co., and that the public was thereby deprived of the benefits of competitive bidding.

2. That the proposed structure' is not of a suitable design or character.

Section 2344 provides as follows:

“When it becomes necessary to erect a bridge, the county commissioners shall determine the length and width of the superstructure, whether it shall have single or double track, and advertise for proposals for performing the labor and furnishing the materials necessary to the erection thereof. In their discretion the commissioners may cause to be prepared plans, descriptions and specifications for such superstructure, which shall be kept on file in the auditor’s office for inspection by bidders and persons interested, and invite bids or proposals in accordance therewith.”

Section 2345 provides as follows:

“They shall also invite, receive and consider proposals on any other plan at the option of bidders, and shall require that all proposals on such plan shall be accompanied with plans and specifications showing the number of spans, the length of each, the nature, quality and size of the materials to be used, the strength of the structure when completed, and whether there is any patent on the proposed plan, or on any, and if any, on what part thereof. ”

Under Section 2344, the board 'must determine the length and the width, etc., of the superstructure. A fair and just construction of the resolution of the board passed July 28, 1913, shows, in my opinion, that this was done. The resolution provided for the furnishing of material and labor for the reconstruction and rebuilding of the superstructure of the Sixth street bridge across the Muskingum river, in Zanesville, Ohio, to -replace the bridge recently destroyed by the flood. It provided that the superstructure should consist either;

(a) Of four spans, each 150 feet in length, one span 76 feet long, and one lift span 75 feet long; or

[282]*282(&) Of a series of reinforced concrete arches with supports from the same material, together with a lift span 75 feet long erected of the same material, on foundations to be provided by the county commissioners.

All bidders to submit plans under two separate plans as follows :

1. Said bridge to have a roadway 32 feet in the clear, to provide for a single street ear track, and to have a sidewalk on each side 6 feet wide, said roadway to be provided with treated block floor, sidewalks to be concrete, said bridge to carry loads as specified for class A, city bridges in Cooper’s latest specifications, 1909.

2. Bridge same dimensions as above except said roadway to be 40 feet in width in the clear, to provide for a double track, and sufficient strength to carry loads above specified.

This resolution clearly fixes the width of the bridge to be 32 feet in the clear, with a single street car track and sidewalks on each side 6 feet wide, and also provides for a bridge of the width of 40 feet in the clear, to be of the same dimensions as above provided. The phrase “dimensions above provided” had reference to the length of the bridge. There were to be four spans, each 150 feet in length, with one span 76 feet long and one lift span 75 feet long. These lengths added together make 751 feet. Applying the legal maxim, “Id cerium est quod cerium redendum est,” the length of the bridge is determined to be 751 feet and the width to be either 32 feet with sidewalks, or 40 feet, at the option of the commissioners, when plans were submitted. In my judgment, Section 2345 does not require, when bidders submit their own plans, that they must be so worked out that the plan submitted will be of the exact length determined by the board in its resolution. ' '

The argument is advanced in the briefs of plaintiff’s counsel that, unless all plans be confined to the length so determined, then there can be no competitive bidding. ,The Legislature has wisely provided that bidders may offer their own plans, and that the board shall accept from the entire number submitted the plan it deems best, considering price, plan, material, and method of construction. Price is not the sole thing to be considered. [283]*283Other elements' enter in, viz., plan, material, and method of construction. A wide discretion is here given to the board of commissioners. A comparison of the plan selected with plaintiff’s plan of bridge shows a difference of only 4.8 feet, when the clear length of the bridge is considered, excluding from both the length of the lift span, and both bids provide for exactly the same kind of lift span.

Section 2345 provides:

“When the bidder submits his own plan, it shall show the number of spans, the length of each, the nature, quality and size of the materials to be used, and the strength of the structure when completed.”

This, it seems to me, plainly means that the bidder is not limited to the exact length of the bridge as determined by the board in its preliminary resolution.

Plaintiff complains that the board of commissioners never accepted the plan and proposal of said J. A. Swingle Contracting Co. This contention is based on the fact that when the joint committee, composed of the three members of the board of commissioners, the auditor and the county engineer, considered the plans submitted by the bidders, two of the commissioners voted against the acceptance of the Swingle plan and proposal. Section 2350 provides:

‘ ‘ If the plans, drawings * * * relate to the building of a bridge, they shall be submitted to the commissioners, county auditor, and county surveyor. If approved by , a majority of them, a copy thereof shall be deposited with the county auditor and kept for the inspection of parties interested.”

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
15 Ohio N.P. (n.s.) 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-evans-v-j-a-swingle-contracting-co-ohctcomplmuskin-1913.