State Ex Rel. E. I. Dupont De Nemours & Co. v. Coda

138 S.E. 324, 103 W. Va. 676, 1927 W. Va. LEXIS 129
CourtWest Virginia Supreme Court
DecidedMay 17, 1927
Docket5780
StatusPublished
Cited by19 cases

This text of 138 S.E. 324 (State Ex Rel. E. I. Dupont De Nemours & Co. v. Coda) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. E. I. Dupont De Nemours & Co. v. Coda, 138 S.E. 324, 103 W. Va. 676, 1927 W. Va. LEXIS 129 (W. Va. 1927).

Opinion

Lively, Judge:

S. C. Coda and C. A. Nash were partners as road contractors, and were successful bidders before the State Road Commission for the construction of “Seng Creek toward Seth” road, in Boone County, executing to the State a bond in the penalty of $21,800.00 with Aetna Casualty & Surety Company as surety, conditioned for the faithful performance of the contract and for payment of laborers and materialmen. Having signed the contract and bond, Coda and Nash, partners as Coda-Nash Company, a few days later, incorporated as Coda-Nash Company and proceeded to build the road. Upon its completion, the State Road Commission owed it $4,011.06 against which Coda-Nash Company had given orders and assignments to creditors, amounting to $4,010.71, and it is over the distribution of the fund held by the Commission that the litigation arises. The decree directed distribution of the fund to the creditors in the order of dignity and priority ascertained by a commissioner in chancery, from which decree P. J. Riley appeals.

The application for the surety bond contained a provision that should the principal fail to carry out the contract whereby the surety became liable, any balance due from the obligee *679 after completion of tbe contract was assigned to and should be paid to tbe surety to protect it against liability, and after all liability of tbe surety bad been paid, including costs and attorney’s fees incurred, any balance remaining should be paid to Coda and Nash, the applicants for the bond. This application was kept by tbe surety company in its files and the assignment therein was not claimed by it until after this suit was begun. Tbe contract and bond for its performance were entered into Feb. 8, 1923, and tbe road work progressed until about tbe beginning of tbe year 1925. In 1923, tbe Coda-Nash Company purchased explosives from E. I. du Pont de Nemours & Company, on which payments were made leaving a balance due tbe du Pont Co. of $2,637.15 • in Oct. 1923, the corporation owed tbe Standard Oil Company, $137.70 for oils; and during tbe progress of the work became indebted to Hagen, Ratcliff & Co., for $410.53 for groceries used in tbe boarding house to feed tbe laborers on tbe project. In the Spring of 1924, tbe road was nearly completed, but tbe contractor was without funds to pay tbe laborers and applied to appellant P. J. Riley for money for that purpose, promising to pay him out of tbe next estimate allowed by tbe Commission, and when tbe work was completed to give him an assignment of tbe funds due it, if be bad not been paid. Riley advanced $4,000.00, May 19, 1924, and a further sum of $1,200.00, Oct. 14, 1924, all of which went to pay the laborers. Prior to tbe final estimate Riley was paid by order on tbe Commission on funds due tbe Corporation on road work in Logan County (another project) tbe sum of $3,160.00, leaving a balance due him with interest of $2,218.00, for which sum be received an order and assignment on the Commission on Dec. 12, 1924, which was immediately filed with tbe Commission.

Tbe orders and assignments given by Coda-Nash Company against tbe balance of $4,011.06 in tbe bands of tbe Commission, with dates and amounts, are as follows:

Bank of Whitesville.Oct. 28,1924.$ 900.00
P. J. Riley.Dec. 12,1924. 2,218.00
Standard Oil Co.Dec. 22,1924. 137.70
*680 Hagen, Ratcliff & Co Dec. 22,1924. 410.53
E. I. dn Pont & Co.Dee. 23,1924. 334.48
$4,010.71

The du Pont Company began the suit by setting up its account of $2,637.15 against Coda and Nash as partners, and the surety on the bond given by them to protect materialmen, and prayed relief against them and their surety on the bond. The surety company answered in the nature of a cross-bill, bringing in as parties the above named persons holding assignments on the fund in the hands of the Commission, made the Commission a party, alleged tha,t the $4,011.06 was a trust fund in its hands to protect the surety, and that there were conflicting claimants of the fund, the total amount of whose claims was $6,303.73; set up the application of Coda-Nash Company for the surety bond, alleging that thereby it had assigned all funds to become due it from the Commission for the protection of the surety; charged that the attempted assignments later given were without effect and void insofar as the surety was concerned; claimed it was entitled to reasonable attorney’s fees from the fund; charged that the claims of Hagen, Ratcliff & Co., Riley, Standard Oil Co., Bank of Whitesville, and du Pont Co. were not for labor or material furnished on the project; and prayed for an adjudication of the conflicting claims against the fund; and for general relief. The Commission answered that it had $4,011.06 in its hands, and asked for a decree of distribution. Riley answered, denying that Coda and Nash did any work on the road or purchased any material therefor; alleged that Coda and Nash incorporated February 8, 1924, and took over, by assignment from Coda and Nash, the road contract, did the work and purchased materials, and that the fund in the hands of the Commission belonged to Coda-Nash Company, a corporation, subject to its assignments, and did not belong to Coda-Nash Company, a partnership. He charged the inability of the corporation to meet its pay-rolls in 1924, its application to him for money for that purpose, his loan to it, and the contract of repayment out of the moneys due and to become due *681 from the Commission, and his assignment of Dec. 12, 1924. He denied that the $4,011.06 was a trust fund, denied that the fund had been assigned to indemnify the surety under the application for the bond, or if an assignment had thereby been made, such assignment was never filed with the Commission and could not take preference over his (Riley’s) assignment; and prayed for payment of his $2,218.00, by the Commission. Coda and Nash filed separate answers, averring that the corporation purchased materials for the road, and that they were in no way responsible, that the corporation built the road, and that the fund had been rightfully assigned by the corporation. Hagen, Ratcliff & Co. answered, setting up its debt for groceries, charging that it was covered by the surety bond, and payable by the surety, and setting up its assignment of Dec. 22, 1924; and praying for payment out of the fund and from the Coda-Nash Company and the surety on its bond. The Standard Oil Co. answered, claiming its account as material furnished, setting up its assignment of Dec. 22, 1924, and claiming payment from both the fund and the surety on the bond.

A master commissioner took evidence, from which he reported that Coda-Nash Company, a partnership, after it had taken the contract and given the surety bond for performance thereof and payment of laborers and materialmen on February 2, 1923, assigned its contract to Coda-Nash Company, a corporation, claimed to have been formed on February 8, 1923, and that the corporation built the road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No.
Arkansas Attorney General Reports, 2006
Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)
Achen-Gardner, Inc. v. Superior Court
839 P.2d 1093 (Arizona Supreme Court, 1992)
Achen-Gardner, Inc. v. Superior Court
809 P.2d 961 (Court of Appeals of Arizona, 1991)
Cardinal Construction Co. v. Besmec, Inc.
701 F. Supp. 1274 (S.D. West Virginia, 1988)
Logan Planing Mill Co. v. Fidelity & Casualty Co. of New York
212 F. Supp. 906 (S.D. West Virginia, 1962)
Humble Oil & Refining Co. v. United States
40 Cust. Ct. 330 (U.S. Customs Court, 1958)
Armenta v. Churchill
267 P.2d 303 (California Supreme Court, 1954)
Fidelity & Deposit Co. of Maryland v. County Court of Lewis County
15 S.E.2d 302 (West Virginia Supreme Court, 1941)
State Ex Rel. First Huntington National Bank v. State Road Commission
164 S.E. 289 (West Virginia Supreme Court, 1932)
Capon Valley Bank v. State Road Commission
163 S.E. 44 (West Virginia Supreme Court, 1932)
Bowling v. Julian Construction Co.
158 S.E. 165 (West Virginia Supreme Court, 1931)
State Ex Rel. Appaline Oil Co. v. Arthur
146 S.E. 619 (West Virginia Supreme Court, 1929)
Horton v. Tyree
139 S.E. 737 (West Virginia Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
138 S.E. 324, 103 W. Va. 676, 1927 W. Va. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-e-i-dupont-de-nemours-co-v-coda-wva-1927.