This text of 78 N.W. 87 (State ex rel. City of Duluth v. St. Paul & Duluth Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. City of Duluth v. St. Paul & Duluth Railroad, 78 N.W. 87, 75 Minn. 473, 1899 Minn. LEXIS 504 (Mich. 1899).

Opinion

COLLINS, J.

These two appellants and another railway company own 12 tracks, which, at grade and in close proximity, cross, or in part cross, Garfield avenue, in the city of Duluth, an avenue which extends from Superior street southerly along what is well known as Rice’s Point. Some of the tracks are owned by the companies severally, and some are owned jointly. In 1896 a resolution was passed by the city council requiring these three companies to construct a continuous steel bridge or viaduct, with the necessary abutments, from Superior street, over all of the tracks, as laid across the avenue, a distance of 2,375 feet. The companies refused to comply with the resolution, and there was a mandamus proceeding to compel a compliance.

At the hearing, evidence was introduced tending to show that public necessity did not. require the tracks to be bridged at this point, and, further, not only that the plans and specifications attached to and made a part of the alternative writ were too indefinite and uncertain to be a basis upon which to require the construction of a proper bridge or viaduct, but that the structure shown thereby would be unnecessarily extensive and expensive, and in excess of the public demand. The court found as a fact that public necessity and welfare required and made necessary the construction of a steel bridge on the avenue over and across the tracks, and this finding, although challenged by appellants’ counsel, was well supported by the evidence. We need say nothing further on this point. The court then found that a bridge somewhat shorter and narrower than the one proposed was required, and fixed the terminal points therefor.

As a conclusion of law it ordered the issuance of a peremptory writ of mandamus commanding and compelling the companies, naming each, at their own expense, to proceed immediately to construct and complete a steel and iron bridge or viaduct over and across these tracks, with all necessary approaches and appurte[476]*476nances, and in accordance with certain plans and specifications prepared by the court and under its direction; and filed with the findings of fact and order for the issuance of a writ a copy of said plans and specifications, to be made a part of the writ. After an unsuccessful attempt on the part of counsel for appellants St. Paul & Duluth Company and the Northern Pacific Company to secure a modification of the findings and order, said counsel moved for a new trial. This appeal is from an order denying the motion.

1. It is urged by appellants’ counsel that the proceedings should have been dismissed when the court determined that the plans and specifications made a part of the alternative writ were so indefinite and uncertain that nothing could be done thereunder.

This amounts to the contention that the peremptory writ in such a proceeding must conform to the alternative writ, and cannot depart or vary from the latter in its commands as to the length, width, size and character of the structure to be erected, although a trial has been had for the express purpose of determining what kind of a bridge is needed. There is no merit in this contention, for, as was well said in State v. Minneapolis & St. L. Ry. Co., 39 Minn. 219, 39 N. W. 153, “this proceeding is sufficiently elastic to enable the court to determine upon trial the plan which ought to be adopted to accomplish the ends in view.” More than this, in each of the appellants’ answers the kind and character of the needed bridge were put in issue, and the court was asked, if it should find a bridge necessary at this point, to “determine and direct definitely the nature, extent and character of such structure to be built.” The trial court had full power, and it was its duty, to take evidence for the purpose of ascertaining the kind of bridge best suited for the purpose, and, if necessary, to direct that new plans and specifications be prepared for its information and for the guidance of the parties upon whom rested the obligation to build.

2. It follows that there was no error in receiving the testimony of the witness Duffies as to the proper dimensions of a structure to be built by appellants across these tracks. The court could not determine what kind of a bridge was reasonable and necessary without expert evidence, and the defiant attitude of appellants, and their evident purpose to refrain from aiding in any attempt to fur[477]*477nish information upon this branch of the case, compelled the court to rely largely upon the evidence produced by the city.

3. This is true, also, of the claim made by appellants that because Mr. Duffies was in the employ of the city he should not have been appointed special referee to draw plans and specifications for the bridge which the court finally ordered to be built. It is also urged by counsel that the court had no power to appoint such a referee without notice to appellants, but there is nothing in this. The court was not required, even if it had the necessary skill for such work, to prepare the plans and specifications for the kind of bridge it had determined should be built, and it had the right to select any competent person to prepare for it such plans and specifications, just as it had the right to adopt plans and specifications already prepared, if found suitable and satisfactory. While in the order appointing Mr. Duffies he was designated as special referee, he was in no sense a referee, and performed none of the duties of a referee. He was nothing more than an agency employed by the court, because of his special skill and fitness, to prepare a portion of its findings of fact, his appointment being “for the purpose of preparing, under the direction, and for the use, of this court, general plans and specifications and detailed drawings.” So prepared, submitted, and incorporated into the findings, the plans, specifications, detailed drawings, etc., became those of the court itself.

4. But these plans and specifications were never submitted to an inspection or examination in behalf of the appellants, and in several essential particulars they were not justified by any evidence introduced upon the trial. It seems that after the trial the court, by an ex parte order, appointed Mr. Duffies for the work above mentioned, and thereupon he proceeded to examine the locality, to make surveys, and to take soundings for the purpose of preparing suitable plans and specifications for a bridge altogether different in many ways from that specified in the alternative writ; the plans and specifications now involved being the result.

It might be that, if the appellants had been given an opportunity to be heard prior to their adoption by the court, an objection that in some substantial respects they were unwarranted by the evidence would not now be available, because the appellants could [478]*478have there pointed out wherein the evidence had been disregarded or was wanting. And it might be that, if there was no evidence as to matters of mere detail in the work, matters which in nó manner affected the substantial rights of appellants, there would be no ground for complaint simply because they were not given a hearing before plans and specifications in which these details were fully covered were adopted. But such is not the present case. We need not particularize wherein there was no evidence upon which could be based certain material parts of the plans and specifications, — matters of substance, and not mere detail, — for it is unnecessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. City of Seattle v. Northern Pacific Railway Co.
221 P. 991 (Washington Supreme Court, 1924)
City of St. Paul v. Great Northern Railway Co.
163 N.W. 788 (Supreme Court of Minnesota, 1917)
State ex rel. Ise v. Atchison, Topeka & Santa Fe Railway Co.
147 P. 801 (Supreme Court of Kansas, 1915)
State ex rel. Board of County Commissioners v. McKellar
99 N.W. 807 (Supreme Court of Minnesota, 1904)
State ex rel. City of St. Paul v. Minnesota Transfer Railway Co.
50 L.R.A. 656 (Supreme Court of Minnesota, 1900)
State ex rel. City of Duluth v. St. Paul & Duluth Railroad
81 N.W. 544 (Supreme Court of Minnesota, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
78 N.W. 87, 75 Minn. 473, 1899 Minn. LEXIS 504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-city-of-duluth-v-st-paul-duluth-railroad-minn-1899.