State Ex Rel. Cass County v. Public Service Commission

259 S.W.3d 544, 2008 Mo. App. LEXIS 285, 2008 WL 564611
CourtMissouri Court of Appeals
DecidedMarch 4, 2008
DocketWD 67739, WD 67740
StatusPublished
Cited by4 cases

This text of 259 S.W.3d 544 (State Ex Rel. Cass County v. Public Service Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Cass County v. Public Service Commission, 259 S.W.3d 544, 2008 Mo. App. LEXIS 285, 2008 WL 564611 (Mo. Ct. App. 2008).

Opinion

*546 RONALD R. HOLLIGER, Judge.

In this appeal we again consider the consequences of Aquila’s decision to build a multi-million — dollar power plant in Cass County without obtaining either zoning approval from Cass County or prior permission of the Public Service Commission (“PSC”). In Stopaquila.Org v. Aquila, Inc., 180 S.W.3d 24 (Mo.App. W.D. 2005) (hereafter Aquila I), this court affirmed a circuit court injunction requiring Aquila to dismantle that power plant and an accompanying substation (collectively, “the facilities”). We there held that Aquila’s franchise and existing certificates of convenience and necessity (“CCNs”) did not confer the “specific authority” necessary for the facilities to qualify for a zoning exemption under section 64.235. 1 In the absence of such an exemption, Aquila I held that the circuit court correctly found that the facilities violated the zoning laws of Cass County. Id. at 27.

After that decision, Aquila sought belated construction approval from the PSC, presumably in the hope that such approval would relieve it of the injunction’s dismantling order. This appeal comes to us, therefore, from a report and order of the PSC purporting to grant CCNs approving construction and operation of the facilities. 2 We today hold that the PSC lacks statutory authority to grant a post hoc CCN approving construction and that Aquila already had all the authority necessary to operate a power plant (under its pre-existing CCN), rendering the instant report and order a nullity.

Factual and Procedural Background

Our opinion in Aquila I contains a thorough recitation of the events giving rise to the underlying controversy in this case. See 180 S.W.3d at 28-29. After Aquila received the report and order from the PSC, Cass County filed a writ of certiorari or review under section 386.510. The County challenges both the authority of the PSC to grant the CCNs at issue, and the reasonableness of the PSC’s decision to grant them without requiring Aquila to secure local zoning approval for the facilities. Various parties, including Aquila and StopAquila.org (an unincorporated association of area residents opposed to Aquila’s plans hereinafter referred to as “StopAqui-la”), intervened in the writ proceeding and remain parties in the case on appeal.

The circuit court granted the writ, heard argument from all parties, and found that the PSC exceeded its statutory authority in granting the CCNs and that the PSC’s failure to impose a condition requiring local zoning approval was unreasonable. Aquila appeals the judgment entered by the circuit court.

On appeal, the parties urge contradictory interpretations of the final paragraph of our published opinion in Aquila I. That paragraph contains our holding, as well as a reservation marking out the precise boundary between what was decided in that case and what was left for future resolution:

[W]e affirm the circuit court’s judgment permanently enjoining Aquila from building the South Harper plant and Peculiar substation in violation of Cass *547 County’s zoning law without first obtaining approval from the county commission or the Public Service Commission. In so ruling, however, we do not intend to suggest that Aquila is precluded from attempting at this late date to secure the necessary authority that would allow the plant and substation, which have already been built, to continue operating, albeit with whatever conditions are deemed appropriate.

Aquila I, 180 S.W.3d at 41.

The first sentence quoted above affirms the trial court judgment at issue in the factual context of that case for the specific reason that Aquila had failed to obtain approval from the county commission or the PSC. Had the appropriate approval been granted by either of those bodies before Aquila constructed the facilities, section 64.235 would have provided an exemption from the county zoning ordinances at issue. 3 The second sentence makes clear that Aquila I did not address the question now before this court: In the absence of any prior approval for the construction of the facilities, may the PSC grant such approval after the facilities have been constructed? Aquila and the PSC argue that, even after Aquila I, Aquila can still seek and obtain all the approval necessary from the PSC to qualify it for a zoning exemption. Cass County and Sto-pAquila argue that the only authorization that would allow operation of the plant after Aquila I must come in the form of zoning approval, which can only be granted by the county.

Standard of Review

Section 386.510 allows for circuit court review of PSC orders “for the purpose of having the reasonableness or lawfulness of the original order or decision ... determined,” and vests this court with appellate jurisdiction over such suits. Section 386.510. 4

When appeal is taken from a circuit court judgment setting aside an order of the PSC, this court “reviews the decision of the Commission, not the judgment of the circuit court.” State ex rel. City of St. Joseph v. Pub. Serv. Comm’n, 713 S.W.2d 593, 595 (Mo.App. W.D.1986). In conducting this review, “our role is to determine whether the commission’s report and order was lawful, and, if so, whether it was reasonable.” State ex rel. Util. Consumers Council of Mo., Inc. v. Pub. Serv. Comm’n, 585 S.W.2d 41, 47 (Mo. banc 1979). “In determining the statutory authorization for, or lawfulness of, the order we need not defer to the commission, which has no authority to declare or enforce principles of law or equity.” Id. If the actions under review exceed the statutory authority of the PSC, this court need not address the reasonableness thereof. See id.

The PSC’s Statutory Authority

The PSC “is a body of limited jurisdiction and has only such powers as are expressly conferred upon it by the Statutes and powers reasonably incidental thereto.” State ex rel. and to Use of Kan *548 sas City Power & Light Co. v. Buzard, 350 Mo. 763, 168 S.W.2d 1044, 1046 (Mo. banc 1943). “Neither convenience, expediency or necessity are proper matters for consideration in the determination of whether or not an act of the commission is authorized by statute.” State ex rel. Mo. Cable Telecomms. Ass’n v. Mo. Pub. Serv. Comm’n,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
259 S.W.3d 544, 2008 Mo. App. LEXIS 285, 2008 WL 564611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-cass-county-v-public-service-commission-moctapp-2008.