State ex rel. Arpin v. George

142 N.W. 945, 123 Minn. 59, 1913 Minn. LEXIS 365
CourtSupreme Court of Minnesota
DecidedSeptember 19, 1913
DocketNo. 18,333
StatusPublished
Cited by14 cases

This text of 142 N.W. 945 (State ex rel. Arpin v. George) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Arpin v. George, 142 N.W. 945, 123 Minn. 59, 1913 Minn. LEXIS 365 (Mich. 1913).

Opinion

Holt, J.

This is an appeal from an order overruling separate demurrers interposed by the defendant and the intervener to a petition and alternative writ of mandamus. The court below certified that the question presented by the demurrers was important and doubtful.

The main facts disclosed by the petition and writ, and necessary here to state in order to a proper understanding of the controversy, are these: The defendant is the auditor of Beltrami county. In February, 1911, the relators entered into a contract with the counties of Marshall and Beltrami to construct therein judicial ditch No. 12, and gave a proper bond for its performance. The ditch was to be completed by December 1, 1912, but an extension of one year was [61]*61grañted. The estimated cost of the ditch and roadway on its banks was about $70,000. As the work progressed, payments were made to the relators of 75 per cent of the yardage excavated, as provided in the law in force when the contract was made and as therein stipulated. The cost of construction apportioned to Beltrami county was '99.73 per cent and to Marshall county .27 per cent. On June 30, 1913, the engineer in charge of the construction issued to relators and filed with the respective county auditors a certificate conforming to chapter 567 of the Laws of 1913 [p. 835] showing that the contract price exceeded $30,000; that the total amount of constructive work done at the.contract price was $48,892.13; that the total amount of the estimates or certificates theretofore issued to the relators for such work was $36,669.09; that the balances retained by said counties upon the work done amounted to $12,223.04; that 72.3 per cent of the whole construction was complete; that 75 per cent of the balance retained by Marshall county for the work as far as completed was $24.75, and by Beltrami county was $9,142.50; and that in his ■opinion no loss will result from the payment of said sums to relators. The defendant, as auditor of last named county, refused to issue a warrant on the treasurer for the amount specified. The county of Beltrami was permitted to intervene by demurrer over the objection ■of relators that the court had no jurisdiction to hear and determine such demurrer.

The relators insist that their objection was valid and should result in the dismissal of the county’s appeal in this court. The relators are not appealing, hence cannot assail the propriety of the order permitting the intervention. Nor should they now have the appeal dismissed, because that would result in giving them the benefit of a decision on the merits on the assumption that jurisdiction -existed.

Tinder the terms of relators’ contract, and the law in force when it was executed, the auditor’s refusal to issue the warrant was prop-on But the right thereto is claimed under chapter 567, Laws of 1913, which amends the amended section .17 of chapter 230, Laws 1905 [p. 321], the drainage act, so that, as to the existing contracts involving work the total estimates of which exceed $30,000, 75 per [62]*62cent of the one-fourth which, under the contracts and the prior law,, was to be retained by the county out of the estimates given by the-engineer in charge as the work progressed until the full completion* thereof might be paid to the contractors, after 50 per cent of the-excavation was done, and there was no default, provided the engineer in charge gave a certificate stating the facts and that no loss, would result from such payment. In the instant case the certificate-above mentioned issued by the engineer in charge complied with the-law of 1913.

The appellants contend that, as to prior contracts, the act referred to contravenes the constitutional provisions, state and Federal, forbidding impairment of contract obligations; that the classification attempted is arbitrary and invalid; that it is special legislation; and' that the effect upon the contract with relators is to appropriate public funds for private gain. The relators’ position is that the county is not interested in drainage contracts, except as a mere governmental' agency of the state in carrying on the purpose of promoting public-health and welfare; that therefore the state retains full control of the drainage contracts, and may modify those already entered into with the consent of the contractors and sureties, at its pleasure; and' that the legislature has plenary power over the disposition of funds-of counties, therefore the county cannot claim any right to contract obligations, or private interest in the contract, or in ditch funds which need be respected by the legislature.

If the county is a party to relators’ contract in any other capacity than as a governmental agency of the state, or if it owned the fund from which the work done is to be paid, no one could pretend that the legislature had the power to change the terms of this contract without the consent of the county. The act would then be objectionable as an impairment of contract obligations and an interference with vested rights. But we have no doubt that in drainage work, as carried on under our statutes, the county is a mere governmental agency of the state. That the state for such public purpose, or for any legitimate object within its police power, may make use of a county or governmental subdivision, and lay the burden upon it to carry out the project is well settled. State v. Smith, 58 Minn. [63]*6335, 59 N. W. 545, 25 L.R.A. 759; State v. Johnson, 111 Minn. 10, 126 N. W. 480. This being so, the state has at all times the right to direct and control its agent in the performance of the work and in the application of the funds raised therefor. While the county is thus a mere agent in carrying on a governmental function, it does, not admit of doubt that the state may impose upon the county the financial responsibility connected with the exercise of such function. Van Pelt v. Bertilrud, 117 Minn. 50, 134 N. W. 226.

Therefore, as far as existing drainage contracts are concerned, we-conclude that the county has not such an individual or private interest therein that it can object to a modification thereof by the state,, whenever the legislature may deem it advisable in furtherance of the drainage scheme. The state could, in the first instance, have prescribed any terms or conditions in drainage contracts which the lawmaking power deemed proper; and, in achieving the object to be attained by drainage, it ought to be able to modify such contract without the consent of its agent, the county, as it finds best. It has been held that a municipal corporation has no such interest in contracts, or funds, held by it for governmental purposes that it can invoke against, a legislative act affecting such contract or fund the constitutional objection of impairment of contract obligation or interference with, vested rights. Little River v. Reno County, 65 Kan. 9, 68 Pac. 1105. See also, Beach, Public Corp. §§ 722, 723, and Guilder v. Town of Dayton, 22 Minn. 366, as to the control of counties and the-funds held for public purposes.

The serious objection to this act, as to contracts entered prior thereto, is the contention that it bestows a gratuity upon the contractor’ out of public funds, without serving any public purpose and without, there being any moral obligation on the state or county so to do. A county, wherein public drainage is undertaken, is required to provide a ditch fund by the issue and sale of bonds for which the county’s, credit is pledged (Van Pelt v. Bertilrud, supra); and it is also authorized to transfer to this fund any surplus remaining in the general revenue, or other funds of the county which can properly be used-for the purpose of the act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County Department of Public Welfare v. Potthoff
44 N.E.2d 494 (Indiana Supreme Court, 1942)
Lyman v. Chase
226 N.W. 633 (Supreme Court of Minnesota, 1929)
Town of Kinghurst v. International Lumber Co.
219 N.W. 172 (Supreme Court of Minnesota, 1928)
Lausen v. Board of Supervisors
214 N.W. 682 (Supreme Court of Iowa, 1927)
Szroka v. Northwestern Bell Telephone Co.
213 N.W. 557 (Supreme Court of Minnesota, 1927)
State Ex Rel. Hilton v. County of Lincoln
210 N.W. 635 (Supreme Court of Minnesota, 1926)
Schulte v. Fitch
202 N.W. 719 (Supreme Court of Minnesota, 1925)
Williams v. Skelton
224 P. 79 (Idaho Supreme Court, 1924)
Pennington County v. Red Lake Drainage & Conservancy District
192 N.W. 184 (Supreme Court of Minnesota, 1923)
Alden v. County of Todd
167 N.W. 548 (Supreme Court of Minnesota, 1918)
State ex rel. Kohler Contracting Co. v. Hansen
167 N.W. 114 (Supreme Court of Minnesota, 1918)
State ex rel. Tri-State Telephone & Telegraph Co. v. Holm
164 N.W. 989 (Supreme Court of Minnesota, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
142 N.W. 945, 123 Minn. 59, 1913 Minn. LEXIS 365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-arpin-v-george-minn-1913.