State Ex Rel. Alton Railroad v. Public Service Commission

70 S.W.2d 57, 334 Mo. 995, 1934 Mo. LEXIS 516
Supreme Court of Missouri·Decided March 14, 1934·Published·Cited by 15 cases

Opinions

This case, coming to the writer by reassignment, is an appeal by the Alton Railroad Company from the judgment of the Circuit Court of Cole County affirming an order of the Public Service Commission requiring the railroad to contribute to the cost of widening a viaduct. In 1931, Jackson County made application to the commission for an order authorizing the widening of a concrete viaduct, between Kansas City and Independence, where Van *Page 996 Horn Road crosses the railroad's track, and apportioning the cost thereof. The estimated cost of the work was $47,539.80. The answer of the railroad made substantially the same allegations as were made in its answer in State ex rel. Alton Railroad v. Public Service Commission, 334 Mo. 985, 70 S.W.2d 52, decided concurrently herewith.

The viaduct had been built in 1914 pursuant to an order of the Public Service Commission, which apportioned the cost sixty per cent to the railroad and forty per cent to the county. The viaduct was 448 feet long and thirty-four feet wide. The county, as a part of its $10,000,000 road program had rebuilt Van Horn Road, three miles in length connecting Kansas City and Independence, by increasing its width from twenty-five to forty-one feet so that it would accommodate four traffic lanes. The county proposed that the 34-foot viaduct be widened to fifty-two feet so that it would have a roadway forty-two feet wide, sufficient for the four traffic lanes of the highway, and also have 5-foot sidewalks on each side. Its plan for widening it was to build equal additions on both sides, supported by steel encased in concrete, cantilevered from rows of new supporting columns placed on each said of the viaduct.

It was shown that Van Horn Road was expected to be the principal artery between Kansas City and Independence; that it connected with Fifteenth Street, which had been widened to 100 feet all the way to Baltimore Avenue on the west side of the business district of Kansas City; that Van Horn Road also had a 100-foot right of way between the two cities; that the new four-lane paving had been constructed the year before so as to widen and straighten the former narrower road; that it had eliminated many dangerous curves; and that its total cost was about a quarter of a million dollars. It was shown that the entire length of the road was developing as a commercial district; that many stores, offices and other business buildings had already been constructed on both sides of Van Horn Road; that many residential districts were being built up nearby; that 35,000 people lived between the two cities; that the Kansas City school district had purchased a site thereon for a new high school; and that there were other schools already established in the vicinity. A week's traffic check in July, 1931, showed that between ten and twelve thousand automobiles passed daily over the viaduct. There was testimony that "the population in Independence increased from eleven to sixteen thousand in the last census, and the population of Kansas City seventy thousand in the last census. Jackson County, outside of Kansas City and Independence, increased nearly fifty per cent, and with this development that is going to be in there, the increase in the next ten years makes it absolutely essential for a four-lane trafficway to be made on Van Horn Road." The engineers for the county were positive in their statements that the viaduct must be *Page 997 made wide enough to carry four lanes of travel. It was shown that there had been a number of accidents on the viaduct and that automobiles had run against the banisters of the bridge and broken off parts of them.

The evidence for the railroad company showed that its right of way was only 100 feet wide; that the viaduct also crossed a creek which required some kind of a structure over it; that there were no sidewalks on the highway; that few pedestrians used the viaduct; and that, if the road had been built so that the entire width could have been added on one side of the viaduct, instead of on both, the cost would have been only one-half of the proposed expense of widening by building on both sides. The chief engineer of the railroad estimated that it would be possible for ten times the number of cars, indicated by the traffic counts, to pass over the viaduct each day, traveling thirty miles per hour, spaced fifty feet apart and moving in two traffic lanes.

[1] The commission found that the heavy travel required a highway with four lanes of traffic; that the present viaduct would only accommodate three lanes; that the convergence of the lanes in the viaduct created a hazardous condition; and that the safety of the traveling public required that it be widened to conform with the width of the road leading to it. It also found that sidewalks were necessary for the safety of pedestrians and that they could be added more economically in connection with widening the roadway than at a future time. The commission ordered the reconstruction of the viaduct and proportioned the cost twenty per cent to the railroad and eighty per cent to the county and ordered that the county should maintain it. The commission stated that in making this apportionment it took into consideration the facts that the railroad right of way was less than one-fourth of the total length of the viaduct; that the widening of the road had caused increased traffic; that the cost would have been reduced if the road had been built so that the widening could have all been made on one side; and that it had reduced the apportionment of the railroad for these reasons.

This case is similar in some respects to the Noland Street road case, 334 Mo. 985, 70 S.W.2d 52, decided concurrently herewith. The same contentions are made concerning the authority of the Public Service Commission and the violation of constitutional provisions because this is not a grade crossing and upon those points it is ruled by that case. In this case, however, the present viaduct was built in 1914 in compliance with an order of the commission separating the grade. It is the contention of the railroad that this order "finally adjudicated and determined the full and complete liability of the railroad in connection with the separation of the then existing grade crossing on Van Horn Road, and that if the county, for alleged traffic reasons which involves no question of safety, desires a wider viaduct, *Page 998 it should bear the expense thereof, and this commission is without any jurisdiction, power or authority to apportion any of the cost of a wider viaduct, such as proposed by the county, against the railroad."

We cannot believe that the Legislature intended that when the commission makes a grade separation it must decide then and forever what kind of a structure shall be constructed for the use of all future generations, regardless of increases in population or in traffic or changes in other conditions which may develop thereafter. Surely the authority of the commission is not limited to the one act of separation of the grade? Authority to require separation is given by subsection 1, Section 5171, Revised Statutes 1929, but subsection 2 thereof reads as follows:

"The commission shall have the exclusive power to determineand prescribe the manner, including the particular point of crossing, and the terms of installation, operation,maintenance, apportionment of expenses, use and protection

Free access — add to your briefcase to read the full text and ask questions with AI

State Ex Rel. Alton Railroad v. Public Service Commission, 70 S.W.2d 57, 334 Mo. 995, 1934 Mo. LEXIS 516 (Mo. 1934).

70 S.W.2d 57 (State Ex Rel. Alton Railroad v. Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. John Knapp
Court of Criminal Appeals of Tennessee, 1997
State Ex Rel. Kansas City v. Public Service Commission
524 S.W.2d 855 (Supreme Court of Missouri, 1975)
State ex rel. State Highway Commission v. Public Service Commission
471 S.W.2d 249 (Supreme Court of Missouri, 1971)
State ex rel. State Highway Commission v. Public Service Commission
459 S.W.2d 736 (Missouri Court of Appeals, 1970)
Boston & Maine Corp. v. State
261 A.2d 267 (Supreme Court of New Hampshire, 1969)
Southern Railway Co. v. Commonwealth
147 S.E.2d 72 (Supreme Court of Virginia, 1966)
State ex rel. City of Neosho v. Public Service Commission
367 S.W.2d 589 (Supreme Court of Missouri, 1963)
State Ex Rel. State Highway Commission of Missouri v. Conrad
310 S.W.2d 871 (Supreme Court of Missouri, 1958)
State ex rel. Wabash Railroad v. Public Service Commission
273 S.W.2d 334 (Supreme Court of Missouri, 1954)
Jackson County v. Alton R.
105 F.2d 633 (Eighth Circuit, 1939)
State Ex Rel. Wabash Railway Co. v. Public Service Commission
100 S.W.2d 522 (Supreme Court of Missouri, 1936)
State Ex Rel. Alton Railroad v. Public Service Commission
70 S.W.2d 52 (Supreme Court of Missouri, 1934)