State Engineer v. Millard County, Utah

CourtNevada Supreme Court
DecidedFebruary 6, 2015
Docket64815
StatusUnpublished

This text of State Engineer v. Millard County, Utah (State Engineer v. Millard County, Utah) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Engineer v. Millard County, Utah, (Neb. 2015).

Opinion

423, 424-25 (1993), this court recognized that a district court order remanding a decision to an administrative agency without finally resolving the substantive issues before the court was not reviewable on appeal as a final judgment. See also Clark Cnty. Liquor & Gaming Licensing Bd. v. Clark, 102 Nev. 654, 658, 730 P.2d 443, 446 (1986) (concluding that this court lacked jurisdiction to consider an appeal from a district court order remanding a matter to the administrative agency to conduct discovery). Here, the order issued by appellant/cross-respondent Jason King, the Nevada State Engineer, concluded that it would be "premature to attempt to set quantitative standards or triggers for mitigation actions in the Management Plan at this time," while also referencing statements from two witnesses indicating that the need for mitigation should be assessed on a case-by-case or site-by-site basis, Although the district court acknowledged King's conclusions in this regard, it further noted that King had also asserted that appellant/cross-respondent the Southern Nevada Water Authority had presented a great deal of data that provided a basis for making sound decisions on the mitigation issue. As a result, the district court found that, if King "has enough data to make informed decisions, setting standards and 'triggers' is not premature." The court further found, as a corollary, that if King did not have enough data to set mitigation standards, then granting the appropriation was premature. Thus, because King's order declined to set objective standards regarding when mitigation would be required, the district court concluded that that order was incomplete and remanded the matter for resolution of this significant issue.

SUPREME COURT OF NEVADA 2 (0) 1947A Insofar as the district court remanded this matter for the State Engineer to resolve a substantive issue, we conclude that the district court's order of remand was not an appealable, final judgment. See Greenspun, 109 Nev. at 1025, 862 P.2d at 424-25; Clark, 102 Nev. at 658, 730 P.2d at 446. Moreover, as no statute or court rule otherwise provides for an appeal from a district court order such as the one at issue here, see NRAP 3A(b) (listing orders and judgments from which an appeal may be taken); Taylor Constr. Co. v. Hilton Hotels Corp., 100 Nev. 207, 209, 678 P.2d 1152, 1153 (1984) (noting that this court has jurisdiction to consider an appeal only when the appeal is authorized by statute or court rule); see also Clark, 102 Nev. at 658, 730 P.2d at 446, we lack jurisdiction to consider this appeal, and therefore order the appeal dismissed. It is so ORDERED.

J. Parraguirre

Gibbons

SUPREME COURT OF NEVADA 3 (0) 1947A es. PICKERING, J., dissenting: The majority concludes that we lack jurisdiction because the district court's order was not a final, appealable judgment. But the order, taken together with the State Engineer's findings, demonstrates that the district court's decision was substantively final as to the core issue presented: Does substantial evidence support the State Engineer's decision to grant Southern Nevada Water Authority's (SNWA) applications under NRS 533.370? The district court found in the negative on that issue and its finding depends on its legal determination as to the underlying law. The district court's order may on its surface indicate that the district court remanded the matter for the State Engineer to consider evidence it failed to consider, rendering the order not "final." See State Taxicab Auth. v. Greenspun, 109 Nev. 1022, 1024, 862 P.2d 423, 424 (1993) (order reversing agency's decision and remanding for the agency to consider evidence it wrongfully refused to consider was not a final judgment). On the last page of the order, the district court stated it would not disturb the State Engineer's findings "save those findings that are the subject of this Order," and "remanded" for the State Engineer to complete four tasks: 1. The addition of Millard and Juab counties, Utah in the mitigation plan so far as water basins in Utah are affected by pumping of water from Spring Valley Basin, Nevada; 2. A recalculation of water available for appropriation from Spring Valley assuring that the basin will reach equilibrium between discharge and recharge in a reasonable time; SUPREME COURT OF NEVADA

(0) 1947A 74049 3. Define standards, thresholds or triggers so that mitigation of unreasonable effects from pumping of water are neither arbitrary nor capricious in Spring Valley, Cave Valley, Dry Lake Valley and Delamar Valley, and; 4. Recalculate the appropriations from Cave Valley, Dry Lake and Delamar Valley to avoid overappropriations or conflicts with down- gradient, existing water rights. The majority focuses upon the third directive—that the State Engineer must set objective standards, thresholds or triggers for when mitigation must occur, and holds that this substantive matter was therefore remanded to the State Engineer to resolve. Majority at 2. As to this third directive, the State Engineer expressly found that he did not have sufficient evidence to achieve it at the time he granted the applications; rather, the State Engineer instead required SNWA to conduct staged pumping, which he reasoned would allow the interested parties to develop the specifics of any mitigation that may be required to counteract any effects that are environmentally unsound or that would conflict with existing rights under NRS 533.370(2). And, as the majority recognizes, the district court found that if the State Engineer "did not have enough data to set mitigation standards, then granting the appropriation was premature." Majority at 2. It was because of the prematurity of this grant that the district court also stated that "this matter must be remanded to the State Engineer until objective standards can be established and stated–as to when mitigation must occur." Therefore, the district court's order held, in effect, that based upon the evidence SNWA presented it, the State Engineer did not have sufficient evidence to grant the applications. The district court's instructions as to how the State Engineer might attempt to make up this factual SUPREME COURT OF

NEVADA 2 (0) 1917A 4e)x) insufficiency, or to allow the State Engineer to somehow hold the applications until such evidence materialized, does not change the holding that at the time the State Engineer made his decision it was not, in the district court's view, supported by substantial, legally sufficient evidence. As to the second instruction, the district court's express holding that substantial evidence did not support the State Engineer's finding that SNWA's Spring Valley appropriations were not against the public interest effectively decided the issue: under NRS 533.370(2), the State Engineer shall reject an application where "its proposed use or change . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Forest Legacy v. Sherman
646 F.3d 1161 (Ninth Circuit, 2011)
Clark County Liquor & Gaming Licensing Board v. Clark
730 P.2d 443 (Nevada Supreme Court, 1986)
State, Taxicab Authority v. Greenspun
862 P.2d 423 (Nevada Supreme Court, 1993)
TAYLOR CONSTRUCTION CO. v. Hilton Hotels Corp.
678 P.2d 1152 (Nevada Supreme Court, 1984)
State v. Morros
766 P.2d 263 (Nevada Supreme Court, 1988)
BALLY'S GRAND HOTEL & CASINO v. Reeves
929 P.2d 936 (Nevada Supreme Court, 1996)
Office of the State Engineer v. Morris
819 P.2d 203 (Nevada Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
State Engineer v. Millard County, Utah, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-engineer-v-millard-county-utah-nev-2015.