State, Department of Highways v. Dugas & LeBlanc, Ltd.

327 So. 2d 594, 1976 La. App. LEXIS 4032
CourtLouisiana Court of Appeal
DecidedJanuary 12, 1976
DocketNo. 10521
StatusPublished
Cited by1 cases

This text of 327 So. 2d 594 (State, Department of Highways v. Dugas & LeBlanc, Ltd.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State, Department of Highways v. Dugas & LeBlanc, Ltd., 327 So. 2d 594, 1976 La. App. LEXIS 4032 (La. Ct. App. 1976).

Opinion

BARNETTE, Judge.

This is a proceeding initiated by the State of Louisiana, through the Department of Highways, for the expropriation of 3.75 acres of land for highway purposes. Upon taking the land in question the Highway Department deposited in the registry of the court the sum of $2,813 as just compensation, computed at $750 per acre. There is no serious contention that this amount was not a fair appraisal of the actual land value, but the defendants claim substantial severance damage for which they seek reimbursement.

Three expert appraisers testified at the trial and their estimates of the land value ranged from $750 per acre, by the Highway Department’s expert, to $800 and $950 respectively, by the defendant’s two experts.

Estimates of severance damage, ranged from none by the Department’s expert to $26,800 and $29,550 by the defendant’s two expert appraisers and $25,000 by one of the defendant co-owners. The trial court accepted the lowest of the appraisals, namely $750 per acre, or $2,813 for the 3.75 acres taken and $25,000 for the severance damage. Fees for each of the two expert witnesses for defendants were fixed at $1,000 and taxed as costs. Judgment was rendered accordingly.

The Department of Highways appealed seeking a reversal of that portion of the judgment which awarded severance damage.

Counsel for defendants-appellees states in his brief before this court that in answer to the appeal, defendants “ask for increase in the amount of just compensation and damages allowed by the trial court.” We find no answer to the appeal in the record before us and will not consider the request for an increase. Alternatively, defendants seek an affirmance of the judgment of the trial court.

The taking of the property in question, July 27, 1972, was for right-of-way for State Highway Route 70 in Assumption Parish, between Paincourtville and the Sunshine Bridge. Prior to this taking the Highway Department had purchased in [596]*596April, 1971, from these defendants, a strip of land 300 feet wide (with an additional SO feet on each side as temporary construction servitude) for State Highway Route 70, almost entirely across the defendant’s property known as Halfway Plantation. Present plans call for a two-lane highway to be constructed on one side of the right-of-way, leaving sufficient space for possible future conversion to a four-lane highway.

The right-of-way acquired by purchase, comprising approximately 50 acres, began at the southern property line of Halfway Plantation and extended in a north-northeasterly direction a distance of approximately 5,000 feet stopping some 300 feet short of the northern property line of Halfway Plantation. The failure to acquire a right-of-way completely across the defendant’s property was the result of an error with respect to the exact northern property line of Halfway Plantation and the extent of the defendant’s ownership. It then became necessary for the Highway Department to acquire the additional approximate 300 feet of right-of-way to completely traverse the defendant’s property, plus a small amount of land on each side of the extended right-of-way for drainage purposes, all of which totaled 3.75 acres and is the subject property of this proceeding.

Prior to the taking in question the Halfway Plantation comprised approximately 1,384 acres, which included the small parcel lying between the end of the purchased right-of-way and the northern boundary line of the plantation. After the taking of the 3.75 acres the defendants had two tracts remaining consisting of 986 acres on the west side and 394 acres on the east side of the right-of-way. That remaining on the east side included about 200 acres of woodland, leaving about 194 acres suitable for sugar cane cultivation.

Prior to the taking of the 3.75 acres in question, but after the purchase of the 5,000 feet of right-of-way, the east and west tracts were physically connected at the northern end of the purchased right-of-way. The taking of this parcel resulted in a complete severance of the defendant’s sugar cane plantation.

The defendants contend that the complete severance of their plantation by the extension of the right-of-way to their northern boundary has substantially damaged the now remaining two separate tracts of land. They contend among other things, that the smaller tract left on the east side is. now without facilities necessary for operation of a sugar plantation, and that the relatively small amount of land left suitable for sugar cane cultivation is too small to justify the expense of providing separate facilities, such as derricks and loading equipment, implement sheds, etc. They point out that all such facilities are provided on the west side of the right-of-way and are virtually inaccessable to the east side. The crossing of the highway, with tractors, cane trucks and other cumbersome equipment which would be subject to Highway Department limitations and restrictions for traffic control including the prohibition of tracking mud on the highway, portends many hazards, much inconvenience and loss of time.

We agree that these are obvious factors to be considered as materially affecting the practical and efficient operation of the two tracts of land as a single plantation unit. These factors would be considered as relevant to severance damage if it is shown that they adversely affect the land remaining after the taking. However, in view of the rationale of this opinion and the conclusion we have reached, it is not necessary for us to consider that question.

At the beginning of the trial of this case in the District Court, counsel for the Department of Highways made an opening statement in which he related for the Court’s information the events leading up to the expropriation of the 3.75 acres in question, in substance as we have stated above. Counsel for the defendants object[597]*597ed to any reference to the prior negotiations for and purchase of the right-of-way alluded to. He acknowledged that what plaintiff's counsel had said was "basically . . . correct” but argued that it had no relevance to the issues then before the court. Counsel for plaintiff argued that “a central issue in this case will be whether the defendants actually believed the road was going to stop 300 feet from the end of their property . . .” and whether or not they intended to sell the entire, [right-of-way] from one boundary to the other.” The court ruled: “We will cross that bridge' when we come to it.”

After plaintiff’s first witness was called and qualified as an appraisal expert and began to testify, counsel for defendants again objected to any questions or testimony tending to change or alter the deed by which the Highway Department had acquired the 5,000 feet of right-of-way. His objection was based on the parol evidence rule, citing Civil Code Article 2276 and pertinent cases. Plaintiff’s counsel argued that it was not his intention to contradict or vary the terms of the deed but rather to show that the defendants thought they were conveying a right-of-way completely across their plantation, causing a severance into two parts, for which they now seek further compensation.

The court’s ruling was in substance that it was not concerned with what had transpired between the parties in the past and would hear no testimony on that, and would hear and consider only the issues of expropriation, the just compensation and severance damages for the taking of the 3.75 acres in question.

Near the conclusion of the trial the plaintiff recalled its first witness, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State, Department of Highways v. Dugas & Leblanc, Ltd.
329 So. 2d 430 (Supreme Court of Louisiana, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
327 So. 2d 594, 1976 La. App. LEXIS 4032, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-department-of-highways-v-dugas-leblanc-ltd-lactapp-1976.