Starr v. J. Abrams Construction Co.

448 N.E.2d 1311, 16 Mass. App. Ct. 74, 1983 Mass. App. LEXIS 1342
CourtMassachusetts Appeals Court
DecidedMay 23, 1983
StatusPublished
Cited by8 cases

This text of 448 N.E.2d 1311 (Starr v. J. Abrams Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Starr v. J. Abrams Construction Co., 448 N.E.2d 1311, 16 Mass. App. Ct. 74, 1983 Mass. App. LEXIS 1342 (Mass. Ct. App. 1983).

Opinion

Greaney, J.

We deal here with an arbitration award of $66,856 on an oral side agreement to a written contract. Under the written contract, the appellee, J. Abrams Construction Co., Inc. (Abrams Construction), had undertaken to build a nursing home for the appellant, Lorraine Starr. In separate actions filed in the Superior Court, Abrams Construction moved to confirm the award of the arbitration panel, see G. L. c. 251, §§ 11 & 15, which, without making findings of fact, granted the full amount Abrams Construction had sought under the side agreement; Starr moved, pursuant to G. L. c. 251, §§ 12(c) (3) & 15, to vacate the [75]*75award. Abrams Construction’s motion to confirm was allowed; Starr’s motion to vacate was denied. Separate judgments reflecting these orders were entered. The cases are consolidated here.

The oral agreement essentially called for Starr to pay for anticipated costs of completing work on the nursing home in excess of the $1,710,000 contract price. The mortgage on the home is insured by the Federal Housing Administration (FHA). Starr asserts that enforcement of the agreement exceeds the powers of the arbitrators because the agreement is against public policy. This claim rests on the assertion that Abrams Construction made a false statement which had the effect of representing to the FHA that the project would be built for the contract price, thereby inducing FHA financing arrangements predicated on that figure, although the company’s principals were aware that the contract sum would be insufficient to complete the desired facility. This course of conduct, it is asserted, violates 18 U.S.C. § 1010 (1976)1 and G. L. c. 266, §§ 30, 33 & 34,2 and the Federal regulatory scheme underlying FHA financing commitments. It is contended that enforcement of the side agreement would condone this illegal conduct and violate public policy.

There was evidence before the arbitrators from which they could have concluded the following facts. The $1,710,000 [76]*76construction cost figure was reached at an August 8, 1975, meeting of Julius Abrams, president of Abrams Construction, Larry Smith and Henry Fitzgerald. Smith was the developer hired by Starr to handle the design, construction and financing of the project. Fitzgerald was the project’s architect. At an October 6, 1975, meeting, which was likewise attended by Abrams, Smith and Fitzgerald, there was a discussion of changes which would have the net effect of adding some $50,000 to the cost. Smith told Abrams that the $1,710,000 figure had been established as the basis of financing arrangements with the FHA and that the figure was “sacred” and untouchable. Everyone agreed that an attempt would be made to do the job for that amount, but that if the net effect of changes, deletions and items which had not previously been figured into the computation forced the cost over $1,710,000 the excess would be paid by the owner. Starr attended a meeting on October 14,1975, with these same individuals. It was agreed at the meeting that after the job was completed Abrams would calculate the value of any work which exceeded the “sacred” amount, and Starr would give Abrams Construction notes (on rather indefinite payment terms) for the appropriate sum at no interest. Starr also attended meetings on December 19, 1975, and June 9, 1976, at which this payment plan was confirmed. Throughout this period (and indeed up until construction began) the plans and specifications for the nursing home were in constant flux as was the estimate of the cost overrun, a situation not unusual in private sector construction. Despite this, a construction contract was signed on November 10, 1975, in order to lock in a favorable sales tax rate and to exempt the project from new safety regulations scheduled to become effective in 1976.3 The contract recited [77]*77the $1,710,000 cost figure. Construction began on June 14, 1976, approximately two months prior to the FHA closing.

Starr’s allegations of illegality focus on FHA form no. 2328, which was executed by Abrams for Abrams Construction on March 31, 1976, and by Starr as mortgagor on April 5, 1976. That form is headed “Contractor’s and/or Mortgagor’s Cost Breakdown,” and it contains the following inscription: “This form represents the Contractors [sic] and/or Mortgagors [sic] firm costs and services as a basis for disbursing dollar amounts when insured advances are requested.” On the form, construction costs are broken down by category. The total cost reported was $1,710,000. It is not disputed that at all times, from and including the dates on which the form was signed, cost overruns of varying proportions were projected and that at the time of the final requisition for payment, which was based on the form no. 2328 figures, the amount of the overrun had crystallized at $66,582. Yet at no time was any attempt made to amend the original contract figure of $1,710,000 which was used in the completion of all official FHA documents, including the final requisition. Abrams testified that revision of the “sacred” figure was rejected because everyone involved knew that such a revision would result in having to start the project over again “from stage one.” The decision to handle the extra costs outside of FHA channels was made, he said, in order to allow the project, already in gestation for a number of years, to proceed apace. As previously indicated, Starr asserts that this conduct violated 18 U.S.C. § 1010 (1976) (see note 1, supra), which punishes those who knowingly make false statements for the purpose of obtaining a loan to be insured by the Department of Housing and Urban Development (of which the FHA is a part) or for the purpose of influencing that department in any way. A violation of State criminal statutes punishing larceny by false pretenses, G. L. c. 266, §§ 30, 33 & 34, is also alleged.

[78]*78It is not contended that the agreement to pay for the overrun is illegal, per se, nor do we think it could be. We are aware of no law which expressly forbids the performance of a contract to pay for construction costs which exceed the figure used as a basis for obtaining financing, federally insured or not. The issue, therefore, is whether the failure to disclose the oral side agreement to the FHA is so repugnant to public policy that a court should add to any potential liability under criminal statutes4 the additional sanction of vacating an arbitration award which enforces the agreement. Assuming, without deciding, that the nondisclosure was illegal and, a fortiori, a violation of public policy, we conclude, with some hesitation, that the decision in Town Planning & Engr. Associates v. Amesbury Specialty Co., 369 Mass. 737, 746 (1976), causes us to enforce the arbitrators’ award.

There is a rule that “[arbitration . . . may not ‘award relief of a nature which offends public policy or which directs or requires a result contrary to express statutory provision.’” Lawrence v. Falzarano, 380 Mass. 18, 28 (1980), quoting Eager, The Arbitration Contract and Proceedings § 121(6), at 316 (1971). That rule, however, is subject to the recognized qualification that “an award of arbitrators is valid and sustainable if there may be a lawful compliance therewith on any rational basis.” Eager, supra at 316.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frishman v. Maginn
912 N.E.2d 468 (Massachusetts Appeals Court, 2009)
ENTERTAINMENT PUBLICATIONS, INC. v. Goodman
67 F. Supp. 2d 15 (D. Massachusetts, 1999)
Fedenyszen v. Pollano
1997 Mass. App. Div. 97 (Mass. Dist. Ct., App. Div., 1997)
Hastings Associates, Inc. v. Local 369 Building Fund, Inc.
675 N.E.2d 403 (Massachusetts Appeals Court, 1997)
Baybank v. Dirico
1996 Mass. App. Div. 30 (Mass. Dist. Ct., App. Div., 1996)
In Re Sanborn, Inc.
181 B.R. 683 (D. Massachusetts, 1995)
Fillion v. Cardinal
1994 Mass. App. Div. 49 (Mass. Dist. Ct., App. Div., 1994)

Cite This Page — Counsel Stack

Bluebook (online)
448 N.E.2d 1311, 16 Mass. App. Ct. 74, 1983 Mass. App. LEXIS 1342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/starr-v-j-abrams-construction-co-massappct-1983.