Starlink Logistics, Inc. v. ACC, LLC

494 S.W.3d 659, 2016 WL 2726333, 2016 Tenn. LEXIS 317
CourtTennessee Supreme Court
DecidedMay 9, 2016
DocketM2014-00368-SC-R11-CV
StatusPublished
Cited by26 cases

This text of 494 S.W.3d 659 (Starlink Logistics, Inc. v. ACC, LLC) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Starlink Logistics, Inc. v. ACC, LLC, 494 S.W.3d 659, 2016 WL 2726333, 2016 Tenn. LEXIS 317 (Tenn. 2016).

Opinion

OPINION

SHARON G. LEE, C.J.,

delivered the opinion of the Court, in which

CORNELIA A, CLARK, JEFFREY S. BIVINS, and HOLLY KIRBY, JJ., joined.

After its closure, a Class II landfill continued to discharge contaminants into a creek that flowed into a lake located on adjoining property. Following years of investigations and multiple failed remedial measures, the landfill owner and the state agency with authority to direct landfill cleanup. operations agreed that the most feasible, practical, and effective way to *661 abate the discharge was for the landfill owner to divert water from entering the landfill and, over a four-year period, to remove and relocate the landfill waste. The neighboring landowner of the properly on which the lake affected by the discharge was located objected to the plan, arguing that the landfill owner should also be required to treat or divert water leaving the landfill site. The Tennessee Solid Waste Disposal Control Board (“the Board”) heard the case and approved the landowner’s plan of action and did not require diversion-of the water leaving the landfill. The neighboring landowner appealed, and the trial court affirmed the Board’s decision. The Court of Appeals,. dissatisfied with the ruling, remanded the case to the Board to take additional proof on whether the neighboring landowner was willing to pay for the costs of diverting the discharge, the costs of implementing the diversion option, and the landfill owner’s ability to pay for the diversion plan. -We granted the Board’s application for permission to appeal. We hold that the Court of Appeals failed to properly apply the judicial review provisions of Tennessee Code Annotated section 4-5-322(h) (2011) and substituted its judgment for that of the Board. The judgment of the Court of Appeals is reversed.

I.

In 1981, the Tennessee Department of Environment and Conservation (“TDEC”) issued ACC, LCC (“ACC”) a permit to construct and operate a Class II landfill in Maury County. 1 The landfill was located on approximately fourteen acres of the 48.02 acre parcel owned by ACC. ACC disposed of aluminum recycling wastes from Smelter Service Corporation’s local aluminum smelting plant. The waste consisted almost exclusively of bag-house dusts and “salt cake” slag. The salt cake slag contained high concentrations of highly soluble sodium chloride and potassium chloride. ACC operated the landfill from 1981 to 1993. In July 1995, ACC submitted a certification of completion of closure to TDEC, and.in April 1996, TDEC issued an acceptance of closure to ACC.

TDEC and ACC learned, within a few years of when the landfill became operational, that high levels of chlorides and ammonia were being discharged from the landfill!'into groundwater and surface water that drained into Sugar Creek and Arrow Lake. The leaching of chloride and ammonia continued after the landfill’s closure and caused areas west of the landfill, including Sugar Creek and Arrow Lake, to become polluted. ACC worked with TDEC to identify and remedy the leaching. ACC performed extensive investigative efforts to determine the cause of the leaching and performed multiple remedial measures but was unsuccessful in abating the pollution. 2 In December 2003, at *662 TDEC’s request, ACC submitted a Corrective Action Plan (“the Plan”) that evaluated available data, described the limitations of available options due to the site conditions, and identified three remaining options to mitigate the release of contaminated leachate from the landfill: clean closure/waste removal, leachate collection/treatment, and natural or enhanced site attenuation. The Plan presented an assessment of the feasibility and potential effectiveness of these options and concluded that a remedy that fulfilled all criteria in Tennessee Compilation of Rules and Regulations Chapter 1200-1-7-.04(7)(a)8(ii) 3 within two to three years was not technically and economically practical. After a January 2004 public meeting, TDEC approved ACC’s plan to build a wetlands system downgradient of the site to retain and buffer leachate and improve water quality and habitat. The wetlands system was constructed but was not successful.

In ■ June 2008, TDEC requested that .ACC submit a modified plan because the rate of discharge of contaminants from groundwater was increasing. In August 2008, ACC submitted a modified plan (“the Modified Plan”) that TDEC approved in April 2010. The Modified Plan acknowledged that the discharge problem stemmed from a failure to accurately characterize the landfill’s hydrogeology features during the permitting and development-process, identified options for reducing the release of chlorides from the landfill and for removal of the contaminated material, and provided a strategy and schedule to evaluate, select, and implement ways to address the contaminated discharge. The first step was a preliminary evaluation of potential corrective action options, followed by a report to TDEC that would identity options as not feasible or potentially feasible, provide additional information for a more complete evaluation of potentially feasible options, and describe the field investigations or other efforts necessary to gather the additional information.

Under the Modified Plan, ACC submitted a preliminary report to TDEC in August 2010, detailing ACC’s efforts since April 2010. The report requested that TDEC clarify its corrective action goals, summarized current site conditions, identified corrective action alternatives, summarized planned additional data gathering efforts to evaluate the feasibility of remaining alternatives, described the future corrective action plans, and recommended a meeting to discuss prioritization and timing of additional necessary efforts.

*663 In January 2011, representatives of ACC and TDEC’s Divisions of Solid Waste Management and Water Pollution Control met to discuss the necessary level of contaminant reduction for Sugar Creek. ACC discussed the potential remedy of removing the waste from the landfill and planned to do test excavations of waste material to assess the feasibility of the remedy.

In February 2011, TDEC personnel inspected the landfill and took water samples at points along Sugar Creek that confirmed that discharge from the landfill caused high levels of chlorides, ammonia, and dissolved solids in Sugar Creek downstream of the landfill.

In June 2011, ACC and TDEC entered into an administrative consent order stating that the release of contaminated discharge from the landfill constituted violations of the Water Quality Control Act of 1977, TenmCode Ann. §§ 69-3-101 to -148 (2011), and the Tennessee Solid Waste Disposal Act, TenmCode Ann. §§ 68-211-101 to -124 (2011). The proposed order provided for remedial actions to address the continuing discharge • from the landfill. ACC agreed to submit a discharge reduction plan to significantly reduce the amount of contamination flowing from the landfill site in surface water and to develop and implement a plan to effectively and permanently prevent the release of landfill waste to the groundwater.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Madison County, Tennessee v. Vatisha Evans-Barken
Court of Appeals of Tennessee, 2026
Betty Malia Bryant v. Shelby County Government
Court of Appeals of Tennessee, 2025
City of Memphis v. Beverly Prye
Court of Appeals of Tennessee, 2022
Shahnaz Poursaied v. Tennessee Board of Nursing
Court of Appeals of Tennessee, 2021
In re: Loring Justice
Sixth Circuit, 2021
John Garcia v. Shelby County Sheriff's Office
Court of Appeals of Tennessee, 2020
In Re: Cumberland Bail Bonding
Tennessee Supreme Court, 2020
Penney Mosley v. City of Memphis
Court of Appeals of Tennessee, 2019
Andres Perez v. Tennessee Board of Medical Examiners
Court of Appeals of Tennessee, 2019

Cite This Page — Counsel Stack

Bluebook (online)
494 S.W.3d 659, 2016 WL 2726333, 2016 Tenn. LEXIS 317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/starlink-logistics-inc-v-acc-llc-tenn-2016.