Stark v. Shell Oil Co.

312 F. Supp. 145, 1970 U.S. Dist. LEXIS 11785
CourtDistrict Court, N.D. Mississippi
DecidedMay 8, 1970
DocketNo. WC 6831-S
StatusPublished

This text of 312 F. Supp. 145 (Stark v. Shell Oil Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stark v. Shell Oil Co., 312 F. Supp. 145, 1970 U.S. Dist. LEXIS 11785 (N.D. Miss. 1970).

Opinion

[147]*147OPINION

ORMA R. SMITH, District Judge.

This case has been tried to the Court without a jury and is submitted for decision on the record, the evidence received at the hearing, including the depositions introduced, and briefs of counsel.

The Court, after having given due consideration to all issues involved, adopts the findings of fact and conclusions of law which follow:

FINDINGS OF FACT

Plaintiff Charles E. Stark on August 28, 1967, an employee of Otis Engineering Corporation, was assigned by his employer to perform the duties of a wire-line operator on the top deck of an offshore production oil platform of defendant Shell Oil Company, situated cf. the Louisiana Coast in the Gulf of Mexico. While engaged in the work to which he was assigned plaintiff was injured when struck in the back by a pipe which was being moved from the top to the lower deck of the offshore platform by defendant, by the use of a crane.

The platform was the property of defendant and a production operation was being conducted there. The platform has two decks, referred to herein as the “top deck” and the “lower deck.” The lower deck is 210 feet long, running north and south, and 110 feet wide, running east and west. The top deck is elevated above the center of the lower deck and is 70 feet wide, east and west, and 50 feet long, north and south. Thus, the lower deck extends some distance north and south and a shorter distance east and west from the outside edges of the top deck.

The crane involved in the case is a thirty-ton crane, with an 80' boom and a large steel cable to which is attached a hook which is used to pick up a cradle or saddle holding objects being moved, in this case, steel pipe. The crane was situated on the west edge of the top deck and the pipe involved, which was being moved from the top deck to the north side of the lower deck, was lying in a pile on the west side of the top deck north of the crane. Before the pipe was picked up by the crane, its boom extended northward.

The crane is so arranged that a seat is provided for the operator, and it is from this point that the crane is placed in operation. The operator commands a full and unobstructed view over the entire floor of the top deck and most of the lower deck outside the portion situated under the top deck.

Within easy reaching distance of the operator’s seat is located a button cf. switch to be used in blowing the horn on the crane. The horn gives notice to all persons situated near the crane that the crane is being or is about to be placed in operation.

The operator is assisted in the operation of the crane by a swamper, who arranges for the loading of the cradle or saddle, which he attaches to a hook on the cable. The swamper works under the orders of the crane operator, and when instructed so to do the swamper will give warning to those on the top deck who appear to be in the line of travel of the craned

At the time of the occurrence involved herein, plaintiff was working with his helper in approximately the center of the top deck, or about 35 feet from the west and east sides and 25 feet from the north and south sides thereof. He was bending over slightly, though with his head erect, pouring solvent from a barrel. His helper was several feet away.

As plaintiff was performing this task, the crane operator initiated the movement whereby several lengths of steel pipe on the top deck would be transferred to a point on the north side of the lower deck.

The pipe was to be picked up 25 or 30, feet north of the base of the crane and moved directly north to the lower deck. The best course to pursue in accomplishing this movement was to pick up the pipe and move it directly north to the lower deck. By such a movement, plaintiff would not have been in or near the [148]*148movement of the pipe. There was nothing to prevent the crane operator from following this course. Instead of selecting this course the operator carried the pipe in a circular or swinging manner so as to swing the load out over the deck where plaintiff was engaged in his work. Having full view of the scene, the operator did not cause the horn to be blown and did not instruct the swamper to give notice to those working on the top deck, including the plaintiff, of the approach of the pipe as it swung out over the deck, and such warning was not given. As the pipe swung around and over the deck it struck plaintiff in the back and on the back of the head, knocking him down to the floor of the deck.

Plaintiff knew of the existence of the crane and that it would be engaged in moving the pipe from the top to the lower deck, but he relied upon defendant to give warning of any movement of pipe that would move close enough so as to endanger him. At the time the pipe struck him, plaintiff was not facing the crane and did not observe its movement.

The work which plaintiff was performing was done under the direction of defendant, and required plaintiff to work with the wells on the platform. The work necessarily demanded his undivided attention. It was not feasible for plaintiff to keep a constant lookout for the crane and properly perform his work. It is reasonable to determine that notice of some kind should have been given to plaintiff when the crane commenced its operation and movement, in such manner as to bring plaintiff within its path.

The accident occurred early in the morning on the date above indicated. Plaintiff continued to work for several hours, before going ashore to his home. Plaintiff’s back was bruised and injured and he began to suffer pain in his back and right knee.

On the third day after his injury, plaintiff went to the company doctor at Harvey, Louisiana, Dr. Vincent V. Tumminello. After examining plaintiff Dr. Tumminello prescribed muscle relaxant drugs and heat treatments for him. Plaintiff was treated on three other occasions by Dr. Tumminello, when he had the same complaints as on the initial visit and the treatment originally prescribed was continued. On one visit a small lumbar corset was prescribed. Dr. Tumminello saw plaintiff the last time on September 11, 1967, at which time he referred him to Dr. Russell Grunsten, an orthopedic surgeon in New Orleans, Louisiana, for examination and treatment. Dr. Tumminello expressed the opinion that plaintiff was able to return to his usual work within seven to ten days of his injury, and that he had not suffered any permanent disability from the injury.

Plaintiff was examined by Dr. Grunsten on September 15, 1967. Dr. Grunsten also reviewed the x-rays taken of plaintiff’s lumbar spine by Dr. Tumminello. Dr. Grunsten expressed the opinion that plaintiff had suffered a direct contusion type of injury to the low back from the accident, but could not find objective evidence of nerve root irritation or mechanical interference in the mobility of the back area. Dr. Grunsten thought that plaintiff could well return to his normal working activity.

Plaintiff returned to work on September 3, 1967, and worked until September 6, 1967, since which time he has not performed any duties connected with his previous employment, and has not otherwise followed a gainful occupation.

During the period January 1, 1967 through September 6, 1967, plaintiff earned the sum of $6,493.60, or approximately $166.00 per week. At this rate his yearly earning capacity would be approximately $8,000.00, taking into consideration time cf. periods during the year.

After his visit to Dr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Rodrigue v. Aetna Casualty & Surety Co.
395 U.S. 352 (Supreme Court, 1969)
L. C. Haynes v. Rederi A/s Aladdin
362 F.2d 345 (Fifth Circuit, 1966)
Brown v. Liberty Mutual Insurance Company
101 So. 2d 696 (Supreme Court of Louisiana, 1958)
Fossier v. D. H. Holmes Co.
139 So. 709 (Louisiana Court of Appeal, 1932)
Donovan v. New Orleans Ry. & Light Co.
61 So. 216 (Supreme Court of Louisiana, 1913)
Guidroz v. Travelers Insurance Co.
99 So. 2d 916 (Louisiana Court of Appeal, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
312 F. Supp. 145, 1970 U.S. Dist. LEXIS 11785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stark-v-shell-oil-co-msnd-1970.