Stantec Consulting Services Inc. v. Kiewitt Louisiana Co.

Louisiana Court of Appeal·Decided December 30, 2025·No. 2025 CA 0536·Unknown

Opinion

STATE OF LOUISIANA

A# ffi W."

I 9 il WA

FIRST CIRCUIT

NO. 2025 CA 0536

STANTEC CONSULTING SERVICES INC.

V& A CONSULTING ENGINEERS, INC., vis AND PATTERSON PUMP COMPANY

CO VERSUS

KIEWIT LOUISIANA CO., M.R. PITTMAN GROUP, L.L.C., AND TRAYLOR BROS., INC., JOINT VENTURERS OPERATING UNDER THE TRADE NAME PCCP CONSTUCTORS, A JOINT VENTURE

Judgment Rendered:

On Appeal from the

19th Judicial District Court Parish of East Baton Rouge, State of Louisiana Trial Court No. 750670

The Honorable Wilson E. Fields, Judge Presiding

Albert D. Clary Attorneys for Co-Plaintiff/Appellant, J. Weston Clark V& A Consulting Engineers, Inc. Alec B. Keane Baton Rouge, Louisiana

David L. Guerry Attorneys for Co-Plaintiff/Appellant, Baton Rouge, Louisiana Stantec Consulting Services, Inc. Ross D. Ginsberg, Pro Hac Vice Matthew A. Marrone, Pro Hac Vice Atlanta, Georgia

Matthew W. Bailey Attorneys for Co-Plaintiff/Appellant, Katherine M. Cook Patterson Pump Company Baton Rouge, Louisiana

Steven W. Usdin Attorneys for Defendants -Appellees, Laura M. Blockman Kiewit Louisiana Co., New Orleans, Louisiana M.R. Pittman Group, L.L.C., and Grant H. Willis, Pro Hac Vice Traylor Bros., Inc., doing business as Washington, DC PCCP Constructors, Joint Venture

BEFORE: LANIER, WOLFE, AND RESTER, JJ.

WOLFE, J.

This appeal concerns a trial court judgment sustaining a dilatory exception pleading the objection of prematurity based on an arbitration agreement and

dismissing, without prejudice, a petition for declaratoryjudgment regarding alleged perempted claims. For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

In June of 2012, the United States Army Corps of Engineers (" the Army Corps") solicited proposals to design and construct Permanent Canal Closures and

Pump Stations (the "Project") in and around New Orleans, Louisiana. The Army Corps awarded the Project contract to PCCP, a Joint Venture, made up of three individual entities, Kiewit LouisianaCo., M.R. Pittman Group, L.L.C., and Traylor Bros., Inc. ( collectively " PCCP"). PCCP, in turn, subcontracted and with many other entities to perform the work on the Project. Three subcontractor entities are

relevant to this appeal: Stantec Consulting Services, Inc., V& A Consulting

I

Engineers, Inc., and Patterson Pump Company ( collectively " the Plaintiffs").

The Army Corps and PCCP agreed that substantial completion of the Project occurred in December 2017. Thereafter, in April 2023, the Army Corps asserted five separate claims against PCCP regarding alleged problems/defects, some of which implicated work performed by PCCP' s subcontractors, including the Plaintiffs. While PCCP and the Army Corps discussed solutions to the claims, the Plaintiffs and PCCP agreed to enter into an Arbitration Agreement to resolve the

respective responsibility of each of the parties for the Army Corps' claims. 2 The

1 PCCP and Stantec entered a subcontract for design on the Project; V& A is an engineering subconsultant to Stantec; and Patterson manufactured and supplied pumps pursuant to another subcontract.

2 Other subcontractors and subconsultants, River City Environmental Services, LLC, Fugro USA Land, Inc., and Infilco Degremont, Inc., now known as Suez Water Technologies, were parties to the Arbitration Agreement as well, but the only relevant parties for purposes of this appeal are PCCP and the Plaintiffs.

Arbitration Agreement was executed between PCCP and the Plaintiffs, with an effective date of July 18, 2023.

PCCP filed an arbitration demand with JAMS Mediation, Arbitration, and Alternative Dispute Resolution Services (" JAMS"), the arbitral body the parties

agreed upon, on July 20, 2023, but then immediately requested that JAMS stay the arbitration proceedings so that PCCP could pursue resolution of its disputes with the Army Corps and to allow the parties to the Arbitration Agreement to work toward resolution of their disputes regarding their respective liability. During the negotiations in the course of the stay, an issue arose as to whether the Arbitration Agreement excluded perempted claims. On May 3, 2024, PCCP notified the Plaintiffs ofits intention to lift the previously agreed- upon stay and to re-initiate the arbitration proceedings related to the Project' s alleged defects as asserted by the Army Corps. On July 12, 2024, the Plaintiffs filed a petition for declaratory judgment against PCCP in the Nineteenth Judicial District Court, seeking a declaration that perempted claims were not encompassed in the Arbitration Agreement, that the Arbitration Agreement was null to the extent that its scope

included p erempted claims, and that p eremption had extinguished PCCP' s claims against the Plaintiffs relating to their work on the Project. On July 16, 2024, PCCP submitted a proposed procedure for arbitrator selection to JAMS and requested that

the arbitration move forward.

In response to the Plaintiffs' p etition, PCCP filed a dilatory exception raising the objection of prematurity on September 11, 2024. PCCP asserted that the

Plaintiffs' petition was premature because of the valid Arbitration Agreement that

existed between the parties, where the parties expressly agreed to arbitrate " Any Disputes ... relating to the Project[,]" including peremption. PCCP requested that the trial court dismiss the Plaintiffs' p etition in order to allow the parties to resolve their disputes through the agreed- upon arbitration process. The Plaintiffs opposed

PCCP' s exception ofprematurity. The trial court heard the exception on December 9, 2024, and took the matter under advisement. On January 29, 2025, the trial court signed a judgment sustaining PCCP' s exception of prematurity and dismissing, without prejudice, the Plaintiffs' petition for declaratory judgment. The Plaintiffs appealed asserting that the trial court legally erred in failing to resolve the issue of peremption before compelling arbitration. 3 LAW AND ANALYSIS

Louisiana Code ofCivil Procedure article 926( A)( 1) provides for the dilatory

exception pleading the objection of prematurity. An action is premature if it is brought before the right to enforce the obligation sued on has accrued. See La. Code Civ. P. art. 423. The objection ofprematurity raises the issue ofwhetherthe judicial cause of action has yet to come into existence because some prerequisite condition has not been fulfilled. Crosby as Trustee of Aaron Guidry Trust v. Crosby Enterprises, LLC, 2023- 1338 ( La. App. 1st Cir. 8/ 9/ 24), 395 So. 3d 296, 300.

The defense that the Plaintiffs in this suit are not entitled to judicial relief because of a valid agreement to submit claims to arbitration may be raised by the dilatory exception of prematurity. Crosby, 395 So. 3d at 300. Since PCCP raised

the failure to arbitrate by means of the exception of prematurity, PCCP had the burden of showing the existence of a valid contract to arbitrate, by reason of which the judicial action is premature. Id. An exception ofprematurity raises a question

of law subject to de novo review. Id.

Arbitration is favored in Louisiana and under federal law. Crosby, 395 So.3d at 301. Arbitration is a substitute for litigation. National Tea Co. v. Richmond,

548 So. 2d 930, 933 ( La. 1989). The purpose of arbitration is settlement of

3 On June 10, 2025, the Plaintiffs filed a motion to stay the ongoing arbitration pending resolution of their devolutive appeal in this court. On August 22, 2025, this court denied the motion to stay. Thus, the arbitration proceedings are moving forward in accordance with the Arbitration Agreement while this appeal is simultaneously being decided.

differences in a fast, inexpensive manner before a tribunal chosen by the parties. Id.

By consensually substituting arbitration for litigation, the parties are presumed to accept the risk of procedural and substantive mistakes of either fact or law by the

arbitrators, which mistakes are not reviewable by the courts. Durr Heavy Construction, LLC v. Willow Grove —North, LLC, 2024- 0090 (La. App. l st Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Stantec Consulting Services Inc. v. Kiewitt Louisiana Co., (La. Ct. App. 2025).

Stantec Consulting Services Inc. v. Kiewitt Louisiana Co. (Stantec Consulting Services Inc. v. Kiewitt Louisiana Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kosmala v. Paul
569 So. 2d 158 (Louisiana Court of Appeal, 1990)
Parker v. ST. TAMMANY HOSP. SERV. DIST.
670 So. 2d 531 (Louisiana Court of Appeal, 1996)
Bd. of Sup. v. Louisiana Agr. Finance Auth.
984 So. 2d 72 (Louisiana Court of Appeal, 2008)
J. Caldarera & Co. v. LA. STADIUM
725 So. 2d 549 (Louisiana Court of Appeal, 1998)
Ciaccio v. Cazayoux
519 So. 2d 799 (Louisiana Court of Appeal, 1987)
National Tea Co. v. Richmond
548 So. 2d 930 (Supreme Court of Louisiana, 1989)
Jasper Contractors, Inc. v. E-Claim.com, LLC
94 So. 3d 123 (Louisiana Court of Appeal, 2012)
Boh Bros. Construction Co. v. Cypress Bend Real Estate Development Co.
206 So. 3d 1131 (Louisiana Court of Appeal, 2016)
Brown v. Kabco Builders, Inc.
274 So. 3d 216 (Louisiana Court of Appeal, 2019)