Stanley v. Conner Construction Co.

651 S.W.2d 34, 1983 Tex. App. LEXIS 4321
CourtCourt of Appeals of Texas
DecidedApril 13, 1983
Docket7062
StatusPublished
Cited by1 cases

This text of 651 S.W.2d 34 (Stanley v. Conner Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanley v. Conner Construction Co., 651 S.W.2d 34, 1983 Tex. App. LEXIS 4321 (Tex. Ct. App. 1983).

Opinion

OPINION

WARD, Justice.

This is a usury case. The Plaintiff sued for usury penalties claiming that he was a comaker on a note executed by a corporation that he controlled. The trial court directed a verdict in favor of the Defendant, holding as a matter of law that the Plaintiff was a guarantor on the corporation note and could not recover because of the prohibition contained in Article 1302-2.-09, Tex.Rev.Civ.Stat.Ann. We affirm.

John R. Stanley was the president and sole stockholder of Southern Pipe Line Corporation. In 1974, Southern contracted with Conner Construction Co. for the purpose of building a pipeline. Southern, by the construction, became indebted to Conner Construction Co. and to finance Southern and to enable it to have an additional extension constructed to its pipeline, three written instruments, all dated May 30,1975, were executed. One was a letter agreement executed by Conner Construction Co., Southern Pipe Line Corporation by John R. Stanley, President and by John R. Stanley, individually. The second was a promissory note for $1,150,000.00 payable to the order of Conner Construction Co., it being executed by Southern Pipe Line Corporation, a Texas corporation, by John R. Stanley, President and John R. Stanley, individually. *36 The third was a deed of trust securing the promissory note.

The letter agreement provided that: (1) it was made as a supplement to the original pipeline construction contract between Southern Pipe Line Corporation and Conner Construction Co. as contractor; (2) Southern Pipe Line Corporation had initially contracted with Conner Construction Co. to extend the pipeline; (3) payment for the work had not been paid the contractor by Southern Pipe Line Corporation; (4) Southern Pipe Line Corporation desired a second extension of the pipeline for approximately twenty miles and Conner Construction Co. would do the work as contractor; and (5) the amounts past due the contractor plus the estimated construction costs for the second extension of twenty miles would total $1,150,000.00 plus interest. The letter agreement provided that, to secure the payment of the amounts due or to become due the contractor, the company would execute a real estate lien note in the amount of $1,150,000.00 bearing interest at the rate of one percent per month on the unpaid balance, and the note would be secured by a deed of trust lien on the pipeline right-of-way together with all improvements placed thereon, a copy of the deed of trust and description of the pipeline contained therein being attached as an exhibit. It also stated that the note would provide for payments of $100,000.00 per month and, in this regard, the contract stated the following: “[t]imely payments on said note are of the essence and to arrange for such timely payments, Southern Pipe Line Corporation will provide Contractor with twelve (12) signed and dated checks drawn on Southern Pipe Line Corporation, each in the amount of $100,000, and this Letter Agreement will constitute Contractor’s authorization to present those checks for payment on the dates indicated.” Southern Pipe Line Corporation represented and warranted that it had secured and would provide pipeline right-of-way for the construction work, that it had purchased the pipe, and that it should be timely delivered to the contractor on the right-of-way free and clear of any and all indebtedness. The agreement then provided as follows: “John R. Stanley will personally and individually guarantee this Contract and co-sign the real estate lien note.” As previously stated, the letter agreement was executed by Southern Pipe Line Corporation by John R. Stanley, President and John R. Stanley, individually.

The deed of trust was executed by Southern Pipeline Corporation by John R. Stanley, President, stating it was the security for the payment of a promissory note in the amount of $1,150,000.00 which note was executed by Southern Pipe Line Corporation.

The promissory note in the amount of $1,150,000.00 which was signed by Southern Pipe Line Corporation, a Texas corporation, by John R. Stanley, President and John R. Stanley, individually, provides at the beginning as follows: “[F]OR VALUE RECEIVED, I, WE, or either of us, as principals, promise to pay to the order of CONNER CONSTRUCTION CO.... ” The interest rate was one percent per month on the unpaid balance.

As provided for in the letter agreement, Conner Construction Co. was provided with the agreed twelve pre-dated installment payment checks, the first eleven being in the amount of $100,000.00 each. The checks, instead of being drawn on Southern Pipe Line Corporation, were drawn on Gas-land, Inc. At trial, it was explained that Gasland, Inc. was actually the holding company of Southern Pipe Line Corporation.

Thereafter, the additional pipeline was constructed for Southern Pipe Line Corporation. As to the predated checks that were given to Conner Construction Co., only the first four that came due were ever paid — a stop order being issued against the payment of the other eight outstanding cheeks.

By his suit, the Plaintiff contends that the letter agreement and real estate lien note conclusively established as a matter of law that Conner Construction Co. charged and contracted with John R. Stanley for interest in excess of the ten percent maximum rate allowed and that he was therefore entitled to recover two times the inter *37 est charged or contracted for in the note plus reasonable attorney’s fees. In this regard, requests for admissions conclusively established that the total interest contracted for and charged under the real estate lien note was $76,198.39. The parties stipulated that if Stanley prevailed in the suit the amount of reasonable attorney’s fees to which he would be entitled was the sum of $15,000.00.

The Defendant pled in its answer and contended at trial that John R. Stanley signed the real estate lien note merely guaranteeing the obligation of Southern and was therefore prohibited from asserting a claim of usury. Over the Plaintiff’s objection, the trial court allowed Jack Conner, the President of Conner Construction Co., to testify regarding the negotiations leading up to the execution of the letter agreement and note and that John R. Stanley was intended only as a guarantor of Southern’s indebtedness. At the close of the evidence, both parties moved for an instructed verdict. It was the Defendant’s motion for instructed verdict which was granted, that motion contending that the letter agreement and note plus other documentary and oral evidence established as a matter of law that the parties intended John R. Stanley to sign only as a guarantor of Southern’s debt and therefore his usury claim was precluded by Article 1302-2.09.

At this point, we note that the rate of interest charged was not illegal for a corporate borrower and, further, that a claim of usury would then not be available to the guarantor of the corporate debt. Article 1302-2.09. Under the terms of the statute, where a corporation agrees to pay interest at a rate permitted, “the claim or defense of usury by such corporation, its successors, guarantors ... is prohibited.” This prohibition against the assertion of the claim of usury by the guarantor applies even though the guarantor is an individual who as against the holder of the note is primarily liable. Universal Metals and Machinery, Inc. v. Bohart, 539 S.W.2d 874

Free access — add to your briefcase to read the full text and ask questions with AI

Related

El Paso Refining, Inc. v. Scurlock Permian Corp.
77 S.W.3d 374 (Court of Appeals of Texas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
651 S.W.2d 34, 1983 Tex. App. LEXIS 4321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanley-v-conner-construction-co-texapp-1983.