Stanley H. Rosenthal v. Doherty & Doherty, L.L.P., Petro Equipment, Inc., Randy West, Glenn Ellis, Nova Drilling Technologies, Inc., Bill West Properties and Billy E. West

Court of Appeals of Texas·Decided March 11, 2014·No. 01-12-01017-CV·Published

Opinion

Opinion issued March 11, 2014

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-12-01017-CV ——————————— STANLEY H. ROSENTHAL, Appellant V. DOHERTY & DOHERTY, L.L.P, PETRO EQUIPMENT, INC., RANDY WEST, GLENN ELLIS, NOVA DRILLING TECHNOLOGIES, INC., BILL WEST PROPERTIES AND BILLY E. WEST, DECEASED, Appellees

On Appeal from the 55th District Court Harris County, Texas Trial Court Case No. 2009-77118

MEMORANDUM OPINION

This appeal arises from a dispute over the responsibility for paying for

repairs to a work-over rig owned by appellant Stanley H. Rosenthal. After a bench

trial, the trial court awarded some but not all of the damages alleged by Rosenthal, against some but not all of the defendants. The final judgment also awarded

attorney’s fees to one defendant who had invoked the settlement procedure of

Chapter 42 of the Texas Civil Practice and Remedies Code.

Finding no reversible error, we affirm.

Background

Rosenthal owned a work-over rig that he used to develop his oil leases.

Appellee Petro Equipment, Inc. (Petro) was a company in the business of

fabricating and refurbishing oilfield drilling equipment. Rosenthal hired Petro to

perform repairs on his rig. Randy West was president of Petro. In managing the

company, West was advised by appellee Glenn Ellis, a man whose company

controlled 80% of Petro.

Before the work began, Rosenthal and West met to inspect the rig. The two

men identified a set of items to be examined and repaired or replaced: the air

brakes, the mast, and the cab. West testified that he gave Rosenthal an estimate of

$75,000 for this work. He further stated that $75,000 would not have been a

reasonable price for a “top to bottom” refurbishment and that he never represented

to Rosenthal that Petro would be conducting a complete refurbishment. The parties

did not enter into a written contract.

The rig was delivered to Petro in May 2008. As work progressed and the rig

was disassembled, Petro discovered additional repair needs. It informed Rosenthal

2 by phone or in person every time new problems were discovered. In each case,

Petro did not proceed without first obtaining approval from Rosenthal for the extra

work. Despite the gradual expansion of the scope of the job, Petro’s task remained

limited to specific equipment and sections of the rig.

The repairs to the rig extended over five months. During this time, Petro sent

several invoices to Rosenthal that reflected the increasing costs of the work

performed. Rosenthal did not pay these invoices.

By November 2008, Petro had yet to complete the agreed work.

Nonetheless, Rosenthal wanted to retake possession of his rig. Petro furnished

Rosenthal with a final bill of approximately $300,000, and when he refused to pay,

it refused to release the rig. The parties agreed to mediate. Both Ellis and West

attended the mediation and negotiated on behalf of Petro.

After mediation, a written settlement agreement was signed whereby

Rosenthal would pay $250,000 to Petro, and the company would return the rig to

him. As part of the bargain, Petro also furnished a one-year warranty. Under the

terms of the warranty, Rosenthal was required to “notify [Petro] in writing of any

defect or warranty claim immediately upon discovery and . . . permit [Petro] to

inspect the Product so [Petro] may determine its warranty obligations.” Of the

$250,000 settlement payment, $225,000 was to be tendered to Petro immediately,

and the rest was to be held in escrow by the law firm of Doherty & Doherty, LLP

3 for the purpose of compensating Rosenthal for any expenses he might incur in

obtaining repairs covered by the warranty. Unused amounts remaining in escrow

would pass to Petro.

Rosenthal retrieved his rig from Petro’s yard on November 10. Soon after he

had recovered it, his employees encountered serious malfunctions and breakdowns.

Rosenthal made a service call to Petro, which dispatched an employee to make the

requested repairs. However, Rosenthal paid for some of the parts used from his

own funds. On December 12, after a clutch breakdown had rendered the rig

unusable, Rosenthal sent a fax to Petro requesting service under the warranty. He

did not receive a response and contracted with other companies for this repair,

incurring substantial expense. Thereafter, Rosenthal continued to encounter

mechanical problems and contracted with third parties for parts and repairs without

notifying Petro or anyone associated with Petro.

By the time Rosenthal sent the December 12 fax, Petro had been locked out

by its landlord and had ceased operations. West became president of appellee

NOVA Drilling Technologies, Inc. On December 26, West, as president of NOVA,

sent a letter to Rosenthal notifying him that NOVA had taken over “custodial and

service duties” for his rig. NOVA performed the same mechanical work as Petro at

the same facilities, used 90% of the same employees, and had the same address,

telephone, and fax numbers.

4 The following May, Rosenthal sent a letter to NOVA requesting

reimbursement for the parts and repairs he had obtained for his rig from third-party

shops. When NOVA refused payment on the grounds that it had not been given an

opportunity to make the warranty repairs itself, Rosenthal sought disbursement

from the escrow fund.

Doherty & Doherty filed an interpleader claim against Petro and Rosenthal.

Rosenthal, by a combined crossclaim and third-party petition, brought claims

against Petro, NOVA, and Ellis. Rosenthal alleged that these parties fraudulently

induced him to enter into the settlement agreement because they knew that Petro

would soon cease operations. He also claimed that Petro had breached the terms of

the settlement agreement by failing to meet its warranty obligations.

At the close of trial, the judge entered findings of fact and conclusions of

law. He found that the agreement between Rosenthal and Petro was to perform

specific repairs to the rig and not to refurbish it so as to make it “good as new.”

Accordingly, he found that the warranty attached to the settlement agreement

covered only work actually performed by Petro and not a complete refurbishment.

He further found that the warranty required written notice and an opportunity for

Petro to inspect to determine its warranty obligations. He thus concluded that

Rosenthal was entitled to recover from the escrow account:

5 (1) the value of parts ($261.49) he furnished to Petro in connection with the service call of November 24, 2008 for which Petro waived the written notice requirement by performing the service, and

(2) his expenses ($4,500.59) incurred in connection with the fax notifying Petro of needed repairs on December 12, 2008, which was properly dispatched but not answered.

However, the judge concluded that Rosenthal was not entitled to recover the

expenses incurred thereafter for which no written claim had been submitted to

NOVA or Petro.

Additionally, the trial court found that Rosenthal was aware of Petro’s

precarious financial condition when he entered the settlement and that Petro had

the contractual right under the settlement agreement to designate another party to

perform the warranty work. It thus concluded that there was no evidence of fraud

by any party.

Finally, the trial court found that Rosenthal had rejected settlement offers

Free access — add to your briefcase to read the full text and ask questions with AI

Stanley H. Rosenthal v. Doherty & Doherty, L.L.P., Petro Equipment, Inc., Randy West, Glenn Ellis, Nova Drilling Technologies, Inc., Bill West Properties and Billy E. West, (Tex. Ct. App. 2014).

Stanley H. Rosenthal v. Doherty & Doherty, L.L.P., Petro Equipment, Inc., Randy West, Glenn Ellis, Nova Drilling Technologies, Inc., Bill West Properties and Billy E. West (Stanley H. Rosenthal v. Doherty & Doherty, L.L.P., Petro Equipment, Inc., Randy West, Glenn Ellis, Nova Drilling Technologies, Inc., Bill West Properties and Billy E. West) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ingram v. Deere
288 S.W.3d 886 (Texas Supreme Court, 2009)
Centex Corp. v. Dalton
840 S.W.2d 952 (Texas Supreme Court, 1992)
Finley v. J.C. Pace Ltd.
4 S.W.3d 319 (Court of Appeals of Texas, 1999)
Southwestern Resolution Corp. v. Watson
964 S.W.2d 262 (Texas Supreme Court, 1998)
Surgitek, Bristol-Myers Corp. v. Abel
997 S.W.2d 598 (Texas Supreme Court, 1999)
Emerald Forest Utility District v. Simonsen Construction Co.
679 S.W.2d 51 (Court of Appeals of Texas, 1984)