Opinion issued March 11, 2014
In The
Court of Appeals For The
First District of Texas ———————————— NO. 01-12-01017-CV ——————————— STANLEY H. ROSENTHAL, Appellant V. DOHERTY & DOHERTY, L.L.P, PETRO EQUIPMENT, INC., RANDY WEST, GLENN ELLIS, NOVA DRILLING TECHNOLOGIES, INC., BILL WEST PROPERTIES AND BILLY E. WEST, DECEASED, Appellees
On Appeal from the 55th District Court Harris County, Texas Trial Court Case No. 2009-77118
MEMORANDUM OPINION
This appeal arises from a dispute over the responsibility for paying for
repairs to a work-over rig owned by appellant Stanley H. Rosenthal. After a bench
trial, the trial court awarded some but not all of the damages alleged by Rosenthal, against some but not all of the defendants. The final judgment also awarded
attorney’s fees to one defendant who had invoked the settlement procedure of
Chapter 42 of the Texas Civil Practice and Remedies Code.
Finding no reversible error, we affirm.
Background
Rosenthal owned a work-over rig that he used to develop his oil leases.
Appellee Petro Equipment, Inc. (Petro) was a company in the business of
fabricating and refurbishing oilfield drilling equipment. Rosenthal hired Petro to
perform repairs on his rig. Randy West was president of Petro. In managing the
company, West was advised by appellee Glenn Ellis, a man whose company
controlled 80% of Petro.
Before the work began, Rosenthal and West met to inspect the rig. The two
men identified a set of items to be examined and repaired or replaced: the air
brakes, the mast, and the cab. West testified that he gave Rosenthal an estimate of
$75,000 for this work. He further stated that $75,000 would not have been a
reasonable price for a “top to bottom” refurbishment and that he never represented
to Rosenthal that Petro would be conducting a complete refurbishment. The parties
did not enter into a written contract.
The rig was delivered to Petro in May 2008. As work progressed and the rig
was disassembled, Petro discovered additional repair needs. It informed Rosenthal
2 by phone or in person every time new problems were discovered. In each case,
Petro did not proceed without first obtaining approval from Rosenthal for the extra
work. Despite the gradual expansion of the scope of the job, Petro’s task remained
limited to specific equipment and sections of the rig.
The repairs to the rig extended over five months. During this time, Petro sent
several invoices to Rosenthal that reflected the increasing costs of the work
performed. Rosenthal did not pay these invoices.
By November 2008, Petro had yet to complete the agreed work.
Nonetheless, Rosenthal wanted to retake possession of his rig. Petro furnished
Rosenthal with a final bill of approximately $300,000, and when he refused to pay,
it refused to release the rig. The parties agreed to mediate. Both Ellis and West
attended the mediation and negotiated on behalf of Petro.
After mediation, a written settlement agreement was signed whereby
Rosenthal would pay $250,000 to Petro, and the company would return the rig to
him. As part of the bargain, Petro also furnished a one-year warranty. Under the
terms of the warranty, Rosenthal was required to “notify [Petro] in writing of any
defect or warranty claim immediately upon discovery and . . . permit [Petro] to
inspect the Product so [Petro] may determine its warranty obligations.” Of the
$250,000 settlement payment, $225,000 was to be tendered to Petro immediately,
and the rest was to be held in escrow by the law firm of Doherty & Doherty, LLP
3 for the purpose of compensating Rosenthal for any expenses he might incur in
obtaining repairs covered by the warranty. Unused amounts remaining in escrow
would pass to Petro.
Rosenthal retrieved his rig from Petro’s yard on November 10. Soon after he
had recovered it, his employees encountered serious malfunctions and breakdowns.
Rosenthal made a service call to Petro, which dispatched an employee to make the
requested repairs. However, Rosenthal paid for some of the parts used from his
own funds. On December 12, after a clutch breakdown had rendered the rig
unusable, Rosenthal sent a fax to Petro requesting service under the warranty. He
did not receive a response and contracted with other companies for this repair,
incurring substantial expense. Thereafter, Rosenthal continued to encounter
mechanical problems and contracted with third parties for parts and repairs without
notifying Petro or anyone associated with Petro.
By the time Rosenthal sent the December 12 fax, Petro had been locked out
by its landlord and had ceased operations. West became president of appellee
NOVA Drilling Technologies, Inc. On December 26, West, as president of NOVA,
sent a letter to Rosenthal notifying him that NOVA had taken over “custodial and
service duties” for his rig. NOVA performed the same mechanical work as Petro at
the same facilities, used 90% of the same employees, and had the same address,
telephone, and fax numbers.
4 The following May, Rosenthal sent a letter to NOVA requesting
reimbursement for the parts and repairs he had obtained for his rig from third-party
shops. When NOVA refused payment on the grounds that it had not been given an
opportunity to make the warranty repairs itself, Rosenthal sought disbursement
from the escrow fund.
Doherty & Doherty filed an interpleader claim against Petro and Rosenthal.
Rosenthal, by a combined crossclaim and third-party petition, brought claims
against Petro, NOVA, and Ellis. Rosenthal alleged that these parties fraudulently
induced him to enter into the settlement agreement because they knew that Petro
would soon cease operations. He also claimed that Petro had breached the terms of
the settlement agreement by failing to meet its warranty obligations.
At the close of trial, the judge entered findings of fact and conclusions of
law. He found that the agreement between Rosenthal and Petro was to perform
specific repairs to the rig and not to refurbish it so as to make it “good as new.”
Accordingly, he found that the warranty attached to the settlement agreement
covered only work actually performed by Petro and not a complete refurbishment.
He further found that the warranty required written notice and an opportunity for
Petro to inspect to determine its warranty obligations. He thus concluded that
Rosenthal was entitled to recover from the escrow account:
5 (1) the value of parts ($261.49) he furnished to Petro in connection with the service call of November 24, 2008 for which Petro waived the written notice requirement by performing the service, and
(2) his expenses ($4,500.59) incurred in connection with the fax notifying Petro of needed repairs on December 12, 2008, which was properly dispatched but not answered.
However, the judge concluded that Rosenthal was not entitled to recover the
expenses incurred thereafter for which no written claim had been submitted to
NOVA or Petro.
Additionally, the trial court found that Rosenthal was aware of Petro’s
precarious financial condition when he entered the settlement and that Petro had
the contractual right under the settlement agreement to designate another party to
perform the warranty work. It thus concluded that there was no evidence of fraud
by any party.
Finally, the trial court found that Rosenthal had rejected settlement offers
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion issued March 11, 2014
In The
Court of Appeals For The
First District of Texas ———————————— NO. 01-12-01017-CV ——————————— STANLEY H. ROSENTHAL, Appellant V. DOHERTY & DOHERTY, L.L.P, PETRO EQUIPMENT, INC., RANDY WEST, GLENN ELLIS, NOVA DRILLING TECHNOLOGIES, INC., BILL WEST PROPERTIES AND BILLY E. WEST, DECEASED, Appellees
On Appeal from the 55th District Court Harris County, Texas Trial Court Case No. 2009-77118
MEMORANDUM OPINION
This appeal arises from a dispute over the responsibility for paying for
repairs to a work-over rig owned by appellant Stanley H. Rosenthal. After a bench
trial, the trial court awarded some but not all of the damages alleged by Rosenthal, against some but not all of the defendants. The final judgment also awarded
attorney’s fees to one defendant who had invoked the settlement procedure of
Chapter 42 of the Texas Civil Practice and Remedies Code.
Finding no reversible error, we affirm.
Background
Rosenthal owned a work-over rig that he used to develop his oil leases.
Appellee Petro Equipment, Inc. (Petro) was a company in the business of
fabricating and refurbishing oilfield drilling equipment. Rosenthal hired Petro to
perform repairs on his rig. Randy West was president of Petro. In managing the
company, West was advised by appellee Glenn Ellis, a man whose company
controlled 80% of Petro.
Before the work began, Rosenthal and West met to inspect the rig. The two
men identified a set of items to be examined and repaired or replaced: the air
brakes, the mast, and the cab. West testified that he gave Rosenthal an estimate of
$75,000 for this work. He further stated that $75,000 would not have been a
reasonable price for a “top to bottom” refurbishment and that he never represented
to Rosenthal that Petro would be conducting a complete refurbishment. The parties
did not enter into a written contract.
The rig was delivered to Petro in May 2008. As work progressed and the rig
was disassembled, Petro discovered additional repair needs. It informed Rosenthal
2 by phone or in person every time new problems were discovered. In each case,
Petro did not proceed without first obtaining approval from Rosenthal for the extra
work. Despite the gradual expansion of the scope of the job, Petro’s task remained
limited to specific equipment and sections of the rig.
The repairs to the rig extended over five months. During this time, Petro sent
several invoices to Rosenthal that reflected the increasing costs of the work
performed. Rosenthal did not pay these invoices.
By November 2008, Petro had yet to complete the agreed work.
Nonetheless, Rosenthal wanted to retake possession of his rig. Petro furnished
Rosenthal with a final bill of approximately $300,000, and when he refused to pay,
it refused to release the rig. The parties agreed to mediate. Both Ellis and West
attended the mediation and negotiated on behalf of Petro.
After mediation, a written settlement agreement was signed whereby
Rosenthal would pay $250,000 to Petro, and the company would return the rig to
him. As part of the bargain, Petro also furnished a one-year warranty. Under the
terms of the warranty, Rosenthal was required to “notify [Petro] in writing of any
defect or warranty claim immediately upon discovery and . . . permit [Petro] to
inspect the Product so [Petro] may determine its warranty obligations.” Of the
$250,000 settlement payment, $225,000 was to be tendered to Petro immediately,
and the rest was to be held in escrow by the law firm of Doherty & Doherty, LLP
3 for the purpose of compensating Rosenthal for any expenses he might incur in
obtaining repairs covered by the warranty. Unused amounts remaining in escrow
would pass to Petro.
Rosenthal retrieved his rig from Petro’s yard on November 10. Soon after he
had recovered it, his employees encountered serious malfunctions and breakdowns.
Rosenthal made a service call to Petro, which dispatched an employee to make the
requested repairs. However, Rosenthal paid for some of the parts used from his
own funds. On December 12, after a clutch breakdown had rendered the rig
unusable, Rosenthal sent a fax to Petro requesting service under the warranty. He
did not receive a response and contracted with other companies for this repair,
incurring substantial expense. Thereafter, Rosenthal continued to encounter
mechanical problems and contracted with third parties for parts and repairs without
notifying Petro or anyone associated with Petro.
By the time Rosenthal sent the December 12 fax, Petro had been locked out
by its landlord and had ceased operations. West became president of appellee
NOVA Drilling Technologies, Inc. On December 26, West, as president of NOVA,
sent a letter to Rosenthal notifying him that NOVA had taken over “custodial and
service duties” for his rig. NOVA performed the same mechanical work as Petro at
the same facilities, used 90% of the same employees, and had the same address,
telephone, and fax numbers.
4 The following May, Rosenthal sent a letter to NOVA requesting
reimbursement for the parts and repairs he had obtained for his rig from third-party
shops. When NOVA refused payment on the grounds that it had not been given an
opportunity to make the warranty repairs itself, Rosenthal sought disbursement
from the escrow fund.
Doherty & Doherty filed an interpleader claim against Petro and Rosenthal.
Rosenthal, by a combined crossclaim and third-party petition, brought claims
against Petro, NOVA, and Ellis. Rosenthal alleged that these parties fraudulently
induced him to enter into the settlement agreement because they knew that Petro
would soon cease operations. He also claimed that Petro had breached the terms of
the settlement agreement by failing to meet its warranty obligations.
At the close of trial, the judge entered findings of fact and conclusions of
law. He found that the agreement between Rosenthal and Petro was to perform
specific repairs to the rig and not to refurbish it so as to make it “good as new.”
Accordingly, he found that the warranty attached to the settlement agreement
covered only work actually performed by Petro and not a complete refurbishment.
He further found that the warranty required written notice and an opportunity for
Petro to inspect to determine its warranty obligations. He thus concluded that
Rosenthal was entitled to recover from the escrow account:
5 (1) the value of parts ($261.49) he furnished to Petro in connection with the service call of November 24, 2008 for which Petro waived the written notice requirement by performing the service, and
(2) his expenses ($4,500.59) incurred in connection with the fax notifying Petro of needed repairs on December 12, 2008, which was properly dispatched but not answered.
However, the judge concluded that Rosenthal was not entitled to recover the
expenses incurred thereafter for which no written claim had been submitted to
NOVA or Petro.
Additionally, the trial court found that Rosenthal was aware of Petro’s
precarious financial condition when he entered the settlement and that Petro had
the contractual right under the settlement agreement to designate another party to
perform the warranty work. It thus concluded that there was no evidence of fraud
by any party.
Finally, the trial court found that Rosenthal had rejected settlement offers
from Ellis that were significantly more favorable than the take-nothing judgment
Rosenthal received against him; the court concluded that Ellis should recover
attorney’s fees pursuant to Section 38.001 of the Texas Civil Practice and
Remedies Code.
The trial court entered judgment that Rosenthal have $4,762.08 from the
escrow fund and $10,000 in attorney’s fees from Petro. All other requested relief
6 was denied. As part of the judgment, the court also decreed that Ellis recover
$30,500.22 in attorney’s fees from Rosenthal. Rosenthal appealed.
Analysis
Rosenthal argues that the trial court erred by not entering judgment in his
favor against NOVA. He claims that he was entitled to a default judgment against
NOVA, which failed to file an answer. In the alternative, he argues that the
judgment is inconsistent in assigning liability to Petro but not NOVA, as NOVA
also refused to authorize the release of escrowed funds.
Rosenthal also challenges the trial court’s conclusion that he failed to
comply with the notice procedure of the warranty. Rosenthal characterizes the trial
court’s decision as an implicit holding that he did not satisfy a contractual
condition precedent. He contends that failure of a condition precedent was not
properly pleaded by Petro or NOVA and should not have been considered by the
trial court.
Rosenthal further contends that the trial court erred in assessing damages—
that it should have awarded him all of the expenses he incurred in repairing his rig.
In support of this position, he argues that the evidence was both legally and
factually insufficient to support the trial court’s finding that the work to be
performed by Petro was limited to specific areas of the rig and was not a complete
refurbishment.
7 Finally, in a separate and discrete issue, Rosenthal contends that the trial
court erred in awarding attorney’s fees to Ellis pursuant to Chapter 42 of the Texas
Civil Practice and Remedies Code. Specifically, he argues that Ellis did not file the
required declaration invoking the section’s procedures before making his
settlement offers.
I. Judgment against NOVA
Rosenthal argues that the trial court should have entered judgment in his
favor against NOVA. He claims that because NOVA did not file an answer, the
trial court should have entered a default judgment against it. In the alternative, he
argues that since NOVA also failed to authorize the disbursement of escrow funds
at his request, it should be included in the judgment along with Petro.
A. Default judgment
Rosenthal argues that the court erred in not entering a default judgment
against NOVA. NOVA was served with process and did not file an answer, but
Rosenthal never moved for the trial court to enter a default judgment. It is a
prerequisite to appellate review that the appellant’s complaint was first made to the
trial court by a timely request, objection, or motion. TEX. R. APP. P. 33.1. Since
Rosenthal never asked that the trial court enter a default judgment against NOVA,
he cannot claim that the trial court erred in not doing so.
8 B. Failure of condition precedent
Rosenthal contends that the trial court erred in considering whether he had
complied with the notice provisions of the warranty as this question concerned
compliance with a condition precedent, an affirmative defense that Petro and
NOVA failed to raise by verified pleadings.
“A condition precedent is an event that must happen or be performed before
a right can accrue to enforce an obligation.” Centex Corp. v. Dalton, 840 S.W.2d
952, 956 (Tex. 1992). “When a contract provides for a particular form of notice,
compliance with such provisions is a condition precedent to invoking the contract
rights which are conditioned on the notice.” Emerald Forest Util. Dist. v. Simonsen
Constr. Co., 679 S.W.2d 51, 54 (Tex. App.—Houston [14th Dist.] 1984, writ ref’d
n.r.e.); accord Tenn. Gas Pipeline Co. v. Technip USA Corp., No. 01–06–00535–
CV, 2008 WL 3876141, at *21 (Tex. App.—Houston [1st Dist.] Aug. 21, 2008,
pet. denied) (mem. op.).
As a plaintiff suing on a contract, Rosenthal did not have to specifically
plead compliance with all conditions precedent. See TEX R. CIV. P. 54. Rather, it
was enough for Rosenthal merely “to aver generally that all conditions precedent
have been performed or have occurred” in his petition. Id. Having done so,
Rosenthal was required only to prove the occurrence of those conditions precedent
“as are specifically denied by the opposite party.” Id.
9 Neither Petro nor NOVA filed an answer specifically denying a condition
precedent. However, issues not raised by the pleadings may nonetheless be tried be
consent. See Sw. Resolution Corp. v. Watson, 964 S.W.2d 262, 264 (Tex. 1997)
(citing TEX. R. CIV. P. 67). “When both parties present evidence on an issue and
the issue is developed during trial without objection, any defects in the pleadings
are cured at trial, and the defects are waived.” Ingram v. Deere, 288 S.W.3d 886,
893 (Tex. 2009) (citing TEX. R. CIV. P. 67).
In this case, the parties offered evidence and argument concerning the
warranty’s notice requirement without objection by Rosenthal. For example,
Rosenthal was aggressively cross-examined as to whether and when he gave notice
that warrantied repairs were needed. Furthermore, after the testimony had
concluded, the trial judge engaged the attorneys in a long colloquy about the law
and facts of the case. Emphasizing the significance of the notice issue at trial, he
asked Rosenthal’s counsel, “From a breach of warranty standpoint, how can there
be warranty claims for . . . repairs where your client did not give Petro . . . notice,
written notice, as required in the warranty?” As this question illustrates, the issue
of notice was tried by consent, and Rosenthal cannot now object to the failure of
Petro or NOVA to raise it by verified pleadings. See Ingram, 288 S.W.3d at 893;
Watson, 964 S.W.2d at 264.
10 C. Consistency of the judgment
Rosenthal observes that the trial court “found that some of Rosenthal’s
requests for payment should have been granted, and awarded attorney’s fees
against Petro, but not against NOVA.” He argues that because his May letter to
NOVA requested disbursement of funds from the escrow fund pursuant to the
warranty agreement, the court should have entered judgment against Petro and
NOVA, jointly and severally.
This argument, however, does not address record evidence from which the
positions of Petro and NOVA may be differentiated. Notably, Rosenthal’s service
call and December 12 fax were addressed to Petro, not NOVA. Moreover, although
NOVA gave notice in its December 26 letter that it would begin performing the
warranty service, Rosenthal never acted on this information by contacting NOVA
to report the repairs sought by the December 12 fax or any of the other breakdowns
for which he obtained solutions from third parties. In sum, the trial judge, who
found that Petro breached the settlement agreement by failing to honor the request
for warranty work contained in the December 12 fax, reasonably could have
reached a different conclusion as to NOVA’s liability when the fax was not
addressed to it and no subsequent communication notified it of a request for
warranty service.
11 We conclude that the trial court did not err by excluding NOVA from the
judgment. Furthermore, as we have sustained the trial court’s finding that
Rosenthal failed to give proper notice under the warranty, it is unnecessary for us
to address his challenge to the court’s findings as to the scope of the original
contract to repair the rig. Regardless of whether the trial court erred in deciding the
breadth of the agreed-upon work, the court’s holding restricted Rosenthal’s
damages to expenses for which he gave proper notice. Whatever the ambit of the
original undertaking, Rosenthal only furnished notice for a limited set of warranty
repairs, and the trial court awarded him damages for the expenses thus incurred.
II. Attorney’s fees
Rosenthal asserts that the trial court should not have awarded attorney’s fees
pursuant to the Civil Practice and Remedies Code because Ellis did not comply
with Chapter 42’s procedures by filing a declaration before making settlement
offers.
Chapter 42 of the Civil Practice and Remedies Code allows a party, by
complying with certain procedures, to recoup litigation expenses from its adversary
if the adversary rejects a settlement offer that proves to be “significantly less
favorable” than the ultimate judgment. See TEX. CIV. PRAC. & REM. CODE ANN.
§ 42.004 (West Supp. 2013). The chapter does not apply “until a defendant files a
declaration that the settlement procedure allowed by this chapter is available in the
12 action.” Id. § 42.002. Once a declaration has been filed, a party may make written
settlement offers that the court can later consider in deciding to award litigation
expenses. Id. §§ 42.003–.004. The statute empowers the Supreme Court of Texas
to make implementing rules, which it has done through Rule 167 of the Texas
Rules of Civil Procedure. See id. § 42.005 (West 2008).
Here, Ellis filed with the court and sent to Rosenthal two documents
denominated “Defendant, Glenn Ellis’, TRCP Rule 167 Offer of Settlement” and
“Defendant, Glenn Ellis’, Second TRCP Rule 167 Offer of Settlement.” The first
document states “Pursuant to the Texas Rules of Civil Procedure, Rule 167 and
Chapter 42 of the Civil Practice and Remedies Code, Mr. Ellis offers $7,500.00 to
Mr. Stanley Rosenthal . . . to fully and finally settle any and all claims, whether
valid or invalid, in Cause No. 2009-77,118 . . . .”
Rosenthal takes the position that the statute requires that a declaration be a
separate document from a settlement offer. He points to the following language in
the statute and the implementing rule as evidence that separate documents are
contemplated:
(b) The rules promulgated by the supreme court must provide: (1) the date by which a defendant or defendants must file the declaration required by Section 42.002(c); (2) the date before which a party may not make a settlement offer (3) the date after which a party may not make a settlement offer . ... Id.
13 (a) Defendant’s declaration a prerequisite; deadline. A settlement offer under this rule may not be made until a defendant—a party against whom a claim for monetary damages is made—files a declaration invoking this rule . . . .
TEX. R. CIV. P. 167.2. Additionally, he contends that certain language found in
Chapter 42 must be contained in any putative declaration—“that the settlement
procedure allowed by this chapter is available in the action”—and that this
language is absent from Ellis’s settlement offers. See TEX. CIV. PRAC. & REM.
CODE ANN. § 42.002.
We do not agree with Rosenthal that Chapter 42 requires that a party use any
specific wording to invoke the procedure. Such a requirement does not appear in
the statute. See id. The words Ellis used, “Pursuant to the Texas Rules of Civil
Procedure, Rule 167 and Chapter 42 of the Civil Practice and Remedies Code,”
were adequate. Cf. Finley v. J.C. Pace Ltd. 4 S.W.3d 319, 320 (Tex. App.—
Houston [1st Dist.] 1999, no pet.) (“The effect of a motion depends on the nature
of the instrument. We look to its substance rather than its form.” (citation
omitted)).
We need not decide whether a document may simultaneously function as a
declaration and settlement offer. In this case, it suffices to find that the first
document, which Ellis titled “Defendant, Glenn Ellis’, TRCP Rule 167 Offer of
Settlement” and filed with the court, constituted a declaration invoking Chapter
14 42.* Regardless of the sufficiency of the first document by itself, the second
document, which Ellis served on Rosenthal and titled “Defendant, Glenn Ellis’,
Second TRCP Rule 167 Offer of Settlement,” qualified as a Chapter 42 settlement
offer. Rosenthal’s issue is overruled.
Conclusion
We affirm the judgment of the trial court.
Michael Massengale Justice
Panel consists of Chief Justice Radack, Justices Massengale and Huddle.
* Cf. TEX. R. CIV. P. 71 (“When a party has mistakenly designated any plea or pleading, the court, if justice so requires, shall treat the plea or pleading as if it had been properly designated”); Surgitek, Bristol–Myers Corp. v. Abel, 997 S.W.2d 598, 601 (Tex. 1999) (“[W]e look to the substance of a motion to determine the relief sought, not merely to its title.”). 15