Stanley Educational Methods, Inc. v. The Becker C.P.A Review Course, Inc.

536 F.2d 86, 1976 U.S. App. LEXIS 7766
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 30, 1976
Docket75-1155
StatusPublished
Cited by2 cases

This text of 536 F.2d 86 (Stanley Educational Methods, Inc. v. The Becker C.P.A Review Course, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanley Educational Methods, Inc. v. The Becker C.P.A Review Course, Inc., 536 F.2d 86, 1976 U.S. App. LEXIS 7766 (5th Cir. 1976).

Opinion

CLARK, Circuit Judge:

On May 8, 1964, Stanley Educational Methods, Inc. (Stanley), and Becker Educational Methods, Inc., predecessor of the present defendant, The Becker CPA Review Course, Ltd. (Becker), entered into a contract under which Becker would supply materials and teaching aids to Stanley for use by the latter in conducting in the Dallas, Texas area review courses for the Certified Public Accountant examination. Becker was to receive a percentage of Stanley’s receipts. The term of the original contract was five years. In 1969, the contract, in substantially its original form, was renewed for a period ending June 1, 1974. In 1971, the parties agreed orally to adopt a similar plan for the New Orleans area. Under the agreements, Stanley taught CPA review courses in January and June each year.

As the expiration date approached, Stanley undertook preparations for a course to begin May 28, 1974; these preparations were undertaken with the knowledge and participation of Becker. At the same time, Becker and Stanley conducted negotiations aimed at producing a new agreement. These negotiations failed to produce such an agreement, however, and on May 20, Becker informed Stanley that the agreement then in force would expire on schedule, June 1.

On May 28 — the day the course was scheduled to begin — Stanley filed a petition for declaratory and injunctive relief in the district court, urging that Becker had no right to “cancel” the contract and that it should be enjoined from interfering with the conduct of the courses under principles of equitable estoppel. The following day, the district court signed a “Fiat” in the form reproduced in the margin. 1 The next court order appearing in the docket entries *89 and record is dated June 27, 1974. The order recites that it continues an injunction. This order, as approved by counsel for both parties, also is reproduced in the margin. 2

A bench trial was held October 16, 1974, at which time the court read into the record findings of fact and conclusions of law; these findings and conclusions subsequently were formalized and entered December 11, 1974, and judgment based thereon was entered one week later.

In sum, the district court found: 1) Becker was not equitably estopped to contend that the 1969 contract renewal had expired June 1, 1974; 2) the contract had so expired; 3) Stanley’s use of the Becker material after June 1 was unauthorized and a breach of contract; 4) Becker was entitled to recover damages of $58,955.50 for the breach; and 5) the breach rendered the non-competition clause of the contract unenforceable.

As a preliminary matter, we are confronted with the question of the effect of the trial court’s orders of May 29 and June 27, 1974. The original complaint prays for a preliminary injunction and requests a “show cause” order to notify Becker and set the date for an adversary hearing. See Fed.R.Civ.P. 65(a)(1) and (2). The district court’s Fiat granted this request, ordering defendant Becker to appear before it at 9:00 a. m., June 13, 1974.

No record of any such proceeding — or reason why it was not held — appears in the docket entries, exhibits or briefs of the parties, nor is such an event claimed to exist dehors the record. Several explanations for this state of affairs are plausable. Stanley and Becker may have agreed to postpone the proceedings. The trial court may have continued the hearing on its own. Becker may have failed to appear June 13, or misconstrued the Fiat as a temporary restraining order. If any of these possibilities be true, what is not explained is the failure of the parties to take proper action to record the actual event. As a result, it is not clear what — if any — injunction was issued.

Not only does Stanley offer no explanation for this omission, it also affirmatively seeks a reversal of the district court’s action premised in part upon the lack of injunctive coercion during this period. Clearly, the responsibility for this crucial deficiency rests with the litigant who would urge the missing matter as a basis for his appellate position. Fed.R.App.P. 10(e).

Despite these procedural deficiencies, justice demands that we premise our review on the same basis accepted by the parties and the court: as though some form of injunctive mandate had been in force from May 29 through the entry of the “order continuing injunction” on June 27. Ob *90 viously this understanding pervaded the case below 3 during the entirety of the proceedings. Stanley’s belated attempt to have us consider that, since no injunction order technically issued, Becker acted voluntarily is at odds with the reality of what happened. If Becker had not obeyed what it thought was its enjoined duty during this period, Stanley obviously would have insisted that its inchoate rights be perfected by a court which thought they already existed. Stanley cannot now derive an advantage from this common mistake or oversight.

Stanley argues that Becker’s acts and omissions caused Stanley to undertake obligations it would not have incurred had it known that its contract would be cancelled. Thus Stanley argues Becker is estopped from asserting that Stanley’s continued conduct of the course which began on May 28 was a breach of contract.

The elements of equitable estoppel as applied in Texas are set out in Gulbenkian v. Penn, 151 Tex. 412, 252 S.W.2d 929 (1952). They are:

D false representation or knowing concealment of
2) material
3) facts
made with 4) actual or constructive knowledge thereof
5) to a party lacking such knowledge or the means of obtaining it
with 6) successful
V intent to induce reliance
8) prejudicial to the party so relying.

See id. at 417-418, 252 S.W.2d at 932.

The discussions contained references to changes in the relationship between the parties, and in the percentages of the proceeds to be retained by Stanley and paid over to Becker. While the original 1964 contract provided for extension for an additional five years at the election of either party, it also provided that the contract would terminate at the end of the second five-year period unless extended by mutual consent. The proof that substantial changes in the nature of the agreement were desired by Becker substantiates the district court’s finding that the negotiations pertained to a new agreement that would embody those changes. Since the discussions pertained, not to present facts, but to future intentions, the third element of an equitable estoppel is missing here as well.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
536 F.2d 86, 1976 U.S. App. LEXIS 7766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanley-educational-methods-inc-v-the-becker-cpa-review-course-inc-ca5-1976.