Stanley-Bledsoe Corp. v. LeBlanc

236 F. Supp. 161, 1964 U.S. Dist. LEXIS 6693
CourtDistrict Court, E.D. Louisiana
DecidedDecember 2, 1964
DocketCiv. A. No. 2735
StatusPublished

This text of 236 F. Supp. 161 (Stanley-Bledsoe Corp. v. LeBlanc) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanley-Bledsoe Corp. v. LeBlanc, 236 F. Supp. 161, 1964 U.S. Dist. LEXIS 6693 (E.D. La. 1964).

Opinion

WEST, District Judge.

Plaintiff, Stanley-Bledsoe Corporation, entered into a contract with United Gas Corporation whereby plaintiff was to construct some 30 odd miles of 30 inch pipe line extending from the south header of Red River in Avoyelles Parish, Louisiana, to the south side of the main line valve number 15 in Lasalle Parish, Louisiana. Item No. 1 of this contract required plaintiff to “Clear, Grub' and Grade Right of Way” through which the pipe line was to be laid. Insofar as is pertinent to this case, the contract between plaintiff and United Gas provided as follows:

“Item No. 1 — Clear, Grub and Grade

Right of Way “Clear
* -X- -X- -X- -X- *
“All permanent right of way shall be cleared to the widths set forth in the easements and shown on the Drawings. Temporary working areas provided may be cleared if clearing is necessary for Contractor’s operations.
“Contractor shall provide a pipe line detector of an approved design and shall locate, uncover and mark all existing lines crossed prior to the beginning of any operation.
“Contractor, having first ascertained from Owner that permission has been secured from the property owner, shall build suitable gates or gaps in the fences crossed by the route of the pipe line and maintain them so that livestock shall be prevented from entering or leaving the property. Before cutting such fences to make these gates or gaps, Contraction [sic] shall brace the fences to prevent damage to them. Gates or gaps shall be so constructed that they can be securely closed. Fence braces, gaps or gates built by Contractor and found unsatisfactory to the land owners shall be corrected to meet their requirements. Where necessary, Contractor shall furnish a watchman to maintain these gates to prevent livestock from entering or leaving the property and also shall furnish watchmen in any instance where required so to do by Owner.
“If timber is encountered, the right of way shall be cleared by the removal of overhanging branches which would be in the way of construction or future operations and by the cutting of all trees, brush, stumps and other encumbrances flush with the finished grade of the right of way, except for stumps in the ditch line which shall be removed by grubbing.
“Contractor shall clear the right of way a sufficient distance from the ditch line by removing all loose brush, stumps and other debris so that the spoil bank from the ditching operations will not fall on any foreign materials that might become mixed with the excavated soil. All trees cleared will be felled on the right of way. Clearing operations done with bulldozers will be con[163]*163fined to the right of way; and trees, stumps, brush and other debris will not be pushed off the right of way. Any merchantable timber shall be stripped of leaves and branches and cut into standard lengths and stacked on and parallel to the right of way for disposal by Owner unless otherwise specified in the right of way easement.
“All timber that is not merchantable and all tree tops, brush and inflammable debris shall be burned on the right of way or disposed of in accordance with the provisions of the right of way easement. Contractor shall take every precaution to prevent .the burning of this material from causing damage off the right of way, and Contractor shall be liable for any damage caused by this operation.
“Grub and Grade
“Contractor shall complete all grubbing and grading necessary over the entire line to allow passage of equipment or to allow the ditch to be excavated to the line and grade established by the Engineer.
“Spoil banks from the grading operations shall not be placed where drainage will be affected. Contractor shall not place spoil off of Owner’s right of way. If additional spoil area is required by Contractor, such spoil area shall be secured at Contractor’s sole cost and expense.
* * * « * *
“Exhibit C — Specifications
“Item No. 7 — Backfill and Cleanup
* ■» -X- -X- * -X-
“Where necessary and where required by the Engineer, Contractor shall install culverts along the right of way, the materials to be furnished by Owner. Contractor shall protect the backfill from washing away by the installation of shoring or rip-rap or sacks of earth or by the building of terraces, or by excavation of cross drain ditches to carry any water from rainfall away from the ditch line.
“Contractor is specifically notified that provisional acceptance and partial payments for work done shall not relieve Contractor from all work necessary to put the backfill, the right of way, and other roads or lands used by it in proper shape at the time of final acceptance of the job. Before final acceptance of the job, the entire line will be inspected, and whatever work is necessary shall be done to leave the right of way in the best possible condition.”

In this prime contract, portions of which are above quoted, the CONTRACTOR referred to is the plaintiff herein.

Plaintiff then entered into a subcontract with the respondents, Mederic J. LeBlanc and Alvin E. LeBlanc, d/b/a LeBlanc Brothers Contractors, and J. B. McDaniels, as joint venturers, whereby plaintiff subcontracted the work of clearing, grubbing and grading to the defendants. This subcontract, in its preamble, stated as follows:

“WITNESSETH:
“WHEREAS, CONTRACTOR has heretofore entered into a contract dated August 3rd, 1961, (hereinafter called “PRINCIPAL CONTRACT”), with United Gas Pipe Line Company, a Corporation, having its principal offices in Shreveport, Louisiana, (hereinafter called “OWNER”).
“The work to be done by CONTRACTOR under the terms of the PRINCIPAL CONTRACT includes but may not be limited to, the construction of a high pressure 30" gas pipe line along with its appurtenances, from a point commencing at the South side of the Red River, Avoyelles Parish, Louisiana, and extending to the South side of the site of the proposed main line valve number 15, located in LaSalle Parish, Louisiana, and identified as Section 3 of the proposed pipe line. Said work includes the cutting of fences and the installation of gates, [164]*164the clearing and removal of timber from the rights-of-way and the grading of the rights-of-way for pipe line construction.”

This subcontract then proceeds to subcontract the following work to respondents:

"SCOPE OF WORK
“SUBCONTRACTOR shall furnish all the labor, materials, tools, construction equipment, fuel, transportation and all other things necessary and perform in a prompt, efficient and workmanlike manner the following work:
“Where fences cross the pipe line right-of-way, the adjacent posts will be braced and a gap the width of the pipe line right-of-way cut in the fence, and temporary gates shall be furnished and installed all in a manner acceptable to the OWNER’S ENGINEER and CONTRACTOR. No fences are to be cut without the approval of the OWNER’S ENGINEER.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
236 F. Supp. 161, 1964 U.S. Dist. LEXIS 6693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanley-bledsoe-corp-v-leblanc-laed-1964.