Stanislaus Food Products Co. v. Public Utilities Commission

560 F. Supp. 114, 1982 U.S. Dist. LEXIS 17279
CourtDistrict Court, N.D. California
DecidedAugust 11, 1982
DocketC 81-2999 SW
StatusPublished
Cited by4 cases

This text of 560 F. Supp. 114 (Stanislaus Food Products Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanislaus Food Products Co. v. Public Utilities Commission, 560 F. Supp. 114, 1982 U.S. Dist. LEXIS 17279 (N.D. Cal. 1982).

Opinion

ORDER AND OPINION GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT

SPENCER WILLIAMS, District Judge.

INTRODUCTION

This matter came before the court on May 27, 1982. After careful consideration of the briefs and arguments of counsel, the affidavits and all other matters in the record, the court denies Plaintiff’s Motion for Summary Judgment and grants Defendants’ Motions for Summary Judgment. The following is a statement of the court’s reasoning and its written order.

FACTUAL BACKGROUND

In early 1974, Stanislaus Food Products Company (Stanislaus) requested Pacific Gas and Electric Company (PG & E) to provide additional natural gas on an interruptible *116 basis. 1 PG & E stated that it would have to construct additional facilities, including gas lines and valves in order to provide Stanislaus with this service. As a condition of providing such service, PG & E required Stanislaus to agree by contract to pay for this construction and the cost of owning and maintaining the facilities for sixty months.

Stanislaus orally objected to PG & E’s demand that it pay these costs. PG & E persisted in its demand and Stanislaus, in need of the gas to operate its plant and with no other source of gas, signed a contract prepared by PG & E on PG & E’s terms.

The contract was executed on June 24, 1974 and provided that PG & E would supply Stanislaus with the requested gas service. Stanislaus was to pay PG & E a non-refundable advance of $41,181, the estimated cost of constructing the facilities, and a monthly charge of $411.81 for a period of sixty months, the estimated cost of owning and maintaining these facilities. Stanislaus paid the advance and thirty-one monthly installments.

PG & E relied on tariff provision Rule E.7 in its demand for the payments for constructing and maintaining the facilities. That rule allows special contracts, approved by the Public Utilities Commission (PUC), to require customers to pay for facilities when there are “unusual circumstances”. PG & E determined the shortage of gas could satisfy this unusual circumstance requirement.

PG & E then filed a letter requesting approval of the terms of this contract with the PUC on August 9,1974. Stanislaus was not served with a copy of this letter nor was it informed that PG & E had applied to the PUC for approval. Stanislaus did know, as it was written into the contract, that PG & E needed the PUC’s approval for any deviation from its tariff. On August 20, 1974 the PUC approved PG & E’s contract with Stanislaus.

On May 3, 1977, the PUC issued Carnation Company v. Pacific Gas and Electric Company, Decision No. 87277, which stated that the existing shortage of gas was not an “unusual circumstance” which justified a departure from the standard tariff charge. The PUC ordered PG & E to pay Carnation the charges imposed by the contract which were in excess of the standard tariff rate.

After becoming aware of this decision, Stanislaus filed a complaint with the PUC to recover the amounts paid to PG & E under the contract plus interest. Stanislaus’ complaint was submitted to the PUC on a stipulation of facts and legal issues signed by both parties. The facts were identical to those of Carnation with two exceptions: (1) Stanislaus, unlike Carnation, did not protest in writing the charges for construction and ownership levied by PG & E, and (2) the PUC in its resolution approving the terms of the contract between Stanislaus and PG & E did not reserve to Stanislaus the right to bring a complaint for reparation as it had to Carnation. The issue presented by both parties to the PUC was whether those two circumstances would destroy Stanislaus’ right to reparation.

Twenty-one months later, on September 12, 1979, the PUC issued a decision denying Stanislaus reparation. The Carnation decision was overruled as the PUC found the shortage of gas to be an “unusual circumstance”.

On October 11, 1979, Stanislaus filed a petition for rehearing with the PUC. The rehearing, set for June 3, 1980 was limited to the receipt of evidence and briefs on the issue of the existence of unusual circumstances as defined in the prior Stanislaus decision.

Stanislaus did not wait for the limited rehearing but applied to the California Supreme Court for a writ of review pursuant to Section 1756 of the California Public Utilities Code. The California Supreme Court denied its application by minute order on March 19, 1980 and gave no reasons for the denial.

*117 On May 1, 1980, Stanislaus petitioned the PUC to amend its claim for reparation to allege (a) that the PUC had denied Stanislaus due process when it approved PG & E’s application for authority to deviate from its tariff without notice and hearing and (b) that numerous other PG & E customers had been treated similarly. Stanislaus stated in its petition that these facts had not been alleged in the complaint because they were irrelevant in light of the stipulation. This petition for amendment was denied on June 16, 1981.

The limited rehearing was held on June 3, 1980. The PUC ruled in favor of PG & E and again denied Stanislaus reparation. Stanislaus did not petition for a review of this decision with the California Supreme Court, but filed the present action in this court under 42 U.S.C. § 1983. It alleged that the PUC’s approval of the contract, without a hearing, resulted in PG & E deviating from its tariff and Stanislaus being deprived of monies without due process. Stanislaus claimed there was no adequate remedy in a California state court.

1. DOES THIS COURT HAVE JURISDICTION UNDER 42 U.S.C. § 1983?

The Civil Rights Act of 1871 (42 U.S.C. § 1983) provides:

“Every person who, under color of any statute, ordinance, regulation, custom, or usage, of any state . .. subjects, or causes to be subjected any citizen of the United States or other person within the jurisdiction thereof to the deprivation of any rights, privileges, or immunities secured by the Constitution and laws, shall be liable to the party injured in an action at law, suit in equity, or other proper proceeding for redress . ... ”

Defendants argue that the PUC is not a “person” within the meaning of this statute but is an administrative agency of the State of California 2 and is, therefore, immune to suit.

Historically, judges have been absolutely immune from liability for acts done in the performance of their official functions. Pierson v. Ray, 386 U.S. 547, 553-55, 87 S.Ct. 1213, 1217, 18 L.Ed.2d 288 (1966). There is strong public interest in allowing judges the liberty to exercise their functions without the threat of intimidation by future lawsuits. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deleo v. Rudin
328 F. Supp. 2d 1106 (D. Nevada, 2004)
Lowery v. Department of Corrections
380 N.W.2d 99 (Michigan Court of Appeals, 1985)
Will v. Department of Civil Service
377 N.W.2d 826 (Michigan Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
560 F. Supp. 114, 1982 U.S. Dist. LEXIS 17279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanislaus-food-products-co-v-public-utilities-commission-cand-1982.