Standard Steel Car Co. v. McGuire

161 F. 527, 88 C.C.A. 469, 1908 U.S. App. LEXIS 4366
CourtCourt of Appeals for the Third Circuit
DecidedMay 13, 1908
DocketNo. 16
StatusPublished
Cited by7 cases

This text of 161 F. 527 (Standard Steel Car Co. v. McGuire) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Steel Car Co. v. McGuire, 161 F. 527, 88 C.C.A. 469, 1908 U.S. App. LEXIS 4366 (3d Cir. 1908).

Opinion

GRAY, Circuit Judge.

The defendant in error, who was plaintiff below and hereafter called the plaintiff, recovered a verdict in an action of trespass for personal injuries claimed to have been caused by the negligence of the plaintiff in error, which was defendant below and hereafter called the defendant. The material facts of the case, as disclosed by the record, are as follows:

Defendant was engaged in the manufacture of steel cars, at Butler, Pa. Plaintiff was an employe of McClintock Marshall Construction Company, an independent contractor engaged in building for the defendant an addition to its shop. The original shop, which was of very large dimensions, was as to its frame at least, constructed of iron, as was also the addition under course of construction, one side of the old shop forming one side of the addition. This side had been so stripped as to leave only the framework of iron, upon the top of the columns of which, iron trusses in sections about 24 feet long by 9 feet deep were being placed, the columns-of the old building serving also for that side of the new.- These Columns were 50 feet in height. The trusses were raised to the top of the column, and temporarily attached, but had to be riveted, which was done by the use of pneumatic tools, the compressed air for which was furnished by the defendant. Ag-ainst the inside of these columns, on both sides of the shop, were placed runways, which were about 12 inches in width, and on which w,ere tracks carrying trucks at either end of traveling cranes. These runways were 25 or 30 feet from the .ground, and as the building was some 1,800 feet in length, there were several of these cranes in use.

The contractor erecting the addition referred to, had two gangs of four men each engaged in riveting the trusses to the tops of the columns, each gang working independently of the other. In the prosecution. of their work, it was necessary for the men to stand upon a scaffolding-. This scaffolding, which was about the length of the truss, say 24 feet, was constructed with what were called needle beams, or sticks of that length, suspended from the top of the truss by ropes, and upon which the'floor of the scaffold was laid. When so suspended, the scaffold was 12 feet or more from the'top of the crane runway, which lay directly underneath it and'against the columns upon which the work was being done. When the work of fastening one section of the truss was. finished, it. was necessary to move further on to the adjoining space between two columns, to fasten another. For this purpose, two of the men, during the five days they had been so employed, would drop down onto the crane runway,- and the scaffolding sticks were lowered with the ropes by the two men who remained on the bottom.strut of the truss. The topes were then- dropped and coiled' up by the men on the runway, and carried with the scaffolding sticks [529]*529along to the next truss, where the rope was thrown up to the men on the truss, and the scaffolding sticks hoisted into place.

This was not only the obvious and convenient method of proceeding with the work, but no other seemed to have suggested itself, that would not have involved much trouble and great delay in the prosecution of the work in hand, and it was in evidence that defendant’s superintendent was on the floor of the mill, from where he could and did observe, without objection, this method of moving the scaffolding. The scaffolding had been so moved several times a day for the five days that this work had been going on. During this time, it' happened more than once that the crane moved along the runways at a time when the plaintiff and another workman were walking thereon, while engaged in making one of these movements of the scaffolding. In each case, they were warned of the approach of the crane by several distinct and loud signals from a bell controlled by the crane operator. On the day of the accident, however, while plaintiff, together with his co-employé, was carrying one of these needle beams along the runway from one truss to the other, the crane approached without any signal being given by bell or otherwise, and without warning from any one, and struck and ran over the plaintiff, who had one end of a needle beam on his shoulder, with his back turned from the direction in which the crane was coming. Plaintiff testifies that, after getting down on the runway, before beginning to move the scaffold, he looked up and down the runway to see if it were clear. The crane in question was operated by a boy stationed in a cage hanging from the end of the crane on the opposite side of the mill to that where the plaintiff was working. It was in evidence on the part of defendant, that printed instructions were given to its own workmen not to go upon the crane runways, but no such instructions or other warning in this respect were given to the contractor or to his employes engaged in doing this work for the defendant.

It was also testified, by the boy who operated the crane from the cage hanging below it on the opposite side of the mill, that he had general instructions to look out for the defendant’s employés at work upon the floor of the mill below him, but was not instructed to look out for those engaged on the trusses, and who might be oil the crane runway; that at the time of the accident he was watching the men on the gound, and not thinking of giving any warning to anybody else. “1 wasn’t thinking of giving any warning to anybody else but the men on the ground.” He also testified that he did not sound the bell at the time of the accident, which on previous occasions had given warning of the approach of the crane to those on the runway. There was testimony tending to show that the work upon which plaintiff was engaged was done in the presence of a superintendent and general manager of defendant, and that the scaffolding had been moved in the manner described about 12 times. It is not in dispute that this use of the crane runway by the men when moving the scaffolding, was known to those in control of defendant’s mill, or that no protest or objection on their part was made thereto. There was certainly testimony tending to show acquiescence on the part of the defendant, in this use of the crane runway, for the purpose and in the manner described, and [530]*530also that any other method of moving the scaffolding would have been exceedingly inconvenient, if not impracticable. At the conclusion of plaintiff’s testimony, defendant moved for a nonsuit, which was refused, and before the case was submitted to the jury, a request for binding instructions was submitted by defendant’s counsel, which was also refused.

The principal assignment of efror is to the refusal of the court to charge the jury that, under the pleadings and evidence in the case, the verdict must be for the defendant. Several of the other -assignments of error may be grouped under this first assignment. We have therefore carefully considered all the evidence in the case and summarized it as above.

We agree with the learned judge of the court below, that the method of moving the scaffolding from one truss to another, had been adopted by the contractors in the necessary discharge of their work, in the presence of the superintendent' and by what, under the testimony must be considered the express permission of the corporation itself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reboni v. Case Brothers, Inc.
78 A.2d 887 (Supreme Court of Connecticut, 1951)
Thibeault v. Boston Towboat Co.
28 F. Supp. 152 (D. Massachusetts, 1939)
McHugh v. First Huntington National Bank
191 S.E. 844 (West Virginia Supreme Court, 1937)
Hozian v. Crucible Steel Casting Co.
9 N.E.2d 143 (Ohio Supreme Court, 1937)
Henry W. Cross Co. v. Burns
81 F.2d 856 (Eighth Circuit, 1936)
Pennsylvania Utilities Co. v. Brooks
229 F. 93 (Third Circuit, 1916)
Kwiechen v. Holmes & Hallowell Co.
118 N.W. 668 (Supreme Court of Minnesota, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
161 F. 527, 88 C.C.A. 469, 1908 U.S. App. LEXIS 4366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-steel-car-co-v-mcguire-ca3-1908.