Standard Stamping Co. v. Hemminghaus

57 S.W. 746, 157 Mo. 23, 1900 Mo. LEXIS 2
CourtSupreme Court of Missouri
DecidedJune 12, 1900
StatusPublished
Cited by2 cases

This text of 57 S.W. 746 (Standard Stamping Co. v. Hemminghaus) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Stamping Co. v. Hemminghaus, 57 S.W. 746, 157 Mo. 23, 1900 Mo. LEXIS 2 (Mo. 1900).

Opinion

GANTT, P. J.

This is an appeal from a judgment, of the circuit court of the city of St. Louis on a verdict in be[27]*27half of defendants. The action was brought on a bond for the performance of a builders’ contract whereby defendants undertook to and did build a five story factory building in the city of St. Louis, on the northwest corner of Second and Chambers streets.

The substantive portion of the petition is as follows: “That a certain clause of the specifications, which were part of the contract, provided that ‘the first floor over the cellar to he laid with best quality white oak, two inches thick, tongued and grooved, flooring laid down level, with close joints, and securely spiked with twenty penny spikes to each joist; balance of first floor of factory and warehouse to be laid with two inches thick, best quality, white oak, dressed to an even thickness, all laid down level, with close joints, and well spiked with twenty penny spikes to each support; every joint of floor to be broken and flooring to be four and one-half inches wide and under.’

“Another clause required ‘all materials to he of the best of their respective kinds.’
“That defendants did erect the buildings so contracted for, but not in accordance with said plans and specifications, by not using the best materials of their respective kinds in constructing the five floors of the building- that, in laying the first floor over the cellar, they did not use the best quality of white oak, two inches thick, tongued and grooved flooring, nor lay the same down level, with close joints, and securely spiked with 20 penny spikes to each joist. That said floor was laid while green; has since shrunk and warped, so that it is rough, not level, and has cracks of great width and length; that, in the portion over the cellar, one can see through the floor, and all the balance of the first floor of the factory and warehouse is not laid with two inches thick, best quality of white oak, dressed to an even thickness, laid level, with close joints, well spiked with 20 penny spikes to each [28]*28support, but was laid while green, has warped and shrunk, leaving cracks and crevices, is rough and uneven, making inclines therein, and rendering it unfit for the purposes of its construction. That, on all the first floor, the ends project from the general level; •& large number of joints are not broken and many pieces are more than four and one-half inches wide, and not of even two-inch thickness after dressing. That these defects were latent, not visible, nor open to inspection, and could not have been known, nor were they known to plaintiff at the time of laying the floor, or completing said building, or making the final payment, but only became visible subsequently; that the building has never been accepted by the owner with knowledge of said defects, nor were the terms of the contract waived.”

Plaintiff also, alleged performance of the contract on its part, and prayed judgment on the bond for $3,000, on account of the alleged breach.

The answer to this amended petition admitted the execution of the bond and contract, but denied that the latter is fully set forth in the petition. Affirmatively, the answer averred, that, under said contract, all the work and materials to be furnished by defendant should be so furnished to the satisfaction of the superintending architect of plaintiff, who was by the contract made the agent of plaintiff in the erection of such improvements. That said superintendent was thereby expressly vested with full power and authority to reject any work or material which might not be in accordance with the letter and spirit of the contract, provided he should notify defendants of his objections at the time the work or materials were being furnished. That all work and material was furnished under the superintendence and direction of Gerhard Becker, plaintiff’s architect, including all the flooring now complained of. That all the flooring was dully submitted to the inspection and approval of said archi[29]*29tect, and only after bis express approval was tbe same incorporated into tbe building, at great expense. Tbat after completion of tbe building, plaintiff formally accepted tbe same and tbe architect fully approved and accepted tbe entire improvements, and defendants gave up possession thereof in consideration of sucb approval.

Tbe reply admitted tbe contract as pleaded, but denied tbe legal effect as averred. Also denied approval of tbe material in question, and averred tbat tbe last payment was made by plaintiff, upon promise of defendants to make sucb additions, alterations or repairs as would be satisfactory to plaintiff if it was discovered later tbat tbe building was not erected according to contract. Tbe cause was tried before Judge Klein and a jury.

Tbe contract was read in evidence and contained tbe clauses set out in tbe petition, and among other provisions tbe following:

“Tbe entire balance of the work to be in accordance with tbe drawings, plans, elevations and specifications furnished by tbe superintending architect, and adopted for said building which are hereto annexed and made a part of this contract. And said superintending architect shall be tbe agent of the party of tbe first part in tbe erection of tbe building and improvements herein named.And tbe said superintendent shall have full power and lawful authority to reject the whole or any part or portion of said material or work which may not be in strict accordance with tbe letter and spirit of these presents; provided, tbe said superintendent notifies tbe parties of tbe second part of bis objections to tbe work and material at the time same are being furnished.Payments to be made as tbe work progresses, as follows: $5,000 when tbe first floor joist is laid and rubble masonry is completed; $5,000 when tbe second floor joist is laid; $5,000 when tbe third floor joist is [30]*30laid; $5,000 when the fourth floor joist is laid; $5,000 when the fifth floor joist is laid; $9,000 when the roof is on, and the balance of $12,000 when the buildings and all work connected with same is completed. And after the completion of said building, according to contract, if payment of the amount due from party of the first part to parties of the second part be not made within ton days after demand for same, then, in ease said parties of the second part shall have recourse to legal process to collect said amount due from said party of the first part, there shall be allowed by the court trying said cause a reasonable attorney’s fee in favor of parties of the second part.It shall be the duty of said superintendent, upon any payment becoming due said parties of the second part, to give orders on the owner for the payment of same, duly signed and sealed by the parties thereto.”

It was further shown that the building has a front on the west line of Second street of 187 feet by 14-7 feet on Madison street. Under the corner of the building for a space of sixty feet each way was a cellar nine feet deep, the bottom of which was left in its natural state except a covering of cinders. Over the whole of this cellar was the tongued and grooved white oak flooring and in the corner an office about twelve feet square partitioned off and covered with oil cloth. The remainder of the first floor was composed of the ungrooved white oak plank, dressed on top, two inches thick and nailed to sleepers five inches square which lay next to the unexcavated ground, the spacing between the sleepers being filled with a mixture of cinders and cement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruton v. Sellers & Marquis Roofing Co.
168 S.W.2d 101 (Missouri Court of Appeals, 1943)
City St. Improvement Co. v. City of Marysville
101 P. 308 (California Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
57 S.W. 746, 157 Mo. 23, 1900 Mo. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-stamping-co-v-hemminghaus-mo-1900.