Standard Oil Co. v. Jasper County

187 S.E. 307, 53 Ga. App. 804, 1936 Ga. App. LEXIS 402
CourtCourt of Appeals of Georgia
DecidedJuly 15, 1936
Docket25218
StatusPublished
Cited by3 cases

This text of 187 S.E. 307 (Standard Oil Co. v. Jasper County) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Oil Co. v. Jasper County, 187 S.E. 307, 53 Ga. App. 804, 1936 Ga. App. LEXIS 402 (Ga. Ct. App. 1936).

Opinion

Stephens, J.

The Standard Oil Company of New Jersey, on January 16, 1934, brought an action against Jasper County and its county commissioners for the purchase-price of certain gasoline sold by the plaintiff to Copeland-Wey Incorporated, and used by the latter in the construction of a State aid highway running from Monticéllo in Jasper County to the county line in the direction of Covington, Georgia. The petition was in seven counts, of which only a few allegations need be stated. The first count alleged an indebtedness of $2832.99; that in September, 1931, a contract was made between the State Highway Department and Jasper County for the construction of projects numbers 193-A and 649-A, the county agreeing to furnish and deliver all the material and to perform all the necessary work; that the county procured CopelandWey Incorporated as contractor to perform certain work and to furnish material for it; that the plaintiff furnished to the contractor certain material used in the construction of the road to the amount of $2831.99; that payment was demanded of the contractor, which refused pay and informed the plaintiff of its inability to pay; that the contractor was insolvent; that the county did not take from the contractor the bond required by the act of August 19, 1916 (Ga. L. 1916, p. 94; Code, § 23-1705); that the petitioner had demanded payment, which the defendants refused; that the plaintiff would sustain loss in said sum because of the failure to take the bond required by the act of 1916 (Code, §§ 23-1704, 23-1705); that the contractor had completed its work, and the amount sued for was due; and that the petitioner had filed with the defendant notice of its claim within twelve months from the time the same became due and payable and within twelve months from the final completion of the work. The second count contained the same allegations as count 1, except that the amount claimed was $1562.99, and there was an allegation that the defendants received the benefit of the material making up the account, and used the material to improve its roads and highways; and that it would be a fraud on the plaintiff not to hold the defendants liable for the material so used by it. Count 3 contained, [806]*806the same allegations as count 2, except that the amount claimed was $4365.98, and it was alleged that the contractor finished the contract on February 21, 1933, and that the plaintiff agreed with the contractor that the purchase-money was due and payable when the contract was finally completed and accepted. Count 4 alleged that the defendants were indebted to the plaintiff on an open account shown by attached exhibits, in the sum of $4365.98, of which amount exhibit A showed material furnished to and used by the defendants on project No. 193-A to the amount of $2832.99, and exhibit B showed material used in project No. 649-A to the amount of $1532.99. Other allegations were substantially the same as in count 2. Count 5 was like count 4, with the additional allegation that the material sued for was sent to Monticello, Jasper County, in the name of Copeland-Wey Incorporated, by the instructions and at the request of the defendants. Count 6 alleged the furnishing and use of the material as in previous counts, and that under the terms of the agreement between the Highway Department and the county the latter agreed to furnish the labor for the construction of the project, and not to sublet any part of the contract; that the defendants violated the contract and hired Copeland-Wey Incorporated to "shoot” the asphalt used on the project, and for that purpose Copeland-Wey Incorporated was the agent of Jasper County; that Copeland-Wey Incorporated carried out the work of "shooting” or pouring the liquid asphalt used in the project which was completed and accepted by the Highway Department on February 21, 1933. Count 7 was largely a repetition of count 6, with more extended allegations that Copeland-Wey Incorporated acted as agents of the county in purchasing the asphalt. Every count alleged presentation of the claim to the defendant within twelve months from the time it became due and payable and within twelve months from the completion of the work.

The plaintiff amended its petition by substituting the figures “679-A” for " 649-A,” and by adding to each count a new paragraph which alleged that the material was used on a paved road beginning at Monticello, Georgia, and extending to the Newton County line, a distance of 13.269 miles, on State route 11 of the highway system of Georgia, and forming one complete paved road. To this amendment were attached copies of the contracts between [807]*807Jasper County and the Highway Board, and of certificates showing completion and acceptance of part of the work on February 21, 1933, and of another part on September 1, 1933, and of another part on September 11, 1933. This amendment also restricted the principal amount sued for in every count to $2832.99. Another amendment added to every count a paragraph which alleged that the original contract between the plaintiff and Copeland-Wey Incorporated as to the time of payment set out in paragraph 2 of the contract was mutually disregarded by both parties under the Code, §§ 20-116, 38-507, and it was verbally agreed between the parties that item 2 of the original contract would not be binding on either of them, but that full payment for the asphalt was to be made at the time that Copeland-Wey Incorporated completed all of its projects in Jasper County, and when the same were finally completed and accepted, and final estimates paid to Copeland-Wey Incorporated, and in the meantime said company would not be sued.

The defendants answered all counts with general denials of liability, and, as to counts 1 and 2, with a denial of any necessity for taking bond from Copeland-Wey Incorporated, because there was no valid and binding contract between Jasper County and said contractor, and a denial that the plaintiff had suffered loss by failure of the defendants to comply with the act of 1916. The answer to each count was amended by adding a paragraph which alleged that the right of action of the plaintiff, if any it ever had, accrued or became payable more than one year before the presentation of the claim and more than one year before the filing of the petition, and therefore it was barred. The case was referred to an auditor, who reported in favor of the defendant on the ground that the claim was barred by the statute of limitations. To this report the plaintiff filed exceptions of fact alleging that the auditor’s finding was contrary to law and to the evidence and without evidence to support it. On the trial of the exceptions the court directed a verdict in favor of the defendants. The plaintiff excepted.

The evidence need not be detailed. There is no conflict as to the facts which must determine the decision of the case. Jasper County made certain contracts with the Highway Department, as alleged in the petition. The county in May, 1931, made a con[808]*808tract with Copeland-Wey Incorporated, whereby the latter agreed to furnish the necessary asphalt and to heat, haul, and apply it in the construction of the road for a certain price per gallon. Copeland-Wey Incorporated, on May 29, 1931, made a contract with Standard Oil Company of New Jersey to buy not exceeding 600,000 gallons of asphalt during the period of twelve months from May 29, 1931, to May 29, 1932, the agreement containing a provision that payments should be made by the buyer “thirty days after date of invoice.” The asphalt for the price of which this suit was brought was shipped to Copeland-Wey Incorporated and was used on the road in April and May, 1932. On November 4, 1932, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelly Energy Systems, Inc. v. Board of Commissioners
396 S.E.2d 498 (Court of Appeals of Georgia, 1990)
United States Fidelity & Guaranty Co. v. Rome Concrete Pipe Co.
348 S.E.2d 83 (Court of Appeals of Georgia, 1986)
Monk v. General Motors Acceptance Corp.
193 S.E. 466 (Court of Appeals of Georgia, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
187 S.E. 307, 53 Ga. App. 804, 1936 Ga. App. LEXIS 402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-oil-co-v-jasper-county-gactapp-1936.